163
|
Mon Nov 15 09:41:50 2021 |
Entered by Maher OMEICH from 134.158.91.212 on Mon Nov 15 09:20:04 2021 | Not Fixed | Problem | Linac Commissionning |
|
RE: IHM | | Ça doit être bon maintenant
|
|
|
408
|
Mon Mar 21 14:45:35 2022 |
Entered by Maher OMEICH from 134.158.91.212 on Mon Mar 21 14:45:17 2022 | | Shift summary | Linac Commissionning |
|
| | ( 10h00 ) Démarrage modulateur et
refroidissement, fermuture casemate et zone
modulateur |
|
|
398
|
Mon Mar 14 13:57:12 2022 |
Entered by Maher OMEICH from 134.158.91.212 on Mon Mar 14 13:56:48 2022 | | Info | RF D1 |
|
| | Bonjour,
Je recommande de mettre une consigne
de tension modulateur de 1000 V au démarrage |
|
|
200
|
Mon Dec 6 11:30:53 2021 |
Entered by Maher OMEICH from 134.158.91.212 on Mon Dec 6 11:30:27 2021 | Under Process | Anneau | Aimants |
|
Tests EPs | | Bonjour, demain mardi 07/12 sera une journée
casemate ouverte pour les tests des éléments
pulsées ( kikers .... ) |
|
|
629
|
Fri Nov 25 15:31:56 2022 |
Entered by Maher OMEICH from 134.158.91.212 on Fri Nov 25 09:58:16 2022 | | Shift summary | RF D1 |
|
| | Vendredi 25/11
Conditionnement Klystron: le conditionnement
du klystron avec RF progresse lentement au |
|
|
420
|
Fri Mar 25 10:26:06 2022 |
Entered by Maher OMEICH from 134.158.91.212 on Fri Mar 25 10:25:42 2022 | Under Process | Problem | RF D1 |
|
modulator | | Pour les problèmes du modulator
j'ai contacté par mail Scandinova,
j'ai relancé hier et aujoud'hui |
|
|
59
|
Fri Jul 30 14:13:35 2021 |
Entered by Maher OMEICH from 134.158.91.212 on Fri Jul 30 14:13:07 2021 | | Shift summary | Linac Commissionning |
|
| | Suite à une panne aléatoire
qui arrêtait le modulateur à
plusieurs reprises le Mardi 27/07 et le Jeudi |
|
|
53
|
Fri Jul 16 14:33:28 2021 |
Entered by Maher OMEICH from 134.158.91.212 on Fri Jul 16 14:31:16 2021 | | Linac | Linac Commissionning |
|
| | Activité semaine passée
Canon
-Montage canon
sur la poutre fait
-Premiers mesures canon
bas niveau sur la poutre réaliser
-Alignement |
|
|
467
|
Mon May 30 09:38:39 2022 |
Entered by MO/SC/VS/HG from 134.158.195.141 on Mon May 30 09:38:24 2022 | Under Process | Linac | Linac Commissionning |
|
Mise en route et faisceau | | Démarrage ThomX (MO,VS,SC,HG)
Eau dans la fosse Nord
Mise en chauffe modulateur et chillers |
 |
|
460
|
Mon May 16 09:38:08 2022 |
Entered by MO/SC/VS from 134.158.195.141 on Mon May 16 09:37:52 2022 | Under Process | Linac | Linac Commissionning |
|
Démarrage linac | | 9h15 : démarrage (MO, SC, VS)
Fermeture de la zone de stockage,
fermeture de la casemate |
  |
|
Draft
|
Fri Jul 15 09:36:19 2022 |
Entered by MJ/SC/JNC from 134.158.195.141 on Fri Jul 15 09:36:06 2022 | Under Process | Linac | Linac Commissionning |
|
Démarrage | | 9h30 Mise en chauffe modulateur et chillers
|
|
|
51
|
Thu Jul 15 12:39:56 2021 |
Entered by Kevin Dupraz from 134.158.195.153 on Thu Jul 15 12:39:32 2021 | Reference Solution | Info | Opt | Linac Commissionning |
|
Alignement PhotoCathode | | L'alignement de la PhotoCatode est
fini. Il est a noter :
- La position de la camera a ete |
|
|
52
|
Thu Jul 15 15:49:36 2021 |
Entered by Kevin Dupraz from 134.158.195.153 on Thu Jul 15 12:39:32 2021 | Reference Solution | Info | Opt | Linac Commissionning |
|
RE: Alignement PhotoCathode | | Le tube de liaison a ete remis, le faisceau
etait legerement decale. Il a ete realigner
sur la PhotoCathode (1mm a gauche de la sortie |
|
|
1066
|
Mon May 12 07:58:58 2025 |
Entered by Kevin Dupraz from 109.222.35.58 on Mon May 12 07:58:41 2025 | Under Process | Shift summary | LI | RF D1 | Vide | Linac Commissionning |
|
shift du 12 mai 2025 : conditionnement GUN | | 8h: mise en chauffe modulateur et frigo/chiller
- problème de lecture de
vide (visible sur toute les jauges LINAC) |
 |
|
445
|
Mon May 2 10:30:35 2022 |
Entered by JNC/VC from 134.158.195.141 on Mon May 2 10:30:21 2022 | Fixed | Linac | Linac Commissionning |
|
Fermeture machine | | Jean Noel a fermé la fosse nord,
Elle est INONDEE, on va faire un ticket aux
infras. |
|
|
372
|
Thu Feb 24 13:37:08 2022 |
Entered by JNC/SC/CB from 134.158.195.142 on Thu Feb 24 13:36:53 2022 | | Linac | Linac Commissionning |
|
Faisceau | | Energie laser = 27 uJ sur la cathode
IHM Camera laser s'est gelé,
impossible de le rouvrir et de voir l'image |
|
|
421
|
Mon Mar 28 16:13:08 2022 |
Entered by JNC/HM/SC from 134.158.195.142 on Mon Mar 28 16:12:52 2022 | Under Process | Linac | Linac Commissionning |
|
Démarrage technique et faisceau | | Démarrage technique général
Tests faisceau jusqu'au dump |
|
|
405
|
Thu Mar 17 17:54:29 2022 |
Entered by JNC/HG/AM/SC from 134.158.195.143 on Thu Mar 17 17:54:14 2022 | Under Process | Linac | Linac Commissionning |
|
Faisceau | | MeanStd fonctionne
Cyclage des dipoles Q01 Q02 et
Q03 fait |
|
|
519
|
Thu Jul 28 11:34:23 2022 |
Entered by JNC from 134.158.206.40 on Thu Jul 28 11:34:09 2022 | Under Process | Linac | Linac Commissionning |
|
Démarrage linac | | Mise en chauffe modulateur
Mise en route chillers et frigo |
|
|
177
|
Tue Nov 23 13:12:37 2021 |
Entered by Iryna Chaikovska from 134.158.89.93 on Tue Nov 23 13:12:22 2021 | Under Process | Other | Aimants | Linac Commissionning |
|
Cyclage quadrupoles | | 23/11/2021
We would like to cycle the quadrupoles
in the linac. The procedure of the cycling |
    |