Status of commissioning, report also here plots are reports., Page 7 of 24
Not logged in
Find
|
Login
|
Help
Full
| Summary |
Threaded
461 Entries
Goto page
Previous
1
,
2
,
3
...
6
, 7,
8
...
22
,
23
,
24
Next
All
ID
Date
Author
Status
Type
Category
Location
Title
Text
52
Fri Aug 30 17:52:41 2019
Ronic Chiche
Fixed
issue
mechanics | detectors and electronics
Optical room
Motor issue
Today, Axis 9 (Z-axis of P1) has blocked
the software which drives all the motors.
impossible to bypass the problem.
53
Tue Sep 3 17:51:04 2019
Ronic Chiche
Fixed
issue
mechanics | lasers and optics | vacuum
Optical room
Vessel cleanliness
looking in the vessel of the FP cavity
using a UV lamp shows a lot of dust... more
dust than outside the cavity !!!
54
Tue Sep 3 18:04:03 2019
Ronic Chiche
Fixed
report
lasers and optics
Optical room
Finesse measurement after mirror cleaning using the spin coater
Following finesse measurements (start @10700):
Clean P1 with SC (water) + isoprop
(wipe) finesse @15000
55
Tue Sep 3 18:06:29 2019
Loïc Amoudry
Fixed
info
lasers and optics
Optical room
Mirrors sent to LMA
Mirrors have been sent today to LMA for
cleaning and maybe annealing (recuit). 3
ULE of ThomX and the fused silicate for injection
56
Fri Sep 6 14:48:14 2019
Loïc Amoudry
Fixed
report
mechanics | vacuum
Optical room
Primary vacuum to check dust
The cavity has been cleaned then put under
primary vacuum (primary pump without vacuum
flow control). Dusts presence was checked
57
Fri Sep 6 14:59:00 2019
Loïc Amoudry
Fixed
info
lasers and optics
Optical room
LMA cleaning technique
Christophe MICHEL told us more precise
informations about spin coater cleaning.
They always clean with pur water
58
Thu Sep 12 16:19:26 2019
Loïc Amoudry
Fixed
report
mechanics | lasers and optics
Optical room
Cavity dust source check
Several experiments have been done in order
to check the potential source of dust in
the ThomX cavity. For each step, we look
59
Wed Sep 25 15:49:28 2019
Ronic Chiche
Fixed
issue
mechanics | detectors and electronics
Optical room
Motor issue
Today again, same problem with axis 9 blocking
the controlling software during the mirror
alignment procedure.
60
Fri Sep 27 10:43:17 2019
Loïc Amoudry
Fixed
report
lasers and optics
Optical room
New Suprasil mirror from LMA
19/09/2019 : email from Chrisophe Michel
about AR coating of LMA mirrors after reading
that Ta2O5 layers can be damaged in vacuum
61
Fri Sep 27 16:17:36 2019
Ronic Chiche
Fixed
info
lasers and optics
Optical room
Finesse measurement
After mirrors were going back from LMA
for cleaning and thermal anealing, they have
been installed in FP cavity for Finesse measurement.
62
Mon Sep 30 11:20:48 2019
Loïc Amoudry
Fixed
info
lasers and optics
Optical room
Diffusion ULE spherical mirror (S3) vs Fused Silicate injection planar mirror (P1)
Observation made with IR Beam Viewer:
The observation of P1 and S3 simultaneously
while locking shows much higher diffusion
63
Mon Sep 30 11:30:32 2019
Ronic Chiche
Fixed
info
lasers and optics
Optical room
Finesse measurement
To complete these observations:
Finesse has been measured
on thursday, right after cleaning the cavity
64
Thu Oct 3 13:49:58 2019
Loïc Amoudry
Fixed
info
mechanics
Optical room
Pneumatic valves
Frederic and Manu from vacuum group came
this morning to fix again the pneumatic valves
which had a leak again.
65
Thu Oct 3 13:53:44 2019
Loïc Amoudry
Fixed
report
vacuum
Optical room
Cavity under vacuum
The cavity is right now at 6.5e-8 mbar
(turbo pumps on for 1 night and ionic pumps
for 3h), primary pumps and turbo pumps are
66
Thu Oct 3 14:00:13 2019
Loïc Amoudry
Fixed
issue
cabling
Optical room
Electrical trouble (disjunction)
The circuit breaker on ThomX cavity drops
@1.5-1.8kW when we turn on 1/2nd
stage of the amplifier or 3rd stage of the
67
Thu Oct 3 18:00:10 2019
Loïc Amoudry
Fixed
report
lasers and optics
Optical room
ThomX amplifier M2
The ThomX M2 has been measured between
1.5-1.6 for x and y
68
Wed Oct 9 10:08:24 2019
Loïc Amoudry
Fixed
info
lasers and optics
Optical room
Improvement holder amplifier fiber
We've added a clamp in the 3rd stage
to prevent the pump fiber from moving and
tilting (it was tilting to the left).
69
Wed Oct 9 10:10:01 2019
Loïc Amoudry
Fixed
info
lasers and optics
Optical room
Free Spectral Range (FSR)
FSR is 33.347 MHz @1e-8 mbar
70
Wed Oct 9 10:16:24 2019
Loïc Amoudry
Fixed
info
lasers and optics
Optical room
Fiber injection and onefive output power
Fiber injection is finished with the new
ThomX stretching CVBG in double pass (+50%
injection power compared to K-BOX CVBG in
71
Wed Oct 9 11:41:11 2019
Loïc Amoudry
Fixed
info
lasers and optics
Optical room
Onefive spectrum and CVBG spectrum
The Onefive spectrum has shifted a little
bit to lower lambda. It's still enough
for the experiment (3mW injection of ampli