HOME Prise de donnees MML Controle commande Simulations Notes Hardware Ligne X Laser Interaction Diagnostiques Synchronisation
Commissionning Commissionning Preparation Pannes ShiftCheck
  Toutes les notes concernant les Commissionning de ThomX, Page 55 of 62  Not logged in ThomX    logo
ID Date Author Status Type Category Important Subjectdown Icon Text Attachments
  708   Wed Mar 8 11:47:20 2023 Entered by Marie Jacquet from 134.158.205.47 on Wed Mar 8 11:45:31 2023 Shift summaryLinac Commissionning (suite elog 28 fev) data X_TLBPM02 vs I_Dipole - Plot Mesures/Simul  Tue Feb 28 08:48:29
2023

8H50-demarrage chiller et chauffage
 2023-02-28-I_Dip_vs_X_TLBPM02.png 
  983   Wed Dec 18 08:37:08 2024 VCUnder ProcessShift summaryLinac Commissionning summary shift Dec 18  demarrage chauffage 8h45

le modulateur refuse de passer
en mode standby
  
  602   Mon Oct 24 14:08:11 2022 Entered by Super Team from 134.158.195.141 on Mon Oct 24 14:07:57 2022 ProblemLinac Commissionning positions en mm ont disparu sur lIHM SST Les positions en mm ont disparu sur lIHM
SST !

est-il possible de les remettre
  
  66   Wed Sep 15 11:41:45 2021 Entered by Super Team from 134.158.195.142 on Wed Sep 15 11:41:31 2021FixedLinacLinac Commissionning démarrage RF canon _ mercredi 15 septembre Le comportement des claquages à
l'arrière du canon est confirmé
ce jour
  
  65   Tue Sep 14 11:02:13 2021 Entered by Super Team from 134.158.195.142 on Tue Sep 14 11:01:58 2021Under ProcessLinacLinac Commissionning démarrage RF canon _ mardi 14 septembre icon12.gif Démarrage modulateur

Passage de 10 Hz à 1 Hz
--> problème interface réglée
 vide14092021_matin.xcfJauges_vol1et2_15.8dB.pngPompes_ioniques_vol1et2_15.8dB.png 
  64   Mon Sep 13 14:20:56 2021 Entered by Super Team on Mon Sep 13 14:18:35 2021Under ProcessLinacLinac Commissionning démarrage RF canon Checks avants conditionnement du canon

1)
Mise en route des chillers

Température
de consigne : 32°C
 vide13092021.pdfvide13092021.dat 
  1213   Tue Mar 17 08:07:49 2026 KD MJ RC DN VKUnder ProcessShift summaryOpt | Linac Commissionning | Ring Commissioning ENERGY-ANGLE reconstruction : prise de donnees - 17 mars 2026 8h05 : mise en chauffe en remote (frigo/chillers,
modulateur, laser, cyclage)

*** programme : Mesures
  
  1132   Thu Oct 2 08:32:08 2025 Entered by Super Team from 134.158.195.141 on Thu Oct 2 08:31:43 2025Under ProcessShift summaryLI  08h30 ThomX warm-up

08h37 Cycling all magnets

10h20 HV is ON
  
  3   Tue Oct 18 15:12:24 2016 Entered by