  Toutes les notes concernant les Commissionning de ThomX, Page 11 of 61  Not logged in ThomX    logo
ID Date Author Status Type Category Important Subject Icon Text Attachments
  1022   Wed Feb 26 22:52:03 2025 Entered by Marie Jacquet from 88.165.97.136 on Wed Feb 26 22:50:49 2025 Shift summaryLI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning 26 fevrier (visite Alberto Paola Luca) - Detecteur Photonic Science  Suite du commissioning
det Photonic Science

**
  
  Draft   Wed Feb 26 07:30:15 2025 KDUnder ProcessShift summaryLinac Commissionning | Ring Commissioning shift du 26 février 2025 7h30: mise en chauffe en remote (Modulateur,
frigo/chiller, laser, cyclage aimants)

8h35 HV is 'On'
  
  1020   Tue Feb 25 22:59:57 2025 Entered by Marie Jacquet from 88.165.97.136 on Tue Feb 25 22:59:29 2025 Shift summaryLI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning 24 -25 fevrier (visite Alberto Paola Luca) - Detecteur Photonic Science Commissioning det Photonic Science

** Depose
Dectris, mise en place Photonic, alignement
  
  1019   Tue Feb 25 08:09:54 2025 KDUnder ProcessShift summaryLinac Commissionning | Ring Commissioning shift du 25 février 2025 8h10: mise en chauffe machine en remote
(Frigo/chiller, modulateur, laser, cyclage
aimants)
 Charge_Drop.png 
  Draft   Mon Feb 24 08:00:09 2025 KD VC VMUnder ProcessShift summaryOpt | Linac Commissionning | Ring Commissioning shift du 24 février 2025 8h: mise en chauffe de la machine (Frigo/chiller,
laser, modulateur et cyclage aimants).

9H demarrage faisceau
  
  1017   Fri Feb 21 08:30:30 2025 shift crewUnder ProcessShift summaryOpt | Linac Commissionning | Ring Commissioning shift du 21 février 2025 8h30 : démarrage machine en remote
(modulateur, laser, chiller/frigo, cyclage)

Nouveau
 6x 
  1016   Thu Feb 20 08:25:11 2025 Entered by Super Team from 134.158.195.141 on Thu Feb 20 08:24:55 2025Under ProcessShift summaryRing Commissioning   08h25 Start ThomX; Start ThomX: Modulator,
Fridge, Laser

08h32 Chillers were started, cycling
 6x 
  1015   Wed Feb 19 17:32:30 2025 shift screw Shift summaryLI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning Rustine pour le probleme CEM kicker - ring storage - Xrays Cable ventilo kicker debranche ==> aucun
effet
Cable balise blinde ==>
 storage_et_Xrays_2025-02-19_19-01-58.pngdet2diodes_pb_voie4_2025-02-19_19-16-07.png 
  1014   Wed Feb 19 08:28:11 2025 Entered by Super Team from 134.158.195.141 on Wed Feb 19 08:27:57 2025Under ProcessShift summaryRing Commissioning   08h26 Start ThomX: Modulator, Fridge, Laser

08h32 Chillers were started, cycling
all magnets
  
  1013   Tue Feb 18 08:28:36 2025 VC, KD, VM, ND, RC, MJUnder ProcessShift summaryLI | Linac Commissionning shift  demarrage machine 8h30

intervention Kicker.. 8h45 

10H30 fin intervention Kicker Ok
 Screenshot_from_2025-02-18_17-52-13.pngScreenshot_from_2025-02-18_17-51-17.pngScreenshot_from_2025-02-18_17-49-55.pngScreenshot_from_2025-02-18_17-58-05.pngScreenshot_from_2025-02-18_17-59-46.png 
  Draft   Mon Feb 17 11:00:01 2025 VM, IC, VKUnder ProcessShift summary  70 MeV WP 10h30 Start beam

Since Friday evening the problem
to store the beam at 70 MeV. There is 1 turn
  
  Draft   Fri Feb 14 08:21:26 2025 Entered by Super Team from 134.158.195.141 on Fri Feb 14 08:21:09 2025Under ProcessShift summaryRing Commissioning   08h20 Start ThomX: modulator, laser, fridge,cycling
all magnets

08h25 chillers are started
  
  1010   Thu Feb 13 10:56:28 2025 ND, SC, Marie Labat, IC, VMUnder ProcessShift summaryRing Commissioning Opérations caméra à balayage / MRSV 8h50 Mise en chauffe modulateur

Changement de la carte mère
pour la badgeuse de la ligne X
 20x 
  1009   Wed Feb 12 08:00:31 2025 KD MJUnder ProcessShift summaryLI | TL | Linac Commissionning shift du 12 février 2025 - Alignements 8h: mise en chauffe à distance (modulateur,
frigo, chiller, laser)

9h30: laser semble pas aligné
 2025-02-12-Shift.pngaxes_BPM_calib.jpgaxes_BPM_nocalib.jpg 
  1008   Tue Feb 11 10:31:57 2025 ND, Marie LabatUnder ProcessShift summaryDiag Streak camera 9:20 Start aligning

12:40 Alignement done for both
linac and ring.
 20250211_173802.jpg20250211_174708.jpg 
  1007   Mon Feb 10 09:42:13 2025 ND, VC, HG, MJUnder ProcessShift summaryLI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning Test demarrage 10/02 9:37 Mise en chauffe

Maher signal que des tests ont
ete fait sur le canon, leger risque de claquage.
 7x 
  1006   Fri Jan 24 17:39:00 2025 MV, IC, VK, RCUnder ProcessShift summaryRing Commissioning   08h45 Start Thomx: Modulator, frigo, laser

08h50 Start chillers, cycling all
magnets
 Screenshot_from_2025-01-24_17-35-38_61p5MeV.pngScreenshot_from_2025-01-24_17-34-48_61p5MeV.pngScreenshot_from_2025-01-24_17-34-23_61p5MeV.png 
  1005   Fri Jan 24 08:45:26 2025 MV, IC, VK, RCUnder ProcessShift summaryRing Commissioning   08h45 Start Thomx: Modulator, frigo, laser

08h50 Start chillers, cycling all
magnets
  
  Draft   Thu Jan 23 17:03:45 2025 Ring team AnneauRing Commissioning Ring Working Points 50 MeV/ 61.5 MeV / 70 MeV 50 MeV

Configuration:
 8x 
  Draft   Thu Jan 23 08:44:17 2025 MV, IC, VK, RCUnder ProcessShift summaryRing Commissioning   08h41 Start Thomx: Modulator, Frigo, Laser

08h46 Start chillers, all magnets
sycling
  