ND, Marie Labat; Streak camera 
|
9:20 Start aligning
12:40 Alignement done for both linac and ring.
Health check: Archiving not working |
ND, Manon Philit, Janine Issa; Shift summary 25/10   
|
9 : 34 Mise en chauffe
Health check OK (a part les Redpitaya)
10:25 démarrage faisceau |
ND, MEK; Conditionnement section
|
8:45 Impossible de passer le modulateur en standby.
Probleme d'eau.
Appel Dalkia |
ND, LS, MB, DN, MA, IC, VK, MEK, JNC, MJ, RC; X-rays attempt 22/06 10x
|
9:23: Mise en chauffe
9:29 Cycle magnets
10:20 Acces casemate cavite CFP |
ND, LS, IC, VM, VK; Prise de donnee 27/4/2023 10x
|
9:19: Mise en chauffe
10:24 Cycling magnets
10:50 Demarrage faisceau |
ND, LS, IC, VK, VM, SW; Ring operation 15/5 7x
|
10:00 Machine warm up
Magnets cycling
11:00 Start machine |
ND, LS, IC, VK, VM; Studies on the Ring revolution frequency 8x
|
Goal: understanding of teh beam natural revolution frequency. Study the effect of the dipoles.
We have started from the previous setting of the machine. Then we loaded the settings from last december and received better storage. RF cavity
is OFF. |
ND, LS, IC, VK, VM; RE: Studies on the Ring revolution frequency
|
Bonjour,
Pouvez vous enregistrer les images de l'oscilloscope et le donnée brute à la place des screenshots. Il y a une option dans
l'interface web pour enregistrer l'oscillogramme "proprement". De même pour les images, cela permet de faire des traitements à |
ND, LS; Prise de donnee 26/4/2023 
|
9:24 Mise en chauffe
9:30 Cyclage des aimants
11h44 Démarrage faisceau |
ND, LS; ThomX operations 26/6
|
9:26 Mise en chauffe
9:40 Cycling the magnets
11:45 Beam ON |
ND, IC, VK, VM, ME; Shift 8/12 14x
|
9h: Mise en Chauffe modulateur + Frigo + Laser
Il n'y a plus de perte de pression ce matin. La fuite du Solénoide semble avoir été la cause.
10:05 Acces SPR en fosse pour installation dosimetre Radon |
ND, IC, VK, VM; Shift àf 3/11/2022 9x
|
9:10 Air pressure: 8 bars, water resistivity 6,33Mohm
9:15 Modulator warm-up
9:20 Ronde zone modulateur |
ND, IC, VK, VM; Prise de donnee 6/01 9x
|
9:15 Mise en chauffe modulateur
10:23 Temperature chiller incorrecte
11h Optilization of the beam for injection. Beam is unstable, what is seen fro, the x/y position trends in the TL. Then, from time to time the |
ND, IC, VK, VM; Optimisation LE    
|
15h Scan extraction kicker vs EL/BPM.01.
See attached plots.
Some interferences with ring storage. |
ND, Enzo Crou, Noé Idesheim, Jean-Nicolas Quenot; Prise de donnee 16/3/2023 17x
|
9:15 Mise en chauffe
10:30 Ronde casemate
10:40 Start beam |
ND, Camille Cheney, Mohamed ; Prise de donnees 16/12 9x
|
9h15 Les comptes operateurs etaient restes allumes avec un message d'erreur indiquant que la machine n'etait pas totalement arretee.
Mise en chauffe
9h45 Demarrage Kicker extraction avec MO. |
ND, Anna K, Elene K, Marie L; Prise de donneees 5/02 
|
Coordinator: ND
9h12: Modulator start
PSS: Default centrale SSI |
ND, Anna K, Elene K; Data taking 26/01 7x
|
9:30 Warm-up
11:00 Modulator OFF => restart warm-up
Pb temperature section. |
ND, AM, VC, ML, SC; Programme faisceau 15/9
|
15-09-2022:
Marie Labat, VC, ND, AM
9h30 Mise en chauffe modulateur tombe |
ND VC; Shift summary
|
Demarrage machine 9H
test cyclage: OK (relecture courant parfois NAN)
Correction des fenetre d'intégration de mesure de charge des ICTs |