HOME
Prise de donnees
MML
Controle commande
Simulations
Notes
Hardware
Ligne X
Laser Interaction
Diagnostiques
Synchronisation
Commissionning
Commissionning Preparation
Pannes
ShiftCheck
Toutes les notes concernant les Commissionning de ThomX, Page 26 of 58
Not logged in
Find
|
Last day
|
Login
|
Help
New entries since:
Thu Jan 1 01:00:00 1970
Full
|
Summary
| Threaded |
Collapse
|
Expand
1147 Entries
Goto page
Previous
1
,
2
,
3
...
25
, 26,
27
...
56
,
57
,
58
Next
SC; Tests CC apres re-démarrage
IC, VM, VK, ND; RIng commissioning
10x
ND, Enzo Crou, Noé Idesheim, Jean-Nicolas Quenot; Prise de donnee 16/3/2023
17x
KD, SC; shift du 14 mars 2023
Entered by Viktor Soskov from 134.158.195.153 on Mon Mar 13 12:33:23 2023; Laser status
Entered by Viktor Soskov from 134.158.195.153 on Mon Mar 13 12:33:23 2023; RE: Laser status
MJ; Le bouton PHASE CANON sur le panneau IHM NE FONCTIONNE PLUS !!!!!!!!!!!
MJ; IHM SST HS - URGENT
IC, VM, ND, VK; Prise de donnee 10/3/2023
7x
ND, Sandry Wallon; Programme prise de donnée 9/03/2023
Entered by Marie Jacquet from 134.158.205.47 on Wed Mar 8 11:45:31 2023; (suite elog 28 fev) data X_TLBPM02 vs I_Dipole - Plot Mesures/Simul
Entered by Marie Jacquet from 134.158.205.47 on Wed Mar 8 11:45:31 2023; I-dipole vs X_TLBPM02 - Mesures/Simul (suite elog 28 fev)
MJ HG KD VC; URGENT SST off
MO VC; Commitionning
VC; pB synchro suite
KD, SC, VC; Jitter énergie
VK VM; Shift 03
VK VM; RE: Shift 03
VK VM; RE: RE: Shift 03
CB/JNC/MJ/ VK/VM; run du 1er mars 2023
CB/JNC; run du 27 février 2023
Entered by Nicolas Delerue from 134.158.195.142 on Fri Feb 24 16:24:00 2023; Shift 24/2
ND, VK, VM; Shift 23/2
9x