127
|
Fri Aug 12 11:46:17 2022 |
Ronic Chiche | Fixed | info | lasers and optics | Optical room | OEwaves lock and Finesse measurement | this morning, I locked the FP cavity with
the OEwaves CW laser and the "Fred fiber
amplifier" used at 500mA of pump current. |
|
|
64
|
Mon Jul 5 14:14:01 2021 |
Manar Amer | Fixed | report | lasers and optics | detectors and electronics | Optical room | OEwaves CW Laser - Phase Noise |
We started measuring the phase
noise on the OEwaves CW laser.
Class
3b
wavelength 1.5 um
The |
  |
|
65
|
Mon Jul 5 14:40:57 2021 |
Manar Amer | Fixed | report | lasers and optics | detectors and electronics | Optical room | OEwaves CW Laser - Phase Noise | a correction on the wavelength of the laser
it is 1030 um
|
|
|
66
|
Mon Jul 5 14:46:44 2021 |
Manar Amer | Fixed | report | lasers and optics | detectors and electronics | Optical room | OEwaves CW Laser - Phase Noise | correction on unit 1030 nm
|
|
|
174
|
Thu Dec 7 09:09:27 2023 |
Ronic Chiche | Fixed | info | lasers and optics | ThomX igloo | New mirrors batch informations | the 2 files describe the specfications
for the 16 mirrors ordered (4 for ThomX +
spare, 4 for SBOX + spare) and the measurements |
  |
|
246
|
Wed Aug 5 11:25:41 2026 |
Ronic Chiche | Under Process | info | mechanics | lasers and optics | cabling | Optical room | Neolase amplifier installation | we have all the adaptor plugs for connecting
the chiller.
so, I tested first the chiller connected |
|
|
247
|
Wed Aug 5 12:22:52 2026 |
Ronic Chiche | Under Process | info | mechanics | lasers and optics | cabling | Optical room | Neolase amplifier installation | now, I connected the chiller circuit to
the amplifier, thanks to the adapters.
chiller IN => blue pipe => |
|
|
248
|
Wed Aug 5 13:49:49 2026 |
Ronic Chiche | Under Process | info | mechanics | lasers and optics | cabling | Optical room | Neolase amplifier installation | pipes are maybe too long ?
we can use the Darcy-Weisbach +
Blasius laws (non linear laws). |
|
|
249
|
Thu Aug 6 14:49:32 2026 |
Ronic Chiche | Under Process | info | mechanics | lasers and optics | cabling | Optical room | Neolase amplifier installation | I drained the chiller to install again
the short pipe (< 1m) in closed loop.
then, I filled again the chiller |
|
|
250
|
Thu Aug 6 15:12:49 2026 |
Ronic Chiche | Under Process | info | mechanics | lasers and optics | cabling | Optical room | Neolase amplifier installation | now, I installed the long pipes (2x 3m)
in closed loop (without the amplifier connected),
but the exact ones used to connect the laser, |
|
|
251
|
Fri Aug 7 10:59:52 2026 |
Ronic Chiche | Under Process | info | mechanics | lasers and optics | cabling | Optical room | Neolase amplifier installation | I cut a small part of the black pipe on
the amplifier side (could it be slightly
deformed by a try with an other type of adapter |
|
|
252
|
Fri Aug 7 11:41:17 2026 |
Ronic Chiche | Under Process | info | mechanics | lasers and optics | cabling | Optical room | Neolase amplifier installation | as soon as I connect the amplifier to the
pipes, the flow decreases to 1.7Lpm.
and the filling process is very |
|
|
176
|
Fri Dec 8 18:59:24 2023 |
Xinyi Lu | Fixed | report | lasers and optics | Optical room | Mounts installation and cavity alignment | Over the last two days, Viktor, Ronic and
I have started to install the mirror mounts
and try to align the cavity. |
|
|
177
|
Thu Dec 14 17:52:53 2023 |
Xinyi Lu | Fixed | report | lasers and optics | Optical room | Mounts installation and cavity alignment | Over the past few days, Viktor, Ronic and
I have continued to align the cavity.
We installed 4 mirrors and monitored the |
 |
|
178
|
Wed Dec 20 10:45:37 2023 |
Xinyi Lu | Fixed | report | lasers and optics | Optical room | Mounts installation and cavity alignment | - Over the last few days, Viktor, Ronic
and I have reinstalled the mounts and realigned
the cavity with CW laser and old mirrors. |
  |
|
7
|
Thu Oct 18 09:42:39 2018 |
Loïc Amoudry | Fixed | report | mechanics | lasers and optics | Optical room | Motors for D-shaped mirrors | Motors have been installed on 16/10/18.
No problem with them.
Effect of the motors tested on |
    |
|
24
|
Fri Dec 21 13:42:43 2018 |
Loïc Amoudry | Fixed | info | lasers and optics | Optical room | Mirrors features, come back from LMA | Mirrors arrived today from LMA. Their features
are damaged.
Photos avant ou après nettoyage, |
  |
|
23
|
Thu Nov 15 13:02:44 2018 |
Loïc Amoudry | Fixed | info | lasers and optics | Optical room | Mirrors cleaning | The new mirrors didn't give expected
results. Then the 4 old mirrors have been
sent to LMA on 12/11/18 for a cleaning and |
|
|
31
|
Fri Dec 6 11:54:58 2019 |
Loïc Amoudry | Fixed | report | lasers and optics | Optical room | Mirror's installed | The initial 400kW SBOX mirrors which have
been cleaned ont 28th of november have been
installed this morning on the SBOX. |
|
|
60
|
Wed Dec 16 12:36:37 2020 |
Loïc Amoudry | Fixed | report | lasers and optics | Optical room | Mirror's cleaning and microscope imaging | On 10th of december 2020 we cleaned the
SBOX mirrors and took microscope images
(the name of the images indicates what they |
14x |