HOME Prise de donnees MML Controle commande Simulations Notes Hardware Ligne X Laser Interaction Diagnostiques Synchronisation
Commissionning Commissionning Preparation Pannes ShiftCheck
  Toutes les notes concernant les Commissionning de ThomX, Page 39 of 63  Not logged in ThomX    logo
New entries since:Thu Jan 1 01:00:00 1970
ID Date Authordown Status Type Category Important Subject Icon Text Attachments
  1014   Wed Feb 19 08:28:11 2025 Entered by Super Team from 134.158.195.141 on Wed Feb 19 08:27:57 2025Under ProcessShift summaryRing Commissioning   08h26 Start ThomX: Modulator, Fridge, Laser

08h32 Chillers were started, cycling
all magnets
  
  311   Wed Feb 9 16:59:58 2022 Entered by Super Team from 134.158.195.141 on Wed Feb 9 16:59:36 2022 Shift summaryLinac Commissionning   Arret du test longue durée à
17h00, pas d'interlock durant toute la
période, pas d'interlock intempestif
  
  310   Wed Feb 9 09:13:04 2022 Entered by Super Team from 134.158.195.141 on Wed Feb 9 09:12:42 2022 Shift summaryLinac Commissionning   Le modulateur à tourner toute la
nuit on position Trig, je démarre 
un essai de longue durée avec RF dans
  
  1166   Wed Dec 10 10:45:33 2025 Entered by Super Team from 134.158.195.141 on Wed Dec 10 10:45:16 2025Under ProcessShift summaryLinac Commissionning   8h30 : machine started on remote
50 MeV operation.
Problem with Yag-TL camera
  
  203   Wed Dec 8 15:11:18 2021 Entered by Super Team from 134.158.195.141 on Wed Dec 8 15:10:57 2021Under ProcessInfoLinac Commissionning Run Linac alignement Operateurs : EG, HG

but : travailler sur l'alignement
de la tete de machine
 laser_8Dec_16h40.pngRedpitaya_08Dec.png 
  202   Wed Dec 8 11:46:49 2021 Entered by Super Team from 134.158.195.141 on Wed Dec 8 11:46:36 2021FixedInfoLaser | Linac Commissionning Moteur Mirroir laser photocathode  Operateur : EG, HG

 

Probleme constaté:
  
  1161   Wed Dec 3 11:09:12 2025 Entered by Super Team from 134.158.195.141 on Wed Dec 3 11:08:54 2025Not FixedInfoRF Anneau | Linac Commissionning | Ring Commissioning Demarrage ThomX icon1.gif Soucis Septum : Maher
help 
  
  196   Wed Dec 1 13:05:53 2021 Entered by Super Team from 134.158.195.141 on Wed Dec 1 13:04:57 2021Under ProcessLinacLinac Commissionning Alignements tete de machine Conditions

Phase RF :

On
se place à la phase qui maximise l'energie
des électrons.
 charge_phase__at_01-12-2021__13-01-17.jpgB_rot_y_scan_after_x_B_in_150_200_50pts.png 
  195   Wed Dec 1 11:45:03 2021 Entered by Super Team from 134.158.195.141 on Wed Dec 1 11:44:50 2021Under ProcessLinacLaser | Linac Commissionning alignement laser Laser:

Recentrer le faisceau
laser dans la mire en agissant sur les moteurs
M5.
 2021-12-01_11_49_39_li_op_las_02_log_scale_False_despeckle_False_min_scale_0_max_scale_25.png2021-12-01_12_29_17_li_op_las_02_log_scale_False_despeckle_False_min_scale_0_max_scale_25.png 
  Draft   Tue Oct 28 08:40:22 2025 Entered by Super Team from 134.158.195.141 on Tue Oct 28 08:40:06 2025Under ProcessShift summary    08h40 Warm-up ThomX: Modulator, Laser,
Fridge

08h45 Chillers were started, cycling
 Screenshot_from_2025-10-28_11-48-31.pngScreenshot_from_2025-10-28_11-47-12.pngScreenshot_from_2025-10-28_11-46-55.pngScreenshot_from_2025-10-28_15-34-03.png 
  192   Tue Nov 30 10:31:04 2021 Entered by Super Team from 134.158.195.141 on Tue Nov 30 10:30:47 2021Not FixedProblemRF D1 | Linac Commissionning Soucis modulateur problèmes pour démarrer,
il se met encore en défait pendant
la periode de chauffe. Le probleme vu hier
  
  633   Tue Nov 29 09:18:20 2022 Entered by Super Team from 134.158.195.141 on Tue Nov 29 09:18:00 2022 LinacLinac Commissionning Faisceau linac 9h15 : Mise en chauffe modulateur, mise
en route refroidissements

Clé fosse nord et fosse
 Signaux_RF_291122.png 
  1157   Tue Nov 25 09:32:03 2025 Entered by Super Team from 134.158.195.141 on Tue Nov 25 09:31:46 2025Under ProcessShift summaryDiag | Ring Commissioning   09h31 Warm-up ThomX: Modulator, Laser,
Fridge

09h36 Chillers were started,
  
  176   Tue Nov 23 12:11:16 2021 Entered by Super Team from 134.158.195.141 on Tue Nov 23 12:11:01 2021Reference SolutionInfoLaser | Linac Commissionning energie laser La puissance laser aujourd'hui (23/11/2021)
est de :

  - Sortie laser : 200 uJ
  
  466   Tue May 24 09:12:27 2022 Entered by Super Team from 134.158.195.141 on Tue May 24 09:09:19 2022Under ProcessLinacLinac Commissionning Démarrage pour faisceau aujourd'hui OdJ : Prise de données pour le ML
(SC, HG, VS, HM, VC)

Mise en chauffe modulateur et chillers
  
  455   Tue May 10 14:03:55 2022 Entered by Super Team from 134.158.195.141 on Tue May 10 14:03:41 2022Under ProcessLinacLinac Commissionning Faisceau sur le premier ecran LI/DG/SST.01 Image faisceau à phi = phiqmax -
40 = 100 degres, bobine de focalisation =
210 A sur LI/DG/SST.01
 2022-05-10_14_03_55_li_dg_sst_01-ccd_01_RAW.png 
  409   Tue Mar 22 11:28:11 2022 Entered by Super Team from 134.158.195.141 on Tue Mar 22 11:27:07 2022Not FixedLinacLaser | RF D1 Signal Redpitaya Signal Photodiode :

Pour comprendre les échelles
ainsi que le manque de dynamique, Viktor
 Screenshot_from_2022-03-22_11-28-59.png 
  1027   Tue Mar 4 18:42:57 2025 Entered by Super Team from 134.158.195.141 on Tue Mar 4 18:42:42 2025Under ProcessLinacLI | TL Conditionnement Canon 1- Conditionnement du Canon à 16
dB, on gagne un peu en vide. 

2- sautes du faisceau : vérification
 Jumps_YagLI.pngJumps_YagLI_NoSteerer.png 
  377   Tue Mar 1 10:34:30 2022 Entered by Super Team from 134.158.195.141 on Tue Mar 1 10:34:10 2022Not FixedUrgentCC panneau IHM ne se lance pas [resolu] resolu

 

Voici l'erreur,
  
  376   Tue Mar 1 09:08:55 2022 Entered by Super Team from 134.158.195.141 on Tue Mar 1 09:08:40 2022 Shift summaryLinac Commissionning   démarrage chillers, modulateur (
en local )

pas de IHM modulateur meme pb que
  
ELOG V3.1.4-395e101