HOME SBOX THOMX MINICAV Utilities
THOMX orders THOMX installation THOMX commissioning THOMX control command
  Status of commissioning, report also here plots are reports., Page 8 of 24  Not logged in ELOG logo
    Reply   Removing high order modes, posted by Ronic Chiche at ThomX igloo about mechanics | lasers and optics | detectors and electronics Capture.PNG
    Reply   Removing high order modes, posted by Ronic Chiche at ThomX igloo about mechanics | lasers and optics | detectors and electronics 
Entry   Remontage mécanique, posted by Ronic Chiche at Optical room about mechanics 
Entry   Remontage des vérins, posted by Ronic Chiche at Optical room about mechanics 
Entry   Recipies for different FPC power, posted by Ronic Chiche at ThomX igloo about lasers and optics 
    Reply   Recipies for different FPC power, posted by Ronic Chiche at ThomX igloo about lasers and optics 
    Reply   Recipies for different FPC power, posted by Ronic Chiche at ThomX igloo about lasers and optics 
Entry   Primary vacuum to check dust, posted by Loïc Amoudry at Optical room about mechanics | vacuum Image3.jpgImage6.jpg
Entry   Powerup with 2.5ps pulses, posted by Loïc Amoudry at Optical room about lasers and optics report.PNGtek00004.png4A.PNG
Entry   Power shut down on September 23th, posted by Ronic Chiche at ThomX igloo about mechanics | lasers and optics | vacuum | detectors and electronics | cabling | software | utilities 
    Reply   Power shut down on September 23th, posted by Ronic Chiche at ThomX igloo about mechanics | lasers and optics | vacuum | detectors and electronics | cabling | software | utilities 
    Reply   Power shut down on September 23th, posted by Ronic Chiche at ThomX igloo about mechanics | lasers and optics | vacuum | detectors and electronics | cabling | software | utilities 
    Reply   Power shut down on September 23th, posted by Ronic Chiche at ThomX igloo about mechanics | lasers and optics | vacuum | detectors and electronics | cabling | software | utilities img1.jpg
Entry   Power shut down on Saturday the 18th, posted by Ronic Chiche at ThomX igloo about utilities 
    Reply   Power shut down on Saturday the 18th, posted by Ronic Chiche at ThomX igloo about utilities 
Entry   Power shut down on August 29th, posted by Ronic Chiche at ThomX igloo about detectors and electronics 
    Reply   Power shut down on August 29th, posted by Ronic Chiche at ThomX igloo about detectors and electronics 
Entry   Possible causes for the noise in the FP-cavity system, posted by Ronic Chiche at ThomX igloo about mechanics | lasers and optics | vacuum | detectors and electronics 
    Reply   Possible causes for the noise in the FP-cavity system, posted by Ronic Chiche at ThomX igloo about mechanics | lasers and optics | vacuum | detectors and electronics long_run_wihtout_lock_loss.pnglong_run_wihtout_lock_loss_with_optimum_CEP.png
Entry   Polarization, posted by Loïc Amoudry at Optical room about lasers and optics Polar_horiz_trans_P4.PNGPolar_vert_trans_P4.PNGPolar_vert_input.PNG
ELOG V3.1.4-395e101