  Draft   Fri Nov 15 07:56:03 2024 IC, VK, VM, ND Shift summary  Ring studies, MRSV 07h50 Start ThomX

09h20 HV is 'ON'

09h25 HV  1215 V
 36x 
  961   Thu Nov 14 09:21:51 2024 Entered by Viktor Soskov from 134.158.195.153 on Thu Nov 14 09:21:36 2024FixedInfoLaser Etat laser Bonjour, rien n'a change au faisceau
laser (distribution reste le meme,l'energie
sur la cathode =60mkJ, Iris = 1.3mm, Att
  
  960   Thu Nov 14 08:33:34 2024 Entered by Super Team from 134.158.195.141 on Thu Nov 14 08:33:03 2024Under ProcessInfoLinac Commissionning   08h30 Start ThomX

10h00 HV is 'ON'

11h03 RF Gun phase 230 dg. Att.
 15x 
  959   Wed Nov 13 08:26:05 2024 VCUnder ProcessShift summaryLinac Commissionning Shift summary 13/11/24 demarrage machine 8h30
demarrage puissance RF
Phase charge max 286° Qmax 103pC
 Q_transport_vs_Soleno.pngQ_transport_vs_Soleno_Align_917_1.pngQ_transport_vs_Soleno_Align_917_2.pngICT_Att_320_to_400.pngSPSum_LI_Att_320_to_400.png 
  958   Tue Nov 12 10:36:39 2024 Entered by Viktor Soskov from 134.158.195.153 on Tue Nov 12 10:36:24 2024FixedInfoLaser Salle laser ThomX Bonjour , l'intervention du Dalkia
sur le CTA de la salle laser est terminee.

Viktor.
  
  957   Tue Nov 12 08:12:06 2024 MJ KD VCUnder ProcessShift summaryLinac Commissionning shift du 12 novembre 2024 8h10 : mise en chauffe en remote (modulateur,
laser, chillers).

redemarrage serveur camera UV
  
  956   Fri Nov 8 09:35:41 2024 IC, VK, JNUnder ProcessShift summaryRing ring studies 8h50 Start of the modumator and all subsystems

Beam studies.

Orbit Correction.
 13x 
  955   Thu Nov 7 08:53:22 2024 IC, VK, VM, JNUnder ProcessShift summaryRing   8h50 Start of the modumator and all subsystems

PC client 1 was frozen => we
restarted
 6x 
  954   Wed Nov 6 08:06:51 2024 VC MJUnder ProcessShift summaryLinac Commissionning shift  demarrage chauffage 8h
autorisation PSS zone modulateur 
interdite => il faut venir valider la
 BPMLI_align_photocathode_13h15.pngBPMLI_align_photocathode_13h56.pngLaser_sur_cameraUV_16h19.png 
  953   Tue Nov 5 17:30:10 2024 Entered by Viktor Soskov from 134.158.195.153 on Tue Nov 5 17:29:48 2024FixedInfoLaser Laser-cathode Bonjour, le laser (miroirs du parcours
optique) a ete realigne.

L'etat actuel: l'enrgie
  
  952   Tue Nov 5 10:09:35 2024 SC VCUnder ProcessShift summaryLinac Commissionning shift linac demarrage modulateur 9H
erreur vanne acquitée
10H intervention Viktor sur le laser
  
  951   Thu Oct 31 08:19:25 2024 KDn Dupraz from 109.222.35.58 on Thu Oct 31 08:19:12 2024Under ProcessShift summaryRing Commissioning shift du 31 octobre 2024 8h15: mise en chauffe en remote (modulateur,
laser, chiller, Cycling)

Tuning of the linac and injection
 Screenshot_from_2024-10-31_13-37-11.pngScreenshot_from_2024-10-31_12-07-13.pngclosed_orbit_31102024.png 
  950   Wed Oct 30 11:33:04 2024 VM, IC, VKUnder ProcessInfoLI | TL | LE | Ring   9h25 Start ThomX

11h20 HV on, linac RF OK, but there
is no laser on the cathode. Trying to fix.
 6x 
  948   Tue Oct 29 10:31:45 2024 HG, SCUnder ProcessInfoLinac Commissionning Etude faisceau linac 9h30 : Mise en chauffe

10h31 : mise en route faisceau

On se place à 0 dB,
 Soleno_Align_noCol1.png 
  947   Mon Oct 28 18:56:01 2024 KD, HGUnder ProcessShift summaryLinac Commissionning | Ring Commissioning shift du 28 octobre 2024 17h: faisceau machine.

** On fait un scan de TL/STR1 avec
QP1 à QP4 à 0, faisceau aligné
 scan_TL_STR1_VS_TL_YAG2.pngScreenshot_2024-10-28_19-40-50_BPM_ring.png 
  946   Fri Oct 25 18:07:48 2024 KDUnder ProcessShift summaryLinac Commissionning performance estimation alignement QP On aligne dans QP1 et QP3 et on regarde
pour une variation de +- 1A la derive sur
TL/BPM.01
 7x 
  945   Fri Oct 25 14:44:05 2024 ND, Manon Philit, Janine IssaUnder ProcessShift summaryLI Shift summary 25/10 9 : 34 Mise en chauffe

Health check OK (a part les Redpitaya)

10:25 démarrage faisceau
 2024-10-25_12_25_26_tl_dg_sst_02-ccd_01_log_scale_False_despeckle_False_min_scale_0_max_scale_100.pngscan_2024_10_25_16_36.pngscan_2024_10_25_16_41.pngscan_2024_10_25_16_51.png 
  943   Thu Oct 24 07:15:40 2024 KD, VMUnder ProcessShift summaryLinac Commissionning shift du 24 octobre 2024 7h15: mise en chauffe machine (modulateur,
laser, refroidissement, cyclage), en remote

Gun Att. = 0.0 dB, Phase=47 dg.,
 TbTSumW_O_RFScreenshot_from_2024-10-24_13-18-57.pngOsc_W_O_RFScreenshot_from_2024-10-24_13-21-59.pngOrbit_WO_RF_TLBPM2plus4mmScreenshotFrom2024-10-24_13-25-15.pngDispersionTLBPM2.pngUnstableTLBPM4Screenshot_from_2024-10-24_14-09-07.png 
  942   Wed Oct 23 17:30:58 2024 Entered by Super Team from 134.158.195.141 on Wed Oct 23 17:27:14 2024Under ProcessShift summaryLinac Commissionning   Gun phase 50 dg., At 0.5 dB; Sect phase
230 dg. At 2.65 dB; Sol. 220 A, Gun charge
-131 pC, Linac -112 pC, TL  -120 pC.
 DispersionTLBPM2.png 
  941   Wed Oct 23 08:15:09 2024 KDUnder ProcessShift summaryLinac Commissionning shift du 23 octobre 2024 8h15: mise en chauffe de la machine (en
remote)

11H HT ON! recette goog_20241009_17_38_49
 bary_11h59.png2024-10-23_11_25_24_li_dg_sst_01-ccd_01_RAW.png2024-10-23_11_45_23_li_dg_sst_01-ccd_01_RAW.png 