  441   Thu Apr 14 09:56:11 2022 Entered by VC/ND/SC from 134.158.195.141 on Thu Apr 14 09:55:56 2022FixedInfoLinac Commissionning Faisceau pour les diagnostics Le programme de la journée
:

- Morning: Iryna, Slava + Viktor
  
  445   Mon May 2 10:30:35 2022 Entered by JNC/VC from 134.158.195.141 on Mon May 2 10:30:21 2022FixedLinacLinac Commissionning Fermeture machine Jean Noel a fermé la fosse nord,
Elle est INONDEE, on va faire un ticket aux
infras.
  
  452   Tue May 10 10:11:37 2022 Entered by Viktor Soskov from 134.158.195.153 on Tue May 10 10:11:18 2022FixedInfoLinac Commissionning Laser status Devices:

....DIA.01-CTL.01 et LAS.01-ASP.01
fonctionnet.
  
  468   Tue May 31 09:21:02 2022 MO/SC/HG, JNC/CBFixedLinacElectronique Demarrage et faisceau 9h15 : Mise en chauffe modulateur et chiller
(SC/MO/HG)

Aujourd'hui : Alignement faisceau
 charge_phase__at_31-05-2022__10-39-33.jpg 
  490   Mon Jul 4 10:28:03 2022 Entered by SC/AG from 134.158.195.141 on Mon Jul 4 10:27:45 2022FixedLinacLinac Commissionning Changement vis des aimants Changement des vis solenoides en cours   
  499   Thu Jul 7 11:13:26 2022 Entered by Viktor Soskov from 134.158.195.153 on Thu Jul 7 11:13:10 2022FixedInfoLinac Commissionning Phototube_Signal    Phototube_2022_07_07.png 
  527   Tue Aug 23 17:26:12 2022 Entered by Viktor Soskov from 134.158.195.153 on Tue Aug 23 17:25:55 2022FixedInfoLinac Commissionning Laser status Bonjour. Laser fonctionne à nouveau
normelment. Merci Kevin et Aurélien.

Viktor.
  
  528   Wed Aug 24 12:02:36 2022 Entered by Viktor Soskov from 134.158.195.153 on Wed Aug 24 12:02:20 2022FixedInfoLinac Commissionning Laser status Bonjour,

Euv=25µJ, D=2mm, Att=400

Viktor.
  
  545   Tue Sep 13 11:49:50 2022 Entered by Viktor Soskov from 134.158.195.153 on Tue Sep 13 11:49:29 2022FixedInfoLinac Commissionning Phase Stability Bonjour, voici la stabilité de phase
laser(oscillateur)-horloge(500MHz). La phase
commence à bouger quant  linac
 13_09_2022_12H00.pdf 
  548   Thu Sep 15 09:34:23 2022 MOFixedOtherLinac Commissionning balise T3G La balise T3G était en défaut
ce matin, redémarrage du PC ( LB 9000
coté THOMX ) pour corriger
  
  549   Fri Sep 16 09:12:35 2022 Entered by Viktor Soskov from 134.158.195.153 on Fri Sep 16 09:12:19 2022FixedUrgentLinac Commissionning Shutters Laser Bonjour,

je n'arrive pas ouvrir les
shutters dans la salle laser et dans la casemate,
  
  Draft   Fri Sep 16 10:09:15 2022 Entered by Viktor Soskov from 134.158.195.153 on Fri Sep 16 09:12:19 2022FixedUrgentLinac Commissionning RE: Shutters Laser 


Entered
  
  551   Fri Sep 16 10:10:36 2022 Entered by Viktor Soskov from 134.158.195.153 on Fri Sep 16 09:12:19 2022FixedUrgentLinac Commissionning RE: RE: Shutters Laser Shutter casemate ouvert

Shutter salle laser encore fermé

  
  552   Fri Sep 16 10:11:24 2022 Entered by Viktor Soskov from 134.158.195.153 on Fri Sep 16 09:12:19 2022FixedUrgentLinac Commissionning RE: RE: RE: Shutters Laser Problème shutter résolu




  
  553   Fri Sep 16 13:39:24 2022 Entered by Viktor Soskov from 134.158.195.153 on Fri Sep 16 13:39:08 2022FixedInfoLinac Commissionning Laser status Bonjour, j'ai changé 2 miroirs
du parcous optique (2 moroirs du periscope
dans la salle laser). La distribution est
  
  555   Fri Sep 16 16:27:49 2022 Entered by Viktor Soskov from 134.158.195.153 on Fri Sep 16 16:27:35 2022FixedInfoLinac Commissionning Laser status Bonjour, voici l"énergie sur
la cathode (µJ) en fonction du diamètre
de l'iris (mm)
  
  Draft   Thu Sep 22 10:08:30 2022 Entered by Hayg Guler from 134.158.91.29 on Thu Sep 22 10:08:17 2022Fixed   , entered from 134.158.91.29     
  565   Mon Sep 26 09:58:14 2022 Entered by Viktor Soskov from 134.158.195.153 on Mon Sep 26 09:57:59 2022FixedInfoLaser | Linac Commissionning Laser status Bonjour, le shutter-linac a été
replacé, on peut le sceller maintenant
(il faut fixer une date). L'énergie
  
  572   Mon Oct 3 12:51:26 2022 Slava, Viktor M, IrynaFixedProblemRing Commissioning Check the QUADs in the ring On last Friday, we found that there is
a potential problem with QUAD 9, 10
an 12 as by switching them OFF, we obtained
  
  581   Mon Oct 10 14:44:44 2022 KD, VS, SCFixedShift summaryLI | Laser shift du 10 octobre 2022 Viktor est intervenu ce matin pour réaligner
le laser sur un autre point du chemin optique
(éviter la partie endommagée
  