  725   Fri Mar 31 10:11:40 2023 Entered by Super Team from 134.158.195.141 on Fri Mar 31 10:11:25 2023 LinacLinac Commissionning Faisceau Linac 10h12 Démarrage modulateur et refroidissement

Lancement de l'archivage

11h05 Fermeture casemate
  
  726   Fri Mar 31 10:44:31 2023 Entered by Super Team from 134.158.195.141 on Fri Mar 31 10:11:25 2023 LinacLinac Commissionning Faisceau Linac Qui me pique internet ?

Et m'éfface le elog
?
  
  729   Thu Apr 6 12:57:29 2023 Entered by Super Team from 134.158.195.141 on Thu Apr 6 12:57:15 2023 LinacLinac Commissionning Faisceau Linac 12h57 Mise en chauffe modulateur et refroiddissement
canon et section

Vide dans l'anneau de l'ordre
  
  730   Fri Apr 7 13:48:55 2023 Entered by Super Team from 134.158.195.141 on Fri Apr 7 13:42:08 2023 LinacLinac Commissionning Faisceau Linac Programme :

 - Mesure Energie apres section
en fonction de la phase avec steerer sur
  
  731   Tue Apr 11 12:59:18 2023 Entered by Super Team from 134.158.195.141 on Tue Apr 11 12:59:03 2023 LinacLinac Commissionning Faisceau Linac 13h : Mise en chauffe modulateur et refroidissement

14h34 Faisceau, HT = 1090V, HoPoslaser
= 5.039, vertposlaser = 2.291, attenuation
  
  733   Tue Apr 11 22:34:19 2023 Marie Vincent Noureddine Jean-Noel Shift summaryLinac Commissionning   Debut vers 16h

Passage section avec Isol=200,
1.7 db, ph=110
  
  735   Wed Apr 19 12:41:18 2023 CB/HG ProblemLinac Commissionning urgent : Pb IHM phase Bonjour,

nous ne pouvons pas piloter la
phase depuis l'IHM, elle est en boucle
  
  736   Wed Apr 19 14:47:58 2023 KD/CB Shift summaryLinac Commissionning run du 19 avril 2023 NB de Christelle
: pendant toute la durée de la manipe,
l'atténuateur section a été
 charge_phase__at_19-04-2023__16-39-28.jpg2023-04-19_19_12_41_li_dg_sst_01-ccd_01_RAW.png 
  Draft   Fri Apr 21 14:30:19 2023 Entered by Super Team from 134.158.195.141 on Fri Apr 21 14:30:03 2023 LinacLinac Commissionning Faisceau Linac 13h49 Démarrage faisceau

Position laser H = 4.9 et V = 2.42,
scan charge phase : phase de focalisation
  
  742   Wed Apr 26 19:03:56 2023 Entered by Marie Jacquet from 134.158.89.45 on Wed Apr 26 19:03:42 2023 Shift summaryLinac Commissionning shift du 26/04 - Quads scans + stabilite 1) Quad scans Isol = 155,
175, 190, 200, 220 pris avec script classique
ET avec script FWHM LIMA - Taille a comparer,
  
  746   Wed May 3 20:10:40 2023 Entered by Marie Jacquet from 134.158.89.45 on Wed May 3 20:10:26 2023 Shift summaryLinac Commissionning Stabilite LINAC Pour illustrer la fin de l'entree
elog 745 d'aujourd'hui  :

 2023-05-03-traitement_Data20230424et26.pdf 
  747   Thu May 4 10:09:43 2023 Entered by Viktor Soskov from 134.158.195.153 on Thu May 4 10:09:22 2023FixedInfoLinac Commissionning Laser status Bonjour l'énergie UV actuelle
sur la cathode = 58µJ avec l'iris
1.3mm
  
  749   Thu May 4 16:14:06 2023 Entered by Marie Jacquet from 134.158.89.45 on Wed May 3 20:10:26 2023 Shift summaryLinac Commissionning RE: Stabilite LINAC  




  
  766   Tue Jun 13 14:42:16 2023 Entered by Viktor Soskov from 134.158.195.153 on Tue Jun 13 14:42:00 2023FixedInfoLinac Commissionning arręt de la machine Bonjour,

avant d'arrêter completement
de la machine il faut absolument fermer le
  
  767   Tue Jun 13 15:00:28 2023 Entered by Viktor Soskov from 134.158.195.153 on Tue Jun 13 15:00:13 2023FixedInfoLinac Commissionning arret de la machine Bonjour,

avant d'arrêter completement
de la machine il faut absolument fermer le
  
  788   Tue Aug 1 09:21:59 2023 CB/JNC/SC LinacLinac Commissionning Faisceau linac 9h20 Mise en chauffe modulateur, démarrage
frigo et laser

Permis casemate en rouge sur le
  
  792   Mon Aug 28 18:13:32 2023 Entered by Viktor Soskov from 134.158.195.153 on Mon Aug 28 18:13:08 2023FixedLinacLinac Commissionning Laser status Bonjour, le parcours optique du laser-cathode
a été aligné. L'énérgie
UV actuelle sur la cathode - 47µJ (iris=1.3mm).
  
  793   Wed Sep 6 11:04:07 2023 Entered by Viktor Soskov from 134.158.195.153 on Wed Sep 6 11:03:51 2023FixedInfoLinac Commissionning Laser status Bonjour,

voici l'image du faisceau laser
sur la cathode, le diamètre d'iris
 VCathode_2023_09_06_11_00.odt 
  794   Wed Sep 20 10:00:58 2023 Entered by Viktor Soskov from 134.158.195.153 on Wed Sep 20 10:00:42 2023FixedInfoLinac Commissionning Laser status Bonjour, le laser-cathode a été
resté allumé pendant la nuit.

Viktor.
  
  828   Mon Jan 15 10:41:48 2024 Entered by Viktor Soskov from 134.158.195.153 on Mon Jan 15 10:41:24 2024FixedInfoLinac Commissionning Laser status Bonjour,

l'état actuel du laser:
on a passé le width du Pockels de
  