  Toutes les notes concernant les Commissionning de ThomX, Page 28 of 58  Not logged in ThomX    logo
New entries since:Thu Jan 1 01:00:00 1970
Entry   SC/ND/IC/VK/VM; Faisceau  11x
Entry   KD, HG; shift du 11 janvier 2023 BPM_stable_16h18.pngfaisceau_TL_YAG3.pngFC_Beam_OFF.pngFC_BeamON.png
Entry   KD, HG; shift du 10 janvier 2023 E_phase_for_different_Att.png
Entry   Entered by Hayg Guler from 134.158.195.141 on Mon Jan 9 19:28:16 2023; Mesures Linac (KD/HG) 
Entry   ND, IC, VK, VM; Prise de donnee 6/01 9x
Entry   ND, SC, VM, VK; Prise de donnee 5/01 8x
Entry   Entered by Maher OMEICH from 134.158.91.212 on Tue Jan 3 17:05:44 2023;  
Entry   Vincent Maher Sophie; Demarrage machine scan_charge_phase_min_180.0_max_260.0_11_5_33.pngScreenshot_from_2023-01-02_16-17-36.png
Entry   ND/PG/JNC/MO/SC/VC/NE; Redémarrage ThomX 
Entry   ND, Camille Cheney, Mohamed ; Prise de donnees 16/12 9x
Entry   KD; shift du 15 decembre 2022, entered from 134.158.195.141 
Entry   HG/CB/KD; run du 14 décembre 2022 
Entry   KD, HG; Run Linac  
Entry   Entered by Marie Jacquet from 134.158.89.45 on Mon Dec 12 16:26:59 2022; Yag Li et TL1 : quid de la calibration ?  2022-12-12-BPM-YAG-STR.pdf
Entry   Entered by Marie Jacquet from 134.158.89.45 on Mon Dec 12 15:49:05 2022; IHM BPM, "mean" HS ? 
Entry   SC/MJ; Linac + TL divers yag_TL2.pngBPM_LI.png
Entry   MJ HG KD; LE passee ce soir faisceau sur yag 5 Faisceau_dans_la_LE_2022-12-09_18-36-53.png
Entry   Entered by Super Team from 134.158.195.141 on Fri Dec 9 11:07:40 2022;  Screenshot_from_2022-12-09_16-53-05.pngScreenshot_from_2022-12-09_16-52-44.png
Entry   KD; shift du 9 decembre 2022 
Entry   ND, IC, VK, VM, ME; Shift 8/12 14x