1059
|
Fri Apr 18 08:23:13 2025 |
VM, IC, ND | Fixed | Problem | LI |
|
Measurements 18/4 | | 08h21 Thomx Started: modulator, frig, laser
08h27 Chillers started, cycling
all magnets |
    |
|
1067
|
Mon May 12 16:27:09 2025 |
Entered by Super Team from 134.158.195.141 on Mon May 12 16:26:53 2025 | Under Process | Linac | LI |
|
Conditionnement | | Demarrage du conditionnement :
Température : 30.90 pour
accorder le canon |
7x |
|
1073
|
Tue May 20 15:18:09 2025 |
HG, SC | Under Process | Info | LI |
|
Faisceau injecteur | | 14h : Faisceau, charge max = 200pC à
300 position attenuateur laser
15h : beaucoup de claquages dans |
 |
|
1093
|
Wed Jun 25 18:47:20 2025 |
Entered by Super Team from 134.158.195.141 on Wed Jun 25 18:47:07 2025 | Under Process | Shift summary | LI |
|
Laser position |
| New laser position :
5.041
4.448 |
|
|
1097
|
Wed Jul 2 14:45:20 2025 |
Entered by Super Team from 134.158.195.141 on Wed Jul 2 14:45:07 2025 | Under Process | Info | LI |
|
| | Vérif position laser photocathode
:
--> bouge de 1mm en Y et 0.2 |
|
|
1132
|
Thu Oct 2 08:32:08 2025 |
Entered by Super Team from 134.158.195.141 on Thu Oct 2 08:31:43 2025 | Under Process | Shift summary | LI |
|
| | 08h30 ThomX warm-up
08h37 Cycling all magnets
10h20 HV is ON |
|
|
1152
|
Tue Nov 18 11:11:33 2025 |
HG, JM, ND | Under Process | Shift summary | LI |
|
Prise de données 18/11 | | 9h Intervention laser
Intervention pour realignement
el/dg/sst.01 |
|
|
1156
|
Mon Nov 24 13:22:59 2025 |
ND + JM + HG | Under Process | Shift summary | LI |
|
Prise de données 24/11 | | 9:15 Mise en chauffe
9h30 Arrivée du SPR: testsSSI
ce matin => pas de faisceau avant midi |
|
|
1191
|
Wed Feb 11 09:12:35 2026 |
VM && HG | Under Process | Shift summary | LI |
|
Linac commissioning | | 09h12 Warm-up ThomX: Modulator, Laser,
Fridge
09h21 Chillers were started, cycling |
  |
|
1192
|
Fri Feb 13 17:38:15 2026 |
Entered by Super Team from 127.0.0.1 on Fri Feb 13 17:38:00 2026 | Under Process | Shift summary | LI |
|
SHift du jour | | The code for laser alignment does not work
properly --> done by hand
H 5.244 |
|
|
1208
|
Wed Mar 11 18:12:23 2026 |
Entered by Super Team from 127.0.0.1 on Wed Mar 11 18:12:09 2026 | Under Process | Shift summary | LI |
|
Emittance vs Iris | | Some Quad scans with variying the Iris
opening.
Data : |
|
|
1240
|
Tue May 12 08:42:45 2026 |
Entered by Super Team from 127.0.0.1 on Tue May 12 08:42:31 2026 | Under Process | Other | LI |
|
manip Gplast | | Demarrage machine 8h40
pB reflechi canon... temp consigne
27.7C |
|
|
1241
|
Wed May 13 08:35:16 2026 |
Entered by Super Team from 127.0.0.1 on Wed May 13 08:35:01 2026 | Under Process | Other | LI |
|
manip Gplast | | demarrage machine 8h30
faisceau ok vers 10H
14h mesure 50 MeV |
|
|
1247
|
Tue Jun 16 13:43:30 2026 |
Entered by Super Team from 127.0.0.1 on Tue Jun 16 13:43:02 2026 | | Fix | LI |
|
| | Hello,
I short-circuit the MPS input to
modulator, we can trig modulator, the klystron |
|
|
1254
|
Mon Jun 29 08:37:27 2026 |
VC | Under Process | Problem | LI |
|
redpitaya | | Les redpitaya baie 17 'RF" ne
"communiquent" plus avec JIVE.
IL faut les redémarrer... |
|
|
992
|
Thu Jan 9 16:03:52 2025 |
ND, IC, VK, VM | Under Process | Shift summary | LE |
|
Optimisation LE | | 15h Scan extraction kicker vs EL/BPM.01.
See attached plots.
Some interferences with ring storage. |
    |
|
1120
|
Fri Sep 12 09:06:59 2025 |
VC, ND, KD | Under Process | Shift summary | LE |
|
Shift summary 12/9/2025 | | 8h20: mise en chauffe en remote (Laser,
modulateur, frigo/chiller, cyclage)
9:00 Redemarrage mean_std qui etait |
  |
|
396
|
Thu Mar 10 09:15:36 2022 |
Entered by Super Team from 134.158.195.141 on Thu Mar 10 09:15:18 2022 | Under Process | Urgent | Infra | Linac Commissionning |
|
intervention M Langlet en sous sol | | 9h : M Langlet a besoin de façon
urgente d'acceder au sous-sol.
Deverouillage de la fosse Nord |
|
|
415
|
Thu Mar 24 10:34:15 2022 |
Entered by Nicolas Delerue from 134.158.195.144 on Thu Mar 24 10:34:03 2022 | Fixed | Fix | Infra | Linac Commissionning |
|
config clefs PSS | | Operateurs: VC, SC, ND
Pour memoire, cf photo... |
|
|
877
|
Fri Jun 7 09:24:59 2024 |
Entered by Super Team from 134.158.195.141 on Fri Jun 7 09:24:42 2024 | New Solution | Shift summary | Infra | Linac Commissionning |
|
Interventions du matin | | 9h Intervention sur les filtres de la CTA
(Dalkia, Stéphane)
9h Intervention dans les sous-sols |
|