1
|
Tue Nov 19 11:16:39 2019 |
Entered by Hayg Guler from 134.158.195.145 on Tue Nov 19 11:16:25 2019 | Under Process | Shift summary | Prise de donnees |
|
| |
Salle de controle :
- installer Xlib pour tout le monde
- mettre les environnements en place
IHM vide :
Chiller :
- rajouter Rac17 AI1
- voir avec Maher pour faire une IHM
Plateforme IHM
- faire des icones plus gros
- rajouter
Modulateur
- A mettre en remote
- sur l'interface cliquer sur Remote
- mettre les secondes ou barre de progression sur le panneau Modulateur
- plutot de d'aller sur Jive
Laser
- voir la procédure pour le démarrage
- Ampli
- Oscillateur
- Synchro
- Lame demi-onde (equivalent de la densité optique) -- LI/OP/OPT.01.Att.01
- sera dans l'IHM
- pour tuner l'energie Laser
- on devra faire la calibration
|
|
2
|
Tue Jul 7 14:25:15 2020 |
Entered by bruni from 134.158.195.142 on Tue Jul 7 14:24:55 2020 | Under Process | Shift summary | Prise de donnees |
|
test régulation températures canon/section | |
Ouverture des chillers et du frigo sur place.
Ouverture de l'IHM plateforme
Mise frigo ON et les chillersV
canon à 6V, et section à 6.3V
Mise à jour de l'état des boutons verts frigo et chiller
trend température, ajouter autoscale, bouton clear ne semble pas marcher
On met la consigne canon à 7V, la température monte à 33 degrés
Si le frigo s'arrete, il se met en défaut. La température monte au niveau des chillers, qui sont bridés à 10V (50 degrés).
Il faut récupérer l'état des chillers (booleen qui va venir d'un cablage des chillers, et à connecter à l'automate). Si un des états est off et que la RF est ON, il faut couper la RF (trig modulateur).
|
| Attachment 1: screenshotIHM_RF.png
|
 |
|
Draft
|
Wed Jul 8 14:33:04 2020 |
Entered by bruni from 134.158.195.142 on Wed Jul 8 14:32:48 2020 | Under Process | Shift summary | Prise de donnees |
|
test moteur solénoide en charge | |
Prise de mesure relative entre les deux bobines : 18.7cm avec les alimentations éteintes mais du refroidissement.
Mise en route des alimentations 80A sur la contre champ, et 275 sur la focalisante.
Prise de mesure à nouveau : 18.7cm --> ca n'a pas bougé
On bouge le moteur Translation li/ae/col.01-mot.01 qui doit faire une translation horizontale : +6 mm butée, -25mm.
On remet off les alimentations des solnénoides
L'encodeur pos ne se met pas à jour : on en déduit que le moteu ne marche pas correctement
On fait la translation verticale col01-mot.02
|
|
16
|
Thu Mar 4 16:36:12 2021 |
Entered by Sophie Chance from 134.158.195.141 on Thu Mar 4 16:35:53 2021 | Under Process | Shift summary | Prise de donnees |
|
Tests IHM RF | |
De nouveaux tests ont été fait sur l'IHM RF amélioré (M. Omeich, H. Guler, S. Chance, JN. Cayla)
Tous les redpitayas ont été testés via un générateur de retard. |
| Attachment 1: IHM_RF.png
|
 |
|
17
|
Thu Mar 4 16:46:04 2021 |
Entered by Sophie Chance from 134.158.195.141 on Thu Mar 4 16:45:48 2021 | Under Process | Shift summary | Prise de donnees |
|
| |
Test du repitaya 1 voie 1 (Pi section) et 2 (Pr section)
|
| Attachment 1: RDP.01_voie1.png
|
 |
| Attachment 2: RDP.01_voie2.png
|
 |
|
18
|
Thu Mar 4 16:56:19 2021 |
Entered by Sophie Chance from 134.158.195.141 on Thu Mar 4 16:56:07 2021 | Under Process | Shift summary | Prise de donnees |
|
redpitaya 2 | |
Tests du redpitaya 2 voie 1 (Boucle section) voie 2 est libre |
| Attachment 1: RDP.02_voie1.png
|
 |
|
19
|
Thu Mar 4 16:57:46 2021 |
Entered by Sophie Chance from 134.158.195.141 on Thu Mar 4 16:57:33 2021 | Under Process | Shift summary | Prise de donnees |
|
tests redpitaya 3 | |
Tests des redpitayas 3 voie 1 (Pi canon) et voie 2 (Pr canon) |
| Attachment 1: RDP.03_voie1.png
|
 |
| Attachment 2: RDP.03_voie2.png
|
 |
|
20
|
Thu Mar 4 16:59:43 2021 |
Entered by Sophie Chance from 134.158.195.141 on Thu Mar 4 16:59:30 2021 | Under Process | Shift summary | Prise de donnees |
|
tests redpitaya 4 | |
Tests des redpitaya 4 voie 1 (Photodiode) et voie 2 (Q section) |
| Attachment 1: RDP.04_voie1.png
|
 |
| Attachment 2: RDP.04_voie2.png
|
 |
|
21
|
Thu Mar 4 17:07:32 2021 |
Entered by Sophie Chance from 134.158.195.141 on Thu Mar 4 17:07:19 2021 | Under Process | Shift summary | Prise de donnees |
|
Tests IHM RF | |
Les tests se sont bien déroulés, on observe bien les signaux correspondants au redpitayas demandés.
