ID Date Author Status Type Categorydown Important Subject Icon Text Attachments
  1015   Wed Feb 19 17:32:30 2025 shift screw Shift summaryLI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning Rustine pour le probleme CEM kicker - ring storage - Xrays Cable ventilo kicker debranche ==> aucun
effet
Cable balise blinde ==>
 storage_et_Xrays_2025-02-19_19-01-58.pngdet2diodes_pb_voie4_2025-02-19_19-16-07.png 
  1020   Tue Feb 25 22:59:57 2025 Entered by Marie Jacquet from 88.165.97.136 on Tue Feb 25 22:59:29 2025 Shift summaryLI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning 24 -25 fevrier (visite Alberto Paola Luca) - Detecteur Photonic Science Commissioning det Photonic Science

** Depose
Dectris, mise en place Photonic, alignement
  
  1022   Wed Feb 26 22:52:03 2025 Entered by Marie Jacquet from 88.165.97.136 on Wed Feb 26 22:50:49 2025 Shift summaryLI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning 26 fevrier (visite Alberto Paola Luca) - Detecteur Photonic Science  Suite du commissioning
det Photonic Science

**
  
  1024   Fri Feb 28 00:32:21 2025 Entered by Marie Jacquet from 134.158.205.38 on Thu Feb 27 23:45:19 2025 Shift summaryLI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning 27 fevrier (visite Alberto Paola Luca)  ** Nouvelle
prise d'images pour determiner les distortions
du det :
  
  1030   Thu Mar 6 10:38:31 2025 Entered by Marie Jacquet from 134.158.205.25 on Thu Mar 6 10:37:50 2025 Shift summaryLI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning Programme de la journee : preparation des valeurs a remplir  1 : Alignement Axe
Q1-Q3 avec SCRIPT - Conditions
 Compare_Align_ALL.pngTrend_Position_Yag_Sautes.pngJauges_2025-03-06_18-47-14.png2025-03-06-Q1Q3_Q4Q5.pdf 
  1034   Wed Mar 12 16:50:29 2025 Entered by Super Team from 134.158.195.143 on Wed Mar 12 16:50:08 2025 Shift summaryLI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning Spectres X (positions fentes 2 et temps d'extraction) IP-Fente2 : 8835 mm
IP-capteur_CdTe: 10460

Calib ouverture Fentes2 : +0.1
  
  1114   Fri Sep 5 09:25:13 2025 ND-VCUnder ProcessShift summaryLI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning shift 9h15: Chauffage klystron

Reinstallation DEG 4.

9:50 Git pull:
 11x 
  1203   Thu Mar 5 13:19:22 2026 MJ VM DN RC HG Shift summaryLI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning Etudes matching icon1.gif Mesures : Spectres et taille source
X + Quads scans associées, @
  
  1250   Fri Jun 19 09:51:28 2026 IC, VMNot FixedUrgentLI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning Restart of the accelerator 09h35 Start-up modulator

09h52 Start the fridge

09h55 Start chillers
  
  1134   Thu Oct 9 08:37:45 2025 Entered by Super Team from 134.158.195.141 on Thu Oct 9 08:37:29 2025Under ProcessShift summaryLI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning Shift "du Jeudi" : VM/HG/KD/DN/RC 09h35 Warmup ThomX

09h40 Cycling all magnets

09h50 Start Chillers
 Screenshot_from_2025-10-09_16-57-23.pngScreenshot_from_2025-10-09_16-50-25.pngScreenshot_from_2025-10-09_16-50-12.pngScreenshot_from_2025-10-09_17-17-57.png 
  890   Thu Jul 25 09:15:25 2024 M ELK, SC, MO FixedLinacLI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning Conditionnement section 25/07 9h00 Mise en route modulateur

signaux RF mesurés :

avec Oscillo :
 0.7_dB_3µs_10Hz__13h04__claquage_réseau_HF.png0.3dB_3us_10Hz_16h35.png1dB_3us_10Hz_16h38.png 
  1154   Thu Nov 20 09:26:33 2025 VM, ICUnder ProcessUrgentLI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning BBA Ring Goal: Ring BBA

09h14 Unable to start thomx. Need
help. Probably problem with cooling water.
 Errors.jpegScreenshot_from_2025-11-20_14-04-53.png 
  1252   Fri Jun 26 08:27:22 2026 IC, VMUnder ProcessProblemLI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning Restart of the accelerator 08h26 Start-up modulator, laser, fridge,
chillers, cycling

09h31 Low SF6 pressure => JN
 Screenshot_from_2026-06-26_15-41-00.pngIMG-20260626-WA0001.jpgScreenshot_from_2026-06-26_16-07-50.pngScreenshot_from_2026-06-26_17-17-00.png 
  1188   Thu Feb 5 13:18:03 2026 KD, HG, VMFixedInfoLI | TL | LE | Ring | CC | Laser | Opt | MECA | SY | Vide | Electronique Laser PC status ** l'iris a été changée
et est opérationnelle

/!\
 Screenshot_from_2026-02-05_17-11-35.png 
  795   Thu Sep 21 16:16:38 2023 RC, DN, VC, NDUnder ProcessShift summaryLI | TL | LE | Ring Operations 21/09  Modulateur en chauffe avant 14h

mise en place d'une synchronisation
compatible à la génération
 scan_Laser_vs_RF_phase_2023_09_21_15_53.png 
  822   Thu Nov 23 08:51:44 2023 SC/KD AnneauLI | TL | LE | Ring Faisceau LE 8h50 Mise en chauffe modulateur

Mise en route chillers et frigo

Problème laser photocathode
  
  839   Thu Feb 1 16:30:20 2024 Entered by Marie Jacquet from 134.158.89.45 on Thu Feb 1 16:30:01 2024Under ProcessShift summaryLI | TL | LE | Ring Complement de la fin du elog 837 En complement de la fin de l'entree
elog 837 ou il est ecrit a la fin :

on
  
  937   Tue Oct 8 09:05:34 2024 ND, VC, HG, SC, MEK, VK, VMUnder ProcessShift summaryLI | TL | LE | Ring Shift summary 8/10/2024 9:10 Maher a redemarre l'ordinateur
du modulateur

9:15 Cyclage des aimants
 Screenshot_from_2024-10-08_12-47-47.pngScreenshot_from_2024-10-08_13-12-49.pngScreenshot_from_2024-10-08_13-25-19.png 
  950   Wed Oct 30 11:33:04 2024 VM, IC, VKUnder ProcessInfoLI | TL | LE | Ring   9h25 Start ThomX

11h20 HV on, linac RF OK, but there
is no laser on the cathode. Trying to fix.
 6x 
  1092   Tue Jun 24 18:33:20 2025 Entered by Marie Jacquet from 134.158.205.58 on Tue Jun 24 18:33:05 2025 Shift summaryLI | TL | LE | Ring Spectres Bazin - Config "cone en plomb" - + enregistrement trends parametres machine (e- et X) *** Spectres
des 4 Echantillons Bazin + Backgroung avec
:
 10x 