Entry   Entered by Super Team from 127.0.0.1 on Thu Mar 19 07:46:39 2026; , entered from 127.0.0.1 
7h45: mise en chauffe en remote (frigo/chillers, laser, modulateur, cyclage)

8h46 The photocathode laser image on the camera is very weak, I can't initiate feedback. Help needed.

08h56 HV is on
Entry   IC, VM; Work on orbit at 70 MeV for X rays xorbit70MeV_Xrays_20032026.pngyorbit70MeV_Xrays_20032026.pngScreenshot_from_2026-03-20_15-49-43.pngY_orbit61.5MeV4Xrays.pngX_orbit61.5MeV4Xrays.png
7h20: mise en chauffe en remote (frigo/chillers, laser, modulateur, cyclage)

08h55 HV is ON

10h07 70 MeV. Beam is in the ring with RF 100 kV, phase -37.5 dg. The recipe_recipe_LI_TL_RI_good_20260318_16_17_14.txt loaded, linac steerers
Entry   KD, VM, MJ, RC; shift du 24 mars 2026 HorOrbit_vs_Att.png
8h05 : mise en chauffe en remote (frigo/chiller, modulateur, laser, cyclage)

09h17 HV is ON

11h36 Mod. on standby
Entry   Entered by Super Team from 127.0.0.1 on Wed Mar 25 07:28:09 2026; Ring studies 
7h30 : mise en chauffe en remote (frigo/chiller, modulateur, laser, cyclage)

08h40 HV ON

==> 50 MeV, Manual phase shifter value set to 3209. Sect. temperatute set to 30C at clarinette, (consigne = 29.2C).
Entry   IC, VM, DN, MJ;  MRSV_Size_vs_LaserPhase.pngHorOrbit_vs_LaserPhase.pngMRSV17h38.pngDispersionAfterLOCO20260326_16h54.png20260326_18h24_TL_Dispersion.png
7h37 : mise en chauffe en remote (frigo/chiller, modulateur, laser, cyclage)

08h57 HV is ON

==> 70 MeV, F=500.031645 MHz
Entry   MJ KD IC VM DN RC; ENERGY-ANGLE 70 MeV - 27 mars 2026 droma_70_MeV.png
** Programme : Energy-Angle 70 MeV

7h40 : mise en chauffe en remote (frigo/chiller, modulateur, laser, cyclage)
08h57 HV is ON
Entry   KD; shift du 31 mars 2026 
7h55 : mise en chauffe en remote (frigo/chillers, laser, modulateur, cyclage)

==> vérifier la pression SF6 avant de commencer.  2461mB

HV On
Entry   KD MJ; shift du 31 mars 2026 : MONO 70 MeV + spectres 61.5 MeV Droma_61p5_MeV_2026-03-31_17-41-07.pngDectris_centre_faisceau_2026-03-31_17-19-05.png
/!\ fort impact du moteur Rsample de la ligne X sur la cavité CFP (obligé de le mettre off)

*** Prise mesure Monochromateur ***

* angle initiale mono : Ry_mono(0) = -0.1° (ajouté aux valeurs d'angles pour la position moteur)
Entry   KD MJ RC DN VK; 1e avril 2026 - Scan Energy-Angle 61.5 MeV orbite_61p5_MeV_2026-04-01_19-24-56.png
7h40 : mise en chauffe en remote (frigo/chillers, modulateur, laser, cyclage)

==> SF6 à remplir avant démarrage. 2.805 bar

09h04 HV is ON
Entry   IC,VM;  
7h50 : mise en chauffe en remote (frigo/chillers, modulateur, laser, cyclage)

08h58 HV is ON

recipe_recipe_LI_TL_RI_all_20260326_09_09_20.txt loaded
Entry   IC,VM, ND; , entered from 127.0.0.1 
7h50 : mise en chauffe en remote (frigo/chillers, modulateur, laser, cyclage)

9h30 HV is ON

recipe_recipe_LI_TL_RI_all_20260402_14_37_41.txt loaded
Entry   IC,VM, KD, DN, MJ; MONO 61.5 MeV - 07 avril 2026 
7h50 : mise en chauffe en remote (frigo/chillers, modulateur, laser, cyclage)
09h30 HV is ON

10h23 Energy = 61.5 MeV, Laser Phase 39 dg., Sect. Phase 225 dg., Sect. Att. 0.952 dB, I_Gun -78.1953 pC, I_Linac -122.7687 pC, I_TL -102.6104
Entry   7h50 : mise en chauffe en remote (frigo/chillers, modulateur, laser, cyclage); , entered from 127.0.0.1 
7h30 : mise en chauffe en remote (frigo/chillers, modulateur, laser, cyclage)

8h30 HV is ON

recipe_recipe_LI_TL_RI_all_20260402_14_37_41.txt loaded
Entry   IC,VM;  
8h10 : mise en chauffe en remote (frigo/chillers, modulateur, laser, cyclage)

09h12 HV is ON

recipe_recipe_TL_all_20260408_17_18_54.txt loaded
Entry   IC,VM;  
7h40 : mise en chauffe en remote (frigo/chillers, modulateur, laser, cyclage)

08h43 HV is ON

recipe_recipe_LI_TL_RI_all_20260409_17_07_05.txt loaded
Entry   IC,VM; Beam studies. preparation for 40 MeV 
8h00 : mise en chauffe en remote (frigo/chillers, modulateur, laser, cyclage)

10h Problem with modulator; It went to OFF and it does not start. Need help;

12h40 Fixed by Maher
Entry   KD MJ RC DN VK; ENERGY/ANGLE 40 MeV - 15 avril 2026 
8h05: mise en chauffe à distance (frigo/chillers, modulateur, laser, cyclage)

*** Programme : Mesure spectre angulaire @40MeV

Matin : probleme de stockage faisceau 40 MeV
Entry   Entered by Super Team from 127.0.0.1 on Thu Apr 16 07:32:14 2026; , entered from 127.0.0.1 Screenshot_from_2026-04-16_20-53-14.pngScreenshot_from_2026-04-16_20-53-34.png
7h30 : mise en chauffe en remote (frigo/chillers, modulateur, laser, cyclage)

9h00 HV is ON

10h33 Energy = 50 MeV, Laser Phase 77 dg., Sect. Phase 217 dg., Sect. Att. 2.546 dB, I_Gun -98.9021 pC, I_Linac -131.1291 pC, I_TL -120.2702
Entry   IC,VM, HG, RC, DN; beam studies. FPC.  
7h30 : mise en chauffe en remote (frigo/chillers, modulateur, laser, cyclage)

08h45 HV is on

Laser camera does not work. Help!!!
Entry   IC;  
10h30 : mise en chauffe  (frigo/chillers, modulateur, laser, cyclage)

All rondes are broken, THOMX key is turned. What is the reason of this intervention?,  There is nobody around. Jean-Noel came and helped
to solve the problems.