  Toutes les notes concernant les Commissionning de ThomX, Page 38 of 63  Not logged in ThomX    logo
New entries since:Thu Jan 1 01:00:00 1970
Entry   Entered by Christelle Bruni from 82.64.20.144 on Thu Oct 28 15:26:15 2021; Mesure du 19 octobre Charge/énergie laser Elaser_19102021.pngClasseur4.xlsx
Entry   Entered by Super Team from 134.158.195.141 on Tue Feb 15 10:14:52 2022; Mesure de la stabilité du synchrolock du laser Photocathode 
Entry   Entered by Super Team from 134.158.195.142 on Fri Oct 8 11:11:59 2021; Mesure de l'erreur sur le pointé laser 
Entry   Entered by Super Team from 134.158.195.142 on Fri Jan 14 12:03:02 2022; Mesure de charge 
Entry   Entered by Super Team from 134.158.195.141 on Wed Nov 24 16:52:10 2021; Mesure d'energie 
Entry   Entered by VC, JNC, SC, HG from 134.158.195.141 on Thu May 19 08:55:39 2022; Mesure courant obscurité 
Entry   VM, IC, ND; Measurements 18/4 Screenshot_from_2025-04-18_09-42-24.pnginjection_sequence_blank2ms_009.pnginjection_sequence_blank2ms_003.pnginjection_sequence_blank2ms_002.pnginjection_sequence_blank2ms_036.png
Entry   Marie Julien Hayg Sophie; Matching ring-TL - Recherche des bons twiss pour la TL Screenshot_from_2025-12-05_18-26-56.png
Entry   Vincent; Manip Gplast 
Entry   MJ, KD; MONOCHROMATEUR - 12 mars 2026 
Entry   IC,VM, KD, DN, MJ; MONO 61.5 MeV - 07 avril 2026 
Entry   Entered by Marie Jacquet from 134.158.89.45 on Mon Nov 28 14:25:31 2022; Lmag STR 3 (steerer après la LIL) 2022-11-28-STEERER_3_Lmag.pdf
Entry   Entered by Super Team from 134.158.195.142 on Wed Dec 7 16:58:42 2022; Linac measurements @ différent modulator voltage settings  
Entry   Entered by Super Team from 134.158.195.141 on Wed Jun 18 12:45:28 2025; Linac measurement + phase +  6x
Entry   VC; Linac commitionning 
Entry   VM && HG; Linac commissioning  Vacc_2026-02-11_11-05-31.pngScreenshot_from_2026-02-11_15-57-35.pngCharge_trend_2026-02-11_17-12-31.png
Entry   SC/MJ; Linac + TL divers yag_TL2.pngBPM_LI.png
Entry   CB,KD,SC; Linac profiles_darkandbeam.pngsolenoscan16h05.pngsolenoscan16h32.png
Entry   CB; Linac 
Entry   VC,SC, ND, IC, VK, CB, V; Linac 