  Status of commissioning, report also here plots are reports., Page 1 of 24  Not logged in ELOG logo
Entry   work with HV voltage on the Laselock, posted by Ronic Chiche at ThomX igloo about lasers and optics | detectors and electronics 
   +  Reply   work with HV voltage on the Laselock, posted by Ronic Chiche at ThomX igloo about lasers and optics | detectors and electronics 
   +  Reply   work with HV voltage on the Laselock, posted by Ronic Chiche at ThomX igloo about lasers and optics | detectors and electronics 
Entry   test des vérins ISP 20mm et 6mm, posted by Ronic Chiche at Optical room about mechanics | cabling 
   +  Reply   test des vérins ISP 20mm et 6mm, posted by Ronic Chiche at Optical room about mechanics | cabling 
Entry   test des vérins ISP , posted by Ronic Chiche at Optical room about mechanics | cabling | software 
   +  Reply   test des vérins ISP , posted by Ronic Chiche at Optical room about mechanics | cabling | software CABLAGE_VERINS.pdf
Entry   telescope for Koheras, posted by Huan Wang at Optical room about lasers and optics 2019.06.18_telescope_of_Koheras.jpg
Entry   strange drift (new effect !?!), posted by Ronic Chiche at ThomX igloo about software 
Entry   some changes in the feedback scheme, posted by Ronic Chiche at ThomX igloo about lasers and optics | detectors and electronics Capture.PNG20231108_154711.jpg
Entry   restarting CFP system after the long summer shutdown (RF section conditionning) and Alphanov amplifier issue, posted by Ronic Chiche at ThomX igloo about lasers and optics | detectors and electronics | software Capture.JPGCapture2.JPG
   +  Reply   restarting CFP system after the long summer shutdown (RF section conditionning) and Alphanov amplifier issue, posted by Ronic Chiche at ThomX igloo about lasers and optics | detectors and electronics | software Capture.JPG
   +  Reply   restarting CFP system after the long summer shutdown (RF section conditionning) and Alphanov amplifier issue, posted by Ronic Chiche at ThomX igloo about lasers and optics | detectors and electronics | software Sans_titre.png
   +  Reply   restarting CFP system after the long summer shutdown (RF section conditionning) and Alphanov amplifier issue, posted by Ronic Chiche at ThomX igloo about lasers and optics | detectors and electronics | software Capture.JPG
   +  Reply   restarting CFP system after the long summer shutdown (RF section conditionning) and Alphanov amplifier issue, posted by Ronic Chiche at ThomX igloo about lasers and optics | detectors and electronics | software 
   +  Reply   restarting CFP system after the long summer shutdown (RF section conditionning) and Alphanov amplifier issue, posted by Ronic Chiche at ThomX igloo about lasers and optics | detectors and electronics | software 
   +  Reply   restarting CFP system after the long summer shutdown (RF section conditionning) and Alphanov amplifier issue, posted by Ronic Chiche at ThomX igloo about lasers and optics | detectors and electronics | software 
   +  Reply   restarting CFP system after the long summer shutdown (RF section conditionning) and Alphanov amplifier issue, posted by Ronic Chiche at ThomX igloo about lasers and optics | detectors and electronics | software 
   +  Reply   restarting CFP system after the long summer shutdown (RF section conditionning) and Alphanov amplifier issue, posted by Ronic Chiche at ThomX igloo about lasers and optics | detectors and electronics | software 
   +  Reply   restarting CFP system after the long summer shutdown (RF section conditionning) and Alphanov amplifier issue, posted by Ronic Chiche at ThomX igloo about lasers and optics | detectors and electronics | software 20240906_161926.jpg