Il faudra faire une modification sur l'IHM car tango bloque par moment et cela "freeze" l'IHM que l'on doit complètement redémarrer. |
|
25
|
Fri Sep 2 08:51:46 2022 |
MO | | Shift summary | etc |
|
démarrage | |
8h35 mise sous tension: PSS, LB9000, modulateur, chillers |
|
27
|
Mon Sep 19 16:29:06 2022 |
IC, VK, VI, VC, JH, HG, ND | New Solution | Shift summary | Prise de donnees |
|
Ring objectives | |
This entry is to be updated as the work progresses.
1) Re-establish beam transport to ring
2) Scan in time the septum
see script git/panneaux/Synchro/scan_septum.py
3) Scan in voltage the septum
4) Adjust timing of kicker by looking at induced noise on ICTs
5) Scan in time the kicker
git/panneaux/Synchro/scan_kicker.py
6) Scan in voltage the kicker
7) Transport further in the ring by playing with correctors
Note: When possible Alexandre will test his feedback code. |
|
30
|
Mon Sep 26 10:21:20 2022 |
IC, VK, VI, VC, JH, HG, ND | New Solution | Shift summary | Prise de donnees |
|
RE: Ring objectives | |
(1), (2), (4) and (5) from last week have been done other items in progress.
New to do list:
(0) Re-establish beam transport to ring
(1) Monitor incident power on RF Gun
(2) Check energy jitter in TL/BPM.02 and TL/SST.02
(3) Use TL optimised transport when available
(4) Compare single pass and TbT BPM signals
(5) Test Alexandre's feedback code.
(6) Scan correctors to increase current on RI-C1/BPM.01 and RI-C2/BPM.06
(7) Start align beam in quadrupoles
| Quote: |
|
This entry is to be updated as the work progresses.
1) Re-establish beam transport to ring
2) Scan in time the septum
see script git/panneaux/Synchro/scan_septum.py
3) Scan in voltage the septum
4) Adjust timing of kicker by looking at induced noise on ICTs
5) Scan in time the kicker
git/panneaux/Synchro/scan_kicker.py
6) Scan in voltage the kicker
7) Transport further in the ring by playing with correctors
Note: When possible Alexandre will test his feedback code.
|
|
|
34
|
Wed Oct 5 09:51:12 2022 |
IC, VK, VI, VC, JH, HG, ND | New Solution | Shift summary | Prise de donnees |
|
RE: RE: Ring objectives | |
New to do list:
(0) Re-establish beam transport to ring
(0bis) Check energy jitter in TL/BPM.02 and TL/SST.02
(1) Try to merge TL optimised transport with ring injection transport => record beam size on TL/SST3 and position on TL/BPM.03 and TL/BPM.04 for current ring transport
(2) Reduce betatron oscillations
(3) Measure and correct orbits
(4) Measure Tune
(5) BBA
(6) Improve charge transport at injection
(7) Start MRSV
| Quote: |
|
(1), (2), (4) and (5) from last week have been done other items in progress.
New to do list:
(0) Re-establish beam transport to ring
(1) Monitor incident power on RF Gun
(2) Check energy jitter in TL/BPM.02 and TL/SST.02
(3) Use TL optimised transport when available
(4) Compare single pass and TbT BPM signals
(5) Test Alexandre's feedback code.
