  Draft   Tue Oct 4 17:34:09 2022 Entered by Nicolas Delerue from 134.158.88.175 on Tue Oct 4 17:33:52 2022 Shift summary  Planning shift Thursday 6th October - Study beam position on SST and BPM vs
iris size / TL/BPM.01

- Start AcQAttrManager
  
  Draft   Wed Oct 5 19:02:28 2022 VK, VM, HG,IC, AL      Shift started with machine receipy from
Monday .

Scan parameters, injection to find
  
  Draft   Thu Oct 27 11:12:33 2022 Entered by Nicolas Delerue from 80.119.21.73 on Thu Oct 27 11:12:17 2022Under ProcessShift summary  Programme prise de donnĂ©e 28/10  

 

===
  
  Draft   Fri Jan 13 09:45:14 2023 ND/VK/IC/KD/HG/MJUnder ProcessShift summary  Prise de donnee 13/01 Mise en chauffe

9:45 Cyclage aimants

9:48 Demarrage
 scan_charge_phase_min_0.0_max_360.0_9_54_10.pngscan_charge_phase_min_190.0_max_230.0_9_54_54.png2023-01-13_09_58_47_li_dg_sst_01-ccd_01_log_scale_False_despeckle_False_Auto_scale_True.png2023-01-13_10_01_07_tl_dg_sst_01-ccd_01_log_scale_False_despeckle_False_Auto_scale_True.png 
  Draft   Wed Mar 8 11:45:46 2023 Entered by Marie Jacquet from 134.158.205.47 on Wed Mar 8 11:45:31 2023    I-dipole vs X_TLBPM02 - Mesures/Simul (suite elog 28 fev) Tue Feb 28 08:48:29
2023

8H50-demarrage chiller et chauffage
  
  Draft   Tue Apr 4 15:21:51 2023      , entered from 134.158.195.141 <p>12h10: Mise en chauffe modulateur, laser
et chiller + PA</p>
  
  Draft   Tue Oct 10 13:46:06 2023 KD MJ Shift summary        
  Draft   Fri Nov 15 07:56:03 2024 IC, VK, VM, ND Shift summary  Ring studies, MRSV 07h50 Start ThomX

09h20 HV is 'ON'

09h25 HV  1215 V
 36x 
  Draft   Mon Feb 17 11:00:01 2025 VM, IC, VKUnder ProcessShift summary  70 MeV WP 10h30 Start beam

Since Friday evening the problem
to store the beam at 70 MeV. There is 1 turn
  
  Draft   Tue Oct 21 12:29:35 2025 HG, DN. VM, MJ      11h40 Thomx warm-up

12h35 HV is ON

12h40 HV 1215 V
 mrsv_2_positions_fente.png 
  Draft   Fri Oct 24 08:33:30 2025 Entered by Super Team from 134.158.195.141 on Fri Oct 24 08:33:07 2025Under ProcessShift summary    08h32 Warm-up ThomX: Modulator, Laser,
Fridge

08h37 Chilers were started, cycling
  
  Draft   Tue Oct 28 08:40:22 2025 Entered by Super Team from 134.158.195.141 on Tue Oct 28 08:40:06 2025Under ProcessShift summary    08h40 Warm-up ThomX: Modulator, Laser,
Fridge

08h45 Chillers were started, cycling
 Screenshot_from_2025-10-28_11-48-31.pngScreenshot_from_2025-10-28_11-47-12.pngScreenshot_from_2025-10-28_11-46-55.pngScreenshot_from_2025-10-28_15-34-03.png 
  Draft   Wed Nov 5 12:50:55 2025 Entered by Super Team from 134.158.195.141 on Wed Nov 5 12:50:37 2025      Matin :

Soucis synchro :
- Nicolas les a redémarré
 Screenshot_from_2025-11-05_17-49-33.pngScreenshot_from_2025-11-05_17-51-14.pngScreenshot_from_2025-11-05_17-50-44.png 
  Draft   Thu Jan 15 09:09:37 2026 ICUnder ProcessShift summary  Ring studies 08h56 Warm-up ThomX: Modulator, Laser,
Fridge
Chillers were started, cycling all
 Screenshot_from_2026-01-15_11-04-16.pngScreenshot_from_2026-01-15_11-33-33.pngRi_C1_Quads_is_off_Screenshot_from_2026-01-15_18-19-14.pngScreenshot_from_2026-01-15_16-42-27.pngScreenshot_from_2026-01-15_17-36-28after1LOCO.png 
  Draft   Fri Jan 16 08:29:33 2026 IC, VM, NDUnder ProcessShift summary    08h29 Warm-up ThomX: Modulator, Laser,
Fridge
Chillers were started, cycling all
 Screenshot_from_2026-01-16_18-28-24.pngScreenshot_from_2026-01-16_13-22-12.pngScreenshot_from_2026-01-16_13-23-01.pngScreenshot_from_2026-01-16_13-31-16MODEl.pngScreenshot_from_2026-01-16_16-02-15LOCO_1it.png 
  Draft   Tue Jan 20 08:35:56 2026 VM, ND, VCUnder ProcessShift summary    08h35 Warm-up ThomX: Modulator, Laser,
Fridge
08h41 Chillers were started, cycling
  
  Draft   Mon Feb 23 09:43:36 2026 IC    Ring studies 9h40: mise en chauffe (chillers/frigo,
modulateur, cyclage)

HV ON
  
  Draft   Thu Feb 26 08:18:00 2026 IC, VM      08h15: mise en chauffe en remote (frigo/chillers,
laser, modulateur, cyclage)

08h15: mise en chauffe en remote
  
  Draft   Fri Mar 6 09:00:45 2026 VMUnder ProcessShift summary    09h00 Warm-up ThomX: Modulator, Laser,
Fridge

09h05 Chillers were started, cycling
  
  Draft   Mon Mar 9 12:55:30 2026 Entered by Super Team from 127.0.0.1 on Mon Mar 9 12:55:16 2026    Restart after strange last shift  12h55 : Vacuum level OK after TRIG ON
13h00 : Laser ON : no spot on screen
put last motor positions (2266 &&
  