  Toutes les notes concernant les Commissionning de ThomX, Page 13 of 61  Not logged in ThomX    logo
ID Date Author Status Type Category Important Subject Icon Text Attachments
  982   Tue Dec 17 23:26:45 2024 Entered by Marie Jacquet from 134.158.205.16 on Tue Dec 17 23:26:26 2024FixedShift summaryLI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning shift 17/12 - scan vert FPC - 50 MeV 8h10 : mise en chauffe de la machine (modulateur,
laser, frigo et chiller)

9h30: faisceau dans anneau avec
 6x 
  981   Tue Dec 17 08:09:41 2024 KDUnder ProcessShift summaryLinac Commissionning | Ring Commissioning shift du 17 décembre 2024 8h10 : mise en chauffe de la machine (modulateur,
laser, frigo et chiller)

9h30: faisceau dans anneau avec
  
  980   Fri Dec 13 08:22:36 2024 VM, IC, VKUnder ProcessShift summaryRing Commissioning   08h23 Start ThomX

09h40 HV is 'On'

10h24 RF Gun Phase 183 dg. Sect.
 Screenshot_from_2024-12-13_11-28-46.pngScreenshot_from_2024-12-13_14-44-28.pngScreenshot_from_2024-12-13_14-46-59.png 
  979   Thu Dec 12 07:54:45 2024 KD, RC, MJ, VM, IC, VKUnder ProcessShift summaryLinac Commissionning | Ring Commissioning shift du 12 décembre 2024 7h50: mise en chauffe en remote (chiller,
frigo, laser, modulateur)

Demarrage alignement sur l'axe
 7x 
  978   Wed Dec 11 08:12:54 2024 KD, VC, RC MJUnder ProcessShift summaryLinac Commissionning | Ring Commissioning shift du 11 décembre 2024 8h10 : mise en chauffe à distance
de la machine (chiller, frigo, laser, modulateur).

/!\ La mesure SF6 faites
 Screenshot_2024-12-11_11-51-40_min_synchrotron_deb_aller_m1_2mmY.pngScreenshot_2024-12-11_11-51-40_min_synchrotron_fin_aller_m1_2mmY.pngScreenshot_2024-12-11_11-51-40_max_synchrotron_deb_aller_m1_2mmY.pngScreenshot_2024-12-11_12-39-36_min_synchrotron_deb_retour_0mmY.png 
  977   Tue Dec 10 11:35:16 2024 VM,HG,SCUnder ProcessShift summaryLI | TL | LE | Ring | Linac Commissionning | Ring Commissioning 50 and 70 MeV Emittance, and transport  Intervention chiller (Maher) : maintenance
nécessaire à prévoir
(clé outil clignote)
 Q_vs_SolenoScan_at_16-52-02_Q1_Off.pngQ_vs_SolenoScan_at_16-39-39_recette_good_xrays.png 
  976   Fri Dec 6 11:11:31 2024 VC MJFixedShift summaryLI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning Installation du PM dans la X-hucth Le PM est installe dans la X-hutch (PM
+ gene + ocsillo), on a  test que ca
fonctionne -
  
  975   Fri Dec 6 08:24:36 2024 VM, IC, VK, HG Under ProcessShift summaryRing Commissioning   08h25 Start ThomX

09h55 HV is 'ON'

10h18 RF Gun Phase is 159 dg. Sect.
 8x 
  974   Thu Dec 5 08:31:34 2024 VM Entered by Super Team from 134.158.195.141 on Thu Dec 5 08:31:12 2024Under ProcessShift summaryRing Commissioning   08h28 Start ThomX

08h40 Some magnets remain switched
off. Cycling was not performed
  
  973   Wed Dec 4 10:54:28 2024 VCFixedFixSY Frequence anneau et systeme de synchro Rappel:


la
  
  972   Tue Dec 3 09:14:50 2024 SC, HG, VMUnder ProcessLinacLI | TL Passage à 61.5MeV et 70 MeV 9h14 Mise en chauffe

Pas de camera laser qui s'ouvre
sur PlateformeIHM
 screenshot_steerers_linac_findejournée.pngBeam_transmission_Sole.png 
  971   Fri Nov 29 08:22:14 2024 VC, Carlos Buitrago, Sudhanshu Thakur, NDUnder ProcessShift summaryLinac Commissionning TP 29-11--2024 demarrage chauffage 8H20

test nouveau code synchro 50Hz
=> ne fonctionne pas
  
  Draft   Thu Nov 28 08:19:05 2024 VM, IC, VK Under ProcessInfoRing Commissioning   08h18 Start ThomX

10h00 HV is 'ON'

10h35 RF Gun phase is 174 dg. Section
  
  969   Wed Nov 27 08:04:44 2024 VCUnder ProcessShift summaryLinac Commissionning Shift summary 27/11 8h : mise en chauffe (laser, modulateur,
frigo, chiller, cyclage)

9H30 y'a eu une intervention
 QP1_scan.pngQP2_scan.pngQP3_scan.png 
  Draft   Tue Nov 26 07:53:39 2024 MJ RC KDUnder ProcessShift summaryLaser | Opt | Linac Commissionning | Ring Commissioning shift du 26 novembre 2024 8h : mise en chauffe en remote (laser,
modulateur, frigo, chiller, cyclage)

 2024-11-26_12_22_06_el_dg_sst_01-ccd_01_RAW_1.png 
  967   Fri Nov 22 11:18:28 2024 KD, RCUnder ProcessShift summaryLinac Commissionning | Ring Commissioning shift du 22 novembre 2024 9h30 : mise en chauffe

intervention casemate pour alignement
laser et nettoyage optique.
 TL_BPM4_locked.dat 
  966   Fri Nov 22 11:04:39 2024 KDNew SolutionLinacLI laser PC  Mesure de ce matin et réalignement:

sortie laser : 298uJ

sortie ligne de transport : 209uJ
 2024-11-22_11_07_23_li_op_las_02_RAW.png2024-11-22_11_07_57_li_op_las_02_RAW.png 
  965   Thu Nov 21 08:27:15 2024 VM Entered by Super Team from 134.158.195.141 on Thu Nov 21 08:26:43 2024Under ProcessInfoRing Commissioning   08H25 Start ThomX

09H45 HV is 'ON'

09h49 Breakdown in the RF Gun
  
  964   Tue Nov 19 08:20:29 2024 MJ VC KD RC DNUnder ProcessShift summaryLinac Commissionning Shift summary 19/11/2024 icon3.gif 8h20 demarrage machine

iris 1.3mm
att 440
 YAG_TL3_beam.pnginjection_ring.pngFluo_det.png 
  963   Fri Nov 15 12:13:42 2024 Entered by Nicolas Delerue from 134.158.195.144 on Fri Nov 15 12:13:26 2024Not FixedInfoTL Charge excess in the TL By looking at the BPM transmission tool
one can see that there is more charge on
TL/BP.03 than on TL/BPM.02 (see attached
 Screenshot_from_2024-11-15_12-12-55.pngScreenshot_from_2024-11-15_12-12-46.png 