(6) Scan correctors to increase current on RI-C1/BPM.01 and RI-C2/BPM.06
(7) Start align beam in quadrupoles
| Quote: |
|
This entry is to be updated as the work progresses.
1) Re-establish beam transport to ring
2) Scan in time the septum
see script git/panneaux/Synchro/scan_septum.py
3) Scan in voltage the septum
4) Adjust timing of kicker by looking at induced noise on ICTs
5) Scan in time the kicker
git/panneaux/Synchro/scan_kicker.py
6) Scan in voltage the kicker
7) Transport further in the ring by playing with correctors
Note: When possible Alexandre will test his feedback code.
|
|
|
|
35
|
Mon Oct 10 10:04:49 2022 |
VK, IC, VI, JH, ND | Under Process | Shift summary | resumes |
|
Summary of the ring commissioning meeting #4 | |
- 300 turns achieved.
- Probably more but limited by libera cut-off frequency.
- Need to measure the injection axis
- Need emittance measurement from the transfer line
- Several measurements are not possible because of lack of progress on the transfer line
|
|
36
|
Mon Oct 10 10:37:43 2022 |
IC, VK, VI, VC, JH, HG, ND | New Solution | Shift summary | Prise de donnees |
|
RE: RE: RE: Ring objectives | |
To do list:
(0) Re-establish beam transport to ring
(0bis) Check energy jitter in TL/BPM.02 and TL/SST.02
(0ter) Measure emittance on TL/SST.03
(1) Try to merge TL optimised transport with ring injection transport => record beam size on TL/SST3 and position on TL/BPM.03 and TL/BPM.04 for current ring transport
définir avec précision les caractéristiques du faisceau en fin de TL pour pouvoir passer au commissioning de l'anneau (et fournir les diagnostics nécessaires pour contrôler ces "bons" réglages de la TL, et savoir qui en est en charge de quoi)
(2) Improve charge transport at injection
(3) Measure and correct orbits
programmer des mesures sur l'anneau permettant d'établir des connexions entre le modèle d'Iryna et l'état actuel de l'anneau (il y a évidemment la mesure des nombres d'ondes
(4) Start MRSV
(5) Measure Tune
| Quote: |
|
New to do list:
(0) Re-establish beam transport to ring
(0bis) Check energy jitter in TL/BPM.02 and TL/SST.02
(1) Try to merge TL optimised transport with ring injection transport => record beam size on TL/SST3 and position on TL/BPM.03 and TL/BPM.04 for current ring transport
(2) Reduce betatron oscillations
(3) Measure and correct orbits
(4) Measure Tune
(5) BBA
(6) Improve charge transport at injection
(7) Start MRSV
| Quote: |
|
(1), (2), (4) and (5) from last week have been done other items in progress.
New to do list:
(0) Re-establish beam transport to ring
(1) Monitor incident power on RF Gun
(2) Check energy jitter in TL/BPM.02 and TL/SST.02
(3) Use TL optimised transport when available
(4) Compare single pass and TbT BPM signals
(5) Test Alexandre's feedback code.
(6) Scan correctors to increase current on RI-C1/BPM.01 and RI-C2/BPM.06
(7) Start align beam in quadrupoles
| Quote: |
|
This entry is to be updated as the work progresses.
1) Re-establish beam transport to ring
2) Scan in time the septum
see script git/panneaux/Synchro/scan_septum.py
3) Scan in voltage the septum
4) Adjust timing of kicker by looking at induced noise on ICTs
5) Scan in time the kicker
git/panneaux/Synchro/scan_kicker.py
6) Scan in voltage the kicker
7) Transport further in the ring by playing with correctors
Note: When possible Alexandre will test his feedback code.
|
|
|
|
|
49
|
Mon Mar 13 09:39:39 2023 |
IC, VM, SC, JH, VC, ND | New Solution | Shift summary | analyse |
|
Summary of the ring commissioning meeting | |
Excitation (betatron oscillation) on the beam observed by exciting it with the extraction kicker => initial measures of the tune.
Tune measured close from expected value.
Reason for oscillation damping is not understood.
The attenatuator of the RF section has to be tuned from time to time to keep the beam energy (beam position on TL/BPM.02).
Energy tolerance of the ring lattice: +/- 1% (but this may affect the transport upstram in the TL).
Next steps:
- Measure oscillations at different cavity power to see how they are affected.
|
| Attachment 1: data_2023-03-10_15-39-12.png
|
 |
| Attachment 2: tbt_x_relative_integer2.png
|
 |
| Attachment 3: tune_simulation.png
|
 |
| Attachment 4: tune.png
|
 |
| Attachment 5: tbt_x_kicker.png
|
 |
|
53
|
Mon May 22 10:05:30 2023 |
IC, VK, LS, JH, ND | New Solution | Shift summary | analyse |
|
Summary of the ring commissioning meeting | |
=== Summary of last week:
- Frequency was reduced to 500.0202MHz but the beam stayed only for 100s of turns
- Good storage was achieved at 500.40MHz:
* Study of the effect of beam energy (linac section attenuator) on the orbit
* first attempts of BBA
=== Measures to do
Thursday: goal store at 500.0202MHz
- Use a spectrum analyser to check the FFT of the BPM electrodes as function of dipole current (Nicolas)
- Scan RF cavity (phase + plunger) at 500.0202MHz (Lisa+ Nicolas)
- check BPM convention (Lisa)
- Adjust beam energy (linac section attenuator and phase) to adjust ring frequency
Friday: Goal increase cavity voltage
- Orbit correction (BBA+SVD) (Iryna + Slava)
- Measure momentum compaction factor
|
|
57
|
Mon Jun 19 09:46:32 2023 |
IC, VK, VM, LS, JH, SC, ND | New Solution | Shift summary | resumes |
|
Summary of the ring commissioning meeting | |
Report from last week:
- Attempted the strategy suggested by Alex
- Comparison of orbit with RF ON and RF OFF helped understand the "natural" frequency of the ring: 500.33MHz
- Attempts to store at 500.22MHz did not sicceed. Storage at 500.27MHz.
Goals for this week:
- Beam on Thursday and Friday
- Work on BBA (IC, VK, VM) + extraction and BPMs (ND, LS)
- Measure below deformation
|
|
59
|
Mon Jun 26 09:57:52 2023 |
VK, IC, LS, ND | New Solution | Shift summary | resumes |
|
Summary of the ring commissioning meeting | |
Discussion mécanique
- Tous les dipoles ont été alignés par rapport à des surfaces de référence
- Le décalage du centre magnétique par rapport au centre mécanique a été mesuré par Cynthia et pris en compte lors de l'installation
- Difficile de décaler les dipoles de l'IP car la table a été ajoutée après et bloque le déplacement des dipoles.
- Pour déplacer tout le demi-anneau RI-C2 l'un des soufflets (près du septum risque d'être limitant). Très long temps d'approvisoinnement si l'on veut de nouveau soufflets.
- Le plus simple pour Rodolphe: bouger les 4 dipoles d'extremité (RI-C[1-2]DP.0[1,4]): 1 heure de travail (pour un test approximatif). Par contre pour revenir à une position intiale c'est 1/2 journée par dipôle.
- Pour réaligner les dipôles il faut que Denis calcul les nouveaux coordonnés.
Question à vérifier:
- est-ce que l'on a de la marge à l'IP pour déplacer les dipôles vers l'extérieur? [Mesure mardi matin avant 10h]
- quelle est la course possible pour le soufflet près du septum?
- Est-ce qu'il est possible de rattraper le fait que la chambre de RI-C2/DP.04 soit trop courte?
Stratégie:
(1) Mesure de la course possible vers l'extérieur des dipôle de l'IP
(2) Calcul par Denis des nouveux coordonnées de tous les dipôles décalés de 1mm vers l'extérieur radialement
(3) Si possible, décalage des 8 dipôles, sinon décalage de 4 dipôles.
Autre besoin:
- Faire étude sur dipôle de rechange en ajoutant des plaques en acier.
===
Objectifs de la semaine:
- Avancer sur l'orbite à 500.33MHz
- BBA
- Déplacement orbite dans IP (avec CFP)
- Vérifier/améliorer transport amont anneau
- Opérations avec ligne d'extraction
|
|
13
|
Thu Dec 10 14:43:07 2020 |
Entered by Nicolas Delerue from 193.55.29.171 on Thu Dec 10 14:42:53 2020 | Not Fixed | Problem | problemes |
|
Clients 1, 4 et 5 non fonctionnels | |
En complément du message de Hayg, client 4 et 5 ne fonctionnent pas non plus (en plus de client 1).
Nicolas |