ID Date Authordown Status Type Category Important Subject Icon Text Attachments
  608   Wed Oct 26 14:13:16 2022 Entered by Super Team from 134.158.195.141 on Wed Oct 26 14:13:01 2022 UrgentLinac Commissionning BPM TL 2, 3 et 4 ? Les BPM TL 2 3 et 4 ont l'air fige
. Les valeurs sur 'ihm sont totalement
figees ...
  
  942   Wed Oct 23 17:30:58 2024 Entered by Super Team from 134.158.195.141 on Wed Oct 23 17:27:14 2024Under ProcessShift summaryLinac Commissionning   Gun phase 50 dg., At 0.5 dB; Sect phase
230 dg. At 2.65 dB; Sol. 220 A, Gun charge
-131 pC, Linac -112 pC, TL  -120 pC.
 DispersionTLBPM2.png 
  179   Wed Nov 24 16:52:29 2021 Entered by Super Team from 134.158.195.141 on Wed Nov 24 16:52:10 2021Under ProcessLinacLinac Commissionning Mesure d'energie Calibration Ecran TL-SST01

 
  
  178   Wed Nov 24 11:21:41 2021 Entered by Super Team from 134.158.195.141 on Wed Nov 24 11:21:24 2021Under ProcessLinacLaser | Linac Commissionning shift du 24 Novembre 2021 Laser :


Viktor a remis
le hublot pour gagner en stabilité
laser
Energie laser : 54 µJ
laser
 charge_phase__at_24-11-2021__15-11-41.jpgScreenshot_from_2021-11-24_15-23-50.pngScreenshot_from_2021-11-24_15-51-42.png 
  Draft   Wed Nov 5 12:50:55 2025 Entered by Super Team from 134.158.195.141 on Wed Nov 5 12:50:37 2025      Matin :

Soucis synchro :
- Nicolas les a redémarré
 Screenshot_from_2025-11-05_17-49-33.pngScreenshot_from_2025-11-05_17-51-14.pngScreenshot_from_2025-11-05_17-50-44.png 
  859   Wed May 15 10:52:19 2024 Entered by Super Team from 134.158.195.141 on Wed May 15 10:51:59 2024 Shift summaryLI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning Conditionnement section sortie PA 120W ---> pas assez pour obtenir
la puissance nominale Klystron, sortie puissance
PA devrait etre autour de 400 W
  
  457   Wed May 11 18:32:38 2022 Entered by Super Team from 134.158.195.141 on Wed May 11 18:32:20 2022Under ProcessInfoLinac Commissionning Run machine : JNC/HG But du run :

refaire le transport jusqu'au
DUMP en vérifiant le transport (steerers
 2022-05-11_18_45_12_li_op_las_02_log_scale_False_despeckle_False_min_scale_0_max_scale_350.png2022-05-11_18_51_09_li_op_las_02_log_scale_False_despeckle_False_min_scale_0_max_scale_350.png2022-05-11_19_01_22_li_op_las_02_Iris1.5mm_log_scale_False_despeckle_False_min_scale_0_max_scale_300.pngScreenshot_from_2022-05-11_21-15-19.pngScan_pos_phase_LIL__at_11-05-2022__21-34-50.png 
  411   Wed Mar 23 12:52:58 2022 Entered by Super Team from 134.158.195.141 on Wed Mar 23 12:52:44 2022Under ProcessLinacElectronique | Linac Commissionning Test des redpitaya baie 17 Point de départ :

- Signal d'entrée :
Générateur AFG Techtro, Sortie
 6x 
  395   Wed Mar 9 11:37:29 2022 Entered by Super Team from 134.158.195.141 on Wed Mar 9 11:37:15 2022Under ProcessLinacDiag | Linac Commissionning Demarrage machine (JNC/HG) Laser :

- 25 µJ

- Images sauvées : /data/shared/Commissioning_tools/Mesure/20220309/Laser
 Screenshot_from_2022-03-09_18-51-23.png 
  1093   Wed Jun 25 18:47:20 2025 Entered by Super Team from 134.158.195.141 on Wed Jun 25 18:47:07 2025Under ProcessShift summaryLI Laser position icon1.gif New laser position :

5.041
4.448
  
  1089   Wed Jun 18 12:45:49 2025 Entered by Super Team from 134.158.195.141 on Wed Jun 18 12:45:28 2025Under ProcessInfoLinac Commissionning Linac measurement + phase +  
Phi Qmax ; 324° : Phi Emax
: 274°
Qmax : 70-80 pC (Att
: 290°) and 300 pC (Att : 420°)
Recipt
 6x 
  495   Wed Jul 6 09:37:10 2022 Entered by Super Team from 134.158.195.141 on Wed Jul 6 09:36:51 2022 Shift summaryRF D1   9h40 pemplissage réseau eau, mise
en route modulateur et chillers

 
  
  494   Wed Jul 6 09:20:53 2022 Entered by Super Team from 134.158.195.141 on Wed Jul 6 09:20:39 2022 Shift summaryRF D1   J'arrete pour remplir le réseau
eau ( il est à 2 bar )

Maher
  
  493   Wed Jul 6 09:03:06 2022 Entered by Super Team from 134.158.195.141 on Wed Jul 6 09:02:45 2022Under ProcessShift summaryDiag | Laser | Linac Commissionning Q beam versus E laser 9H demarrage chauffage Klystron + frigo

9H 10 demarrage chiller canon et
section
  
  1097   Wed Jul 2 14:45:20 2025 Entered by Super Team from 134.158.195.141 on Wed Jul 2 14:45:07 2025Under ProcessInfoLI   Vérif position laser photocathode
:

--> bouge de 1mm en Y et 0.2
  
  235   Wed Jan 5 17:35:11 2022 Entered by Super Team from 134.158.195.141 on Wed Jan 5 17:34:46 2022Reference SolutionInfoLaser | Linac Commissionning Iris Motorisé [KD et HG]

-  Mise en place de l'iris
motorisé à peu près
  
  234   Wed Jan 5 15:25:30 2022 Entered by Super Team from 134.158.195.141 on Wed Jan 5 15:25:13 2022Under ProcessProblemRF D1 | Linac Commissionning Interventon Modulateur  Soucis modulateur qui ne passe pas en HV.

--> [MO, JN]  : Intervention
sur le modulateur.
  
  236   Wed Jan 5 17:41:03 2022 Entered by Super Team from 134.158.195.141 on Wed Jan 5 15:25:13 2022Under ProcessProblemRF D1 | Linac Commissionning RE: Interventon Modulateur  soucis Modulateur toujours pas réglé.
Un signal (dans un module d'automate
du modulateur) semble poser problème.
  
  1014   Wed Feb 19 08:28:11 2025 Entered by Super Team from 134.158.195.141 on Wed Feb 19 08:27:57 2025Under ProcessShift summaryRing Commissioning   08h26 Start ThomX: Modulator, Fridge, Laser

08h32 Chillers were started, cycling
all magnets
  
  311   Wed Feb 9 16:59:58 2022 Entered by Super Team from 134.158.195.141 on Wed Feb 9 16:59:36 2022 Shift summaryLinac Commissionning   Arret du test longue durée à
17h00, pas d'interlock durant toute la
période, pas d'interlock intempestif
  