ID Date Authordown Status Type Category Important Subject Icon Text Attachments
  810   Thu Oct 26 09:02:33 2023 VC,SC, ND, IC, VK, CB, V LinacLI | TL | Ring Linac 8h30 Mise en chauffe

Pas d'internet sur client1
et client2
  
  824   Mon Dec 11 09:41:41 2023 VC,ND Shift summarySY Tests synchro 8H15 démarrage chiller et modulateur

Mesure synchro, cf https://elog.lal.in2p3.fr/THOMX/Synchronisation/76

Mesures utilisant la redpitaya
  
  986   Fri Dec 20 08:37:20 2024 VC,NDUnder ProcessShift summaryLinac Commissionning | Ring Commissioning Shift summary 20/12 demarrage machine 8h40

Matin: travail sur la synchro,
creation du mode "diags only"
 10x 
  935   Mon Oct 7 08:56:20 2024 VC, VM, VK, ICUnder ProcessShift summaryRing | Linac Commissionning Shift summary 8h55 démarrage chauffage Klystron

pression SF6: 2.3 bar  =>
à besoin d'etre complété
 Screenshot_from_2024-10-07_12-44-39.pngScreenshot_from_2024-10-07_12-45-12.png 
  848   Wed Feb 28 08:49:30 2024 VC, VM, VKUnder ProcessShift summaryLI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning Commintionning RING demarrage machine 8H50

Alim

EL/PS/DPI.01 demarrage à
 health_check_2024_02_28_08_50.pngScreenshot_from_2024-02-28_11-47-13.pngScreenshot_from_2024-02-28_15-34-51.pngScreenshot_from_2024-02-28_16-50-50.png 
  846   Mon Feb 26 09:07:06 2024 VC, VK, VM, IC, NDUnder ProcessShift summaryLI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning redemarage machine après élongation anneau 9H démarrage machine en mode linac

chauffage klystron ok

chiller ok
 scan_Laser_vs_RF_phase_2024_02_26_10_41.pngScreenshot_from_2024-02-26_12-13-46.png 
  1120   Fri Sep 12 09:06:59 2025 VC, ND, KDUnder ProcessShift summaryLE Shift summary 12/9/2025 8h20: mise en chauffe en remote (Laser,
modulateur, frigo/chiller, cyclage)

9:00 Redemarrage mean_std qui etait
 wc3_shutter_effect.pngwc3_steererH_scan.pngScreenshot_from_2025-09-12_15-56-50.png 
  823   Thu Dec 7 14:46:29 2023 VC, ND Shift summarySY Tests synchro Objectif: Test nouveau code CPLD

14:44 Mise en chauffe modulateur

Le code semble fonctionner =>
  
  807   Fri Oct 20 15:12:39 2023 VC, Marie Labat, NDUnder ProcessShift summaryLI | Diag Mesures pour la streak 14:12 Mise en chauffe

15:12 Faisceau

Recette 20230929_17_49_07
 signal_Cerenkov.jpg 
  1013   Tue Feb 18 08:28:36 2025 VC, KD, VM, ND, RC, MJUnder ProcessShift summaryLI | Linac Commissionning shift  demarrage machine 8h30

intervention Kicker.. 8h45 

10H30 fin intervention Kicker Ok
 Screenshot_from_2025-02-18_17-52-13.pngScreenshot_from_2025-02-18_17-51-17.pngScreenshot_from_2025-02-18_17-49-55.pngScreenshot_from_2025-02-18_17-58-05.pngScreenshot_from_2025-02-18_17-59-46.png 
  833   Wed Jan 24 08:57:25 2024 VC, IC, VK, VMUnder ProcessShift summaryLinac Commissionning | Ring Commissioning Commissioning Demmarrage machine à 8h45

IHM ThomX warm-up

8H55 Chauffage klystron, Frigo 
 10x 
  1062   Wed Apr 30 08:51:08 2025 VC, DN, MJ, IC, VMUnder ProcessShift summaryLinac Commissionning | Ring Commissioning Recherche position image camera MRSV Start chauffage 9H

There were some problems: the phase
section motor was in the wrong position,
 2025-04-30_16-23-33_MRSV_fwhm_trends.png2025-04-30_17-14-26_total_beam.png2025-04-30_17-15-03_coupe_moitie_basse.png2025-04-30_17-15-54_coupe_moitie_haute.png 
  971   Fri Nov 29 08:22:14 2024 VC, Carlos Buitrago, Sudhanshu Thakur, NDUnder ProcessShift summaryLinac Commissionning TP 29-11--2024 demarrage chauffage 8H20

test nouveau code synchro 50Hz
=> ne fonctionne pas
  
  599   Fri Oct 21 08:12:27 2022 VC VK ICUnder ProcessShift summaryRing Commissioning Commissionning 8H15 demarrage chauffage Klystron et chiller

9h15 bunker ouvert (intervention
société extérieure jusqu'à
  
  568   Wed Sep 28 08:31:27 2022 VC VK AM IC & allUnder ProcessShift summaryRing Commissioning Shift du 28/09/2022 icon14.gif AM :

git pull sur $HOME_IHM


pression vanne vide : 8
 Screenshot_from_2022-09-28_19-05-00.pngScreenshot_from_2022-09-28_19-08-26.pngfirst_turn28092022.png 
  419   Fri Mar 25 08:22:18 2022 VC SC HG NDUnder ProcessLinacDiag | Linac Commissionning commisionning Charge et OTR  demarrage Modulateur 8h20

9h15 temp chiller ok

energie laser 32uJ atténuateur
 12x 
  1055   Fri Apr 11 08:52:07 2025 VC SC HGUnder ProcessShift summaryLI | Linac Commissionning | Ring Commissioning shift du 11 avril  demarrage chauffage 8hh50

faisceau sur Yag 1 depuis 1heure....

le script d'alignement solenoide
 align_soir.png 
  567   Tue Sep 27 08:40:33 2022 VC SC CBUnder ProcessShift summaryLI | Linac Commissionning Shift du jour Summary:

- Mesure du jitter et de la position
relative de pulse laser PC avec la RF canon
  
  922   Wed Sep 25 08:17:22 2024 VC MJ KD HG VKUnder ProcessShift summaryLinac Commissionning Shift summary Demarrage chauffage modulateur 8h15
le chiller canon n'était
pas éteint!
 6x 
  842   Tue Feb 6 08:52:28 2024 VC MJ KDUnder ProcessShift summaryLI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning commissionning 8h45 demarrage machine

modulateur frigo ampli laser chiller
et cyclage des aimants
 7x 