| ID |
Date |
Author |
Status |
Type |
Category |
Important |
Subject |
Icon |
Text |
 |
|
Draft
|
Fri Nov 15 07:56:03 2024 |
IC, VK, VM, ND | | Shift summary | |
|
Ring studies, MRSV | | 07h50 Start ThomX
09h20 HV is 'ON'
09h25 HV 1215 V |
36x |
|
961
|
Thu Nov 14 09:21:51 2024 |
Entered by Viktor Soskov from 134.158.195.153 on Thu Nov 14 09:21:36 2024 | Fixed | Info | Laser |
|
Etat laser | | Bonjour, rien n'a change au faisceau
laser (distribution reste le meme,l'energie
sur la cathode =60mkJ, Iris = 1.3mm, Att |
|
|
960
|
Thu Nov 14 08:33:34 2024 |
Entered by Super Team from 134.158.195.141 on Thu Nov 14 08:33:03 2024 | Under Process | Info | Linac Commissionning |
|
| | 08h30 Start ThomX
10h00 HV is 'ON'
11h03 RF Gun phase 230 dg. Att. |
15x |
|
959
|
Wed Nov 13 08:26:05 2024 |
VC | Under Process | Shift summary | Linac Commissionning |
|
Shift summary 13/11/24 | | demarrage machine 8h30
demarrage puissance RF
Phase charge max 286° Qmax 103pC |
    |
|
958
|
Tue Nov 12 10:36:39 2024 |
Entered by Viktor Soskov from 134.158.195.153 on Tue Nov 12 10:36:24 2024 | Fixed | Info | Laser |
|
Salle laser ThomX | | Bonjour , l'intervention du Dalkia
sur le CTA de la salle laser est terminee.
Viktor. |
|
|
957
|
Tue Nov 12 08:12:06 2024 |
MJ KD VC | Under Process | Shift summary | Linac Commissionning |
|
shift du 12 novembre 2024 | | 8h10 : mise en chauffe en remote (modulateur,
laser, chillers).
redemarrage serveur camera UV |
|
|
956
|
Fri Nov 8 09:35:41 2024 |
IC, VK, JN | Under Process | Shift summary | Ring |
|
ring studies | | 8h50 Start of the modumator and all subsystems
Beam studies.
Orbit Correction. |
13x |
|
955
|
Thu Nov 7 08:53:22 2024 |
IC, VK, VM, JN | Under Process | Shift summary | Ring |
|
| | 8h50 Start of the modumator and all subsystems
PC client 1 was frozen => we
restarted |
6x |
|
954
|
Wed Nov 6 08:06:51 2024 |
VC MJ | Under Process | Shift summary | Linac Commissionning |
|
shift | | demarrage chauffage 8h
autorisation PSS zone modulateur
interdite => il faut venir valider la |
  |
|
953
|
Tue Nov 5 17:30:10 2024 |
Entered by Viktor Soskov from 134.158.195.153 on Tue Nov 5 17:29:48 2024 | Fixed | Info | Laser |
|
Laser-cathode | | Bonjour, le laser (miroirs du parcours
optique) a ete realigne.
L'etat actuel: l'enrgie |
|
|
952
|
Tue Nov 5 10:09:35 2024 |
SC VC | Under Process | Shift summary | Linac Commissionning |
|
shift linac | | demarrage modulateur 9H
erreur vanne acquitée
10H intervention Viktor sur le laser |
|
|
951
|
Thu Oct 31 08:19:25 2024 |
KDn Dupraz from 109.222.35.58 on Thu Oct 31 08:19:12 2024 | Under Process | Shift summary | Ring Commissioning |
|
shift du 31 octobre 2024 | | 8h15: mise en chauffe en remote (modulateur,
laser, chiller, Cycling)
Tuning of the linac and injection |
  |
|
950
|
Wed Oct 30 11:33:04 2024 |
VM, IC, VK | Under Process | Info | LI | TL | LE | Ring |
|
| | 9h25 Start ThomX
11h20 HV on, linac RF OK, but there
is no laser on the cathode. Trying to fix. |
6x |
|
948
|
Tue Oct 29 10:31:45 2024 |
HG, SC | Under Process | Info | Linac Commissionning |
|
Etude faisceau linac | | 9h30 : Mise en chauffe
10h31 : mise en route faisceau
On se place à 0 dB, |
|
|
947
|
Mon Oct 28 18:56:01 2024 |
KD, HG | Under Process | Shift summary | Linac Commissionning | Ring Commissioning |
|
shift du 28 octobre 2024 | | 17h: faisceau machine.
** On fait un scan de TL/STR1 avec
QP1 à QP4 à 0, faisceau aligné |
 |
|
946
|
Fri Oct 25 18:07:48 2024 |
KD | Under Process | Shift summary | Linac Commissionning |
|
performance estimation alignement QP | | On aligne dans QP1 et QP3 et on regarde
pour une variation de +- 1A la derive sur
TL/BPM.01 |
7x |
|
945
|
Fri Oct 25 14:44:05 2024 |
ND, Manon Philit, Janine Issa | Under Process | Shift summary | LI |
|
Shift summary 25/10 | | 9 : 34 Mise en chauffe
Health check OK (a part les Redpitaya)
10:25 démarrage faisceau |
   |
|
943
|
Thu Oct 24 07:15:40 2024 |
KD, VM | Under Process | Shift summary | Linac Commissionning |
|
shift du 24 octobre 2024 | | 7h15: mise en chauffe machine (modulateur,
laser, refroidissement, cyclage), en remote
Gun Att. = 0.0 dB, Phase=47 dg., |
    |
|
942
|
Wed Oct 23 17:30:58 2024 |
Entered by Super Team from 134.158.195.141 on Wed Oct 23 17:27:14 2024 | Under Process | Shift summary | Linac Commissionning |
|
| | Gun phase 50 dg., At 0.5 dB; Sect phase
230 dg. At 2.65 dB; Sol. 220 A, Gun charge
-131 pC, Linac -112 pC, TL -120 pC. |
|
|
941
|
Wed Oct 23 08:15:09 2024 |
KD | Under Process | Shift summary | Linac Commissionning |
|
shift du 23 octobre 2024 | | 8h15: mise en chauffe de la machine (en
remote)
11H HT ON! recette goog_20241009_17_38_49 |
  |