  Notes concernant la preparation du Commissionning, Page 1 of 3  Not logged in ThomX    logo
Entry   Hayg; WC tests TANGO 

CALC/DG/MeanStd_charge1/ER_CA_rac.05-elr.01-WAC.03_Ch0_chargeMean
CALC/DG/MeanStd_charge1/ER_CA_rac.05-elr.01-WAC.01_Ch0_chargeMean
CALC/DG/MeanStd_charge1/ER_CA_rac.05-elr.01-WAC.02_Ch0_chargeMean
CALC/DG/MeanStd_charge1/ER_CA_rac.05-elr.01-WAC.02_Ch3_chargeMean
CALC/DG/MeanStd_charge1/ER_CA_rac.05-elr.01-WAC.02_Ch4_chargeMean


 

Dans les variables MeanStd :


Charge 1 :

er_ca_rac.05-elr.01-wac.01_Ch0_chargeMean 


Charge 2 :

er_ca_rac.05-elr.01-wac.02_Ch0_chargeMean   
er_ca_rac.05-elr.01-wac.02_Ch3_chargeMean  
er_ca_rac.05-elr.01-wac.02_Ch4_chargeMean  


Charge
    Reply   Hayg; RE: WC tests TANGO Screenshot_from_2021-03-03_11-29-57.png
 




Hayg
wrote:




CALC/DG/MeanStd_charge1/ER_CA_rac.05-elr.01-WAC.03_Ch0_chargeMean
CALC/DG/MeanStd_charge1/ER_CA_rac.05-elr.01-WAC.01_Ch0_chargeMean
CALC/DG/MeanStd_charge1/ER_CA_rac.05-elr.01-WAC.02_Ch0_chargeMean
CALC/DG/MeanStd_charge1/ER_CA_rac.05-elr.01-WAC.02_Ch3_chargeMean
CALC/DG/MeanStd_charge1/ER_CA_rac.05-elr.01-WAC.02_Ch4_chargeMean


 
Entry   IC, VK, AM, VC, ND; Beam requirements for the ring 
The following parameters are required for ring operations:

- At least 50pC on TL/DG/ICT.01 with std <20pC

- At least 20pC on TL/DG/ICT.02 with std <20pC
    Reply   ND; RE: Beam requirements for the ring 
An IHM to check some of these parameters has been created (git/panneaux/StatusInfoIHM_ring_vars.py) and added to Plateforme_IHM...




Quote:



The following parameters are required for ring operations:
Entry   Entered by Hayg Guler from 134.158.195.145 on Tue Nov 19 11:16:25 2019;  
Salle de controle :


installer Xlib pour tout le monde
mettre les environnements en place


IHM vide :


couleurs ??


Chiller :
Entry   Entered by bruni from 134.158.195.142 on Tue Jul 7 14:24:55 2020; test régulation températures canon/section screenshotIHM_RF.png
Ouverture des chillers et du frigo sur place.

Ouverture de l'IHM plateforme

Mise frigo ON et les chillersV
Entry   Entered by bruni from 134.158.195.142 on Wed Jul 8 14:32:48 2020; test moteur solénoide en charge 
Prise de mesure relative entre les deux bobines : 18.7cm avec les alimentations éteintes mais du refroidissement.

Mise en route des alimentations 80A sur la contre champ, et 275 sur la focalisante.

Prise de mesure à nouveau : 18.7cm --> ca n'a pas bougé
Entry   Entered by Sophie Chance from 134.158.195.143 on Thu Jul 16 09:50:21 2020; demarrage à blanc 
debut du démarrage à blanc 9h45. Démarrage prévu par étape.
Entry   Entered by Hayg Guler from 134.158.195.145 on Tue Dec 1 14:34:08 2020;  
Laser :

Camera : mettre le temps d'exposition à 0.2 secondes
Entry   Entered by Hugues Monard from 134.158.195.145 on Thu Dec 3 10:57:47 2020; demarrage a blanc 3 dec 2020 
Bilan démarrage à blanc 3 dec 2020 : (H Monard, S Cavalier)

but : verification etat IHM pour conditionnement RF avec H Monard + JN Cayla

Sur compte H Monard : sur Client2 plateforme IHM ne se lance pas
Entry   Entered by Hugues Monard from 134.158.195.145 on Thu Dec 3 13:44:55 2020; signal photodiode laser photodiode-laser2.png
 
Entry   Entered by Hugues Monard from 134.158.195.145 on Thu Dec 3 13:50:13 2020; signal photodiode 03-12-20 plot.pdf
 
Entry   Entered by Hugues Monard from 134.158.195.145 on Thu Dec 3 15:16:48 2020;  
Signaux RF - REdPitaya 03-12-20

Photodiode laser - RP.04 A

QS RP.04 B
Entry   Entered by Hugues Monard from 134.158.195.145 on Thu Dec 3 15:26:07 2020;  photodiode-Prc_Qs.pdf
signaux photodiode PrC Qs test avec generateur impulsion ! 2 V , 3 µs (bleu ciel)  et signal avec rampe, 1V (moire), photodiode (rose)
Entry   Entered by Hugues Monard from 134.158.195.145 on Wed Dec 9 14:26:20 2020; re-organisation PC-client en SdC 
suite à la discussion de lundi 7 /12/20, les PC clients en SdC ont été déplacés et re-organisé avec les numeros
client1 ,2 , 3 ,4 ,5 dans le sens horaire en salle de controle, en commencant par la gauche en entrant

+----------------------------------------------------------------+
    Reply   Hayg; RE:  
Pour info :


client 1 ne fonctionne pas encore. Il n'a pas été utilisé depuis longtemps, Guillaume a été prévenu
pour y jeter un oeil.
Client 3 et 5 sont maintenant aux places qui n'ont qu'un seul écran. Une MAJ de la salle devra être
Entry   Entered by Nicolas Delerue from 193.55.29.171 on Thu Dec 10 14:42:53 2020; Clients 1, 4 et 5 non fonctionnels 
En complément du message de Hayg, client 4 et 5 ne fonctionnent pas non plus (en plus de client 1).

Nicolas
Entry   Entered by Sophie Chance from 134.158.195.141 on Thu Mar 4 16:35:53 2021; Tests IHM RF  IHM_RF.png
De nouveaux tests ont été fait sur l'IHM RF amélioré (M. Omeich, H. Guler, S. Chance, JN. Cayla)

Tous les redpitayas ont été testés via un générateur de retard.
Entry   Entered by Sophie Chance from 134.158.195.141 on Thu Mar 4 16:45:48 2021;  RDP.01_voie1.pngRDP.01_voie2.png
Test du repitaya 1 voie 1 (Pi section) et 2 (Pr section)

 
Entry   Entered by Sophie Chance from 134.158.195.141 on Thu Mar 4 16:56:07 2021; redpitaya 2 RDP.02_voie1.png
Tests du redpitaya 2 voie 1 (Boucle section) voie 2 est libre