Entry   SC; Tests CC apres re-démarrage 
Entry   IC, VM, VK, ND; RIng commissioning 10x
Entry   ND, Enzo Crou, Noé Idesheim, Jean-Nicolas Quenot; Prise de donnee 16/3/2023 17x
Entry   KD, SC; shift du 14 mars 2023 
Entry   Entered by Viktor Soskov from 134.158.195.153 on Mon Mar 13 12:33:23 2023; Laser status 
    Reply   Entered by Viktor Soskov from 134.158.195.153 on Mon Mar 13 12:33:23 2023; RE: Laser status 
Entry   MJ; Le bouton PHASE CANON sur le panneau IHM NE FONCTIONNE PLUS !!!!!!!!!!!  
Entry   MJ; IHM SST HS - URGENT IHM_HS_2023-03-13_12-42-01.pngScreenshot_from_2023-03-13_12-55-32.png
Entry   IC, VM, ND, VK; Prise de donnee 10/3/2023 7x
Entry   ND, Sandry Wallon; Programme prise de donnée 9/03/2023 health_check_2023_03_09_10_51.pnghealth_check_2023_03_09_11_30.pngscan_charge_phase_min_20.0_max_60.0_12_2_35.png
Entry   Entered by Marie Jacquet from 134.158.205.47 on Wed Mar 8 11:45:31 2023; (suite elog 28 fev) data X_TLBPM02 vs I_Dipole - Plot Mesures/Simul  2023-02-28-I_Dip_vs_X_TLBPM02.png
Entry   Entered by Marie Jacquet from 134.158.205.47 on Wed Mar 8 11:45:31 2023; I-dipole vs X_TLBPM02 - Mesures/Simul (suite elog 28 fev) 
Entry   MJ HG KD VC; URGENT SST off  SST_HS_023-03-06_12-14-40.png2023-03-06_14-44-27.png2023-03-06_14-49-54.png
Entry   MO VC; Commitionning 
Entry   VC; pB synchro suite 
icon4.gif   KD, SC, VC; Jitter énergie  
Entry   VK VM; Shift 03 
    Reply   VK VM; RE: Shift 03 
       Reply   VK VM; RE: RE: Shift 03 
Entry   CB/JNC/MJ/ VK/VM; run du 1er mars 2023 Screenshot_2023-03-01_at_19.27.13.pngScreenshot_2023-03-01_at_19.26.29.png
Entry   CB/JNC; run du 27 février 2023 
Entry   Entered by Nicolas Delerue from 134.158.195.142 on Fri Feb 24 16:24:00 2023; Shift 24/2 
Entry   ND, VK, VM; Shift 23/2 9x