  Status of commissioning, report also here plots are reports., Page 9 of 13  Not logged in ELOG logo
ID Date Authordown Status Type Category Location Title Text Attachments
  145   Wed Sep 7 18:57:20 2022 Manar AmerFixedreportlasers and opticsOptical roomTelescope / amplifier outputWe increased the power of the amplifier
up to 10 W to see if there is a change in
the beam shape at the injection point or
  
  146   Wed Sep 7 18:58:03 2022 Manar AmerFixedreportlasers and opticsOptical roomLocking Amplifier with Cavity Today we managed to observe the fundamental
mode and stabilize the scan on it until we
improved the alignment enough.
 20220907_00mode.jpg20220907_00mode_diameter.jpgScreenshot_2022-09-07_0_174654.pngScreenshot_2022-09-07_2_182520.png 
  147   Thu Sep 8 11:16:40 2022 Manar AmerFixedreportlasers and opticsOptical roomLocking Amplifier with Cavity Today, we played on the CEP but using the
I-tune input of the Menhir Laser (+/- 5V
maximal range).
  
  148   Thu Sep 8 13:39:03 2022 Manar AmerFixedreportlasers and opticsOptical roomLocking Amplifier with Cavity We played on the CEP using the USB command
"id0=xxxxx" of the Menhir.

we put id0=48650 and we improved
 Screenshot_2022-09-08_0_133245.png 
  149   Thu Sep 8 14:58:51 2022 Manar AmerFixedreportlasers and opticsOptical roomLocking Amplifier with Cavity We managed to lock the cavity by adding
the AOM , but the lock is still difficult
to stabilize.
 Screenshot_2022-09-08_2_144338.png 
  150   Thu Sep 8 18:28:51 2022 Manar AmerFixedreportlasers and opticsOptical roomLocking Amplifier with Cavity We wanted to increase the power of the
amplifier to measure the transmission output
at M2,
  
  151   Fri Sep 9 11:50:17 2022 Manar AmerFixedreportlasers and opticsOptical roomLocking Amplifier with Cavity We locked the cavity, and it is stable
using the Transmission,

the high frequency that we thought
  
  152   Fri Sep 9 12:45:19 2022 Manar AmerFixedreportlasers and opticsOptical roomLocking Amplifier with Cavity image of the lock with Coupling of ~ 60%

 

 Screenshot_2022-09-09_0_120737.png 
  153   Fri Sep 9 12:49:44 2022 Manar AmerFixedreportlasers and opticsOptical roomLocking Amplifier with Cavity Alignment was improved to ~ 1.2 V on the
photodiode.

Only the second stage was on with
  
  154   Fri Sep 9 14:44:35 2022 Manar AmerFixedreportlasers and opticsOptical roomPower storage In CavityWe start of power output from amplifier
of 1W with only the first and second stage
on then we start with the third stage power
  
  155   Fri Sep 9 15:47:46 2022 Manar AmerFixedreportlasers and opticsOptical roomPower storage In CavityAt transmission power of 42 mW, coupling
60%, we see fundamental mode with a degeneracy

The D-shape motors were moved to
 Transmission_after_S2.jpg 
  158   Mon Sep 12 16:27:14 2022 Manar AmerFixedreportlasers and opticsOptical roomPower storage In CavityPower increased in the amplifier

reflective filters added at the
transmission point to be able to have signal
  
  159   Mon Sep 12 17:00:35 2022 Manar AmerFixedreportlasers and opticsOptical roomPower storage In Cavityat max stage we reached at 2.5
A on the diodes we have

8000 gain , coupling ~
 00mode_higer.jpg00mode_Removed_higer.jpg 
  160   Mon Sep 12 18:49:42 2022 Manar AmerFixedissuelasers and opticsOptical roomDamage on mirror surface Following the storage of ~ 50 kW inside
the cavity and a sudden drop in transmitted
power from the cavity 
 image001.jpgimage002.jpgimage004.jpg 
  161   Mon Sep 12 18:50:57 2022 Manar AmerFixedissuelasers and opticsOptical roomDamage on mirror surface Tomorrow will try to shift the injection
mirror to avoid hitting the damaged spot.

 
  
  162   Tue Sep 13 19:26:27 2022 Manar AmerFixedreportlasers and opticsOptical roomDamage on mirror surface After discussing, we have decided against
shifting the mirror to avoid the time lost.

We changed the injection mirror
  
  163   Tue Sep 13 19:31:14 2022 Manar AmerFixedreportlasers and opticsOptical roomliPower storage In CavityAfter changing the mirror M1 and cleaning
the 2 mirrors

They were placed in the cavity
 Screenshot_2022-09-13_0_184445.png 
  164   Wed Sep 14 16:16:08 2022 Manar AmerFixedreportlasers and opticsOptical roomPower storage In CavityThe cavity was locked under vacuum, coupling
is approximately < 10%

The lock was relatively easy and
 High_Finesse_sign_on_transmission_.jpgScreenshot_2022-09-14_0_161520.png 
  165   Wed Sep 14 17:21:59 2022 Manar AmerFixedreportlasers and opticsOptical roomPower storage In CavityWe improved the lock using the alignment,
polarization and CEP , the maximum we got
was ~ 12% coupling
 Screenshot_2022-09-14_0_161520.png 
  166   Fri Sep 16 15:56:45 2022 Manar AmerFixedreportlasers and opticsOptical roomDamage on mirror surface a better image of the damaged spot, image
taken with the arrow for the reflective surface
facing the other direction (image shows position)
 M1_mirror_on_Microscope_stand0.jpgM1X_front_min_zoom.jpgM1X_front_max_zoom.jpgM1X_front_damaged_spot_max_zoom.jpg 