7h50: mise en chauffe de la machine en remote (modulateur, frigo/chiller, laser, cyclage aimants)
*** Programme de la 2e semaine de prise de données imagerie X ***
REPEAT
. Lag time measure with different exposure time, last time we did 200ms, go lower.
. Noise Power Spectrum, acquire 20 images with 2 thickness, for example 0 and 3 cm plexi.
. MTF one acquisition
.Tomography
NEW
. Wire
. Wedge Phantom
10h44 Beam is in the ring. RF Gun phase 10 dg., Sect. phase 207 dg., Sect. Att. 2.59 dB, Charges: -137pC, -135 pC, -147 pC
Linac steerers: H [0.55 -2.82], V [-2.62 2.86], TL/BPM2 X=4 mm -> 3 mm
11h09 RF Gun phase 11 dg., Sect. phase 208 dg., Sect. Att. 2.53 dB,
12h15 RF Gun phase 2 dg., Sect. phase 207 dg., Sect. Att. 2.61 dB, TL/BPM2 X=3 mm, RFCav. 150 kV Phase -19.5 dg.
13h49 Linac was readjusted: Gun phase -2 dg., Sect. phase 212 dg., Sect. Att. 2.53 dB, TL/BPM2 X=4.3 mm, RFCav. 150 kV Phase -19.5 dg.
14h07 Linac was readjusted: Gun phase -4 dg., Sect. phase 216 dg., Sect. Att. 2.53 dB, TL/BPM2 X=4.3 mm, RFCav. 150 kV Phase -19.5 dg. I3 current around 40000 pA
17h04 Linac was readjusted: Gun phase -6 dg., Sect. phase 217 dg., Sect. Att. 2.55 dB, TL/BPM2 X=3.7 mm,
18h51: stop thomx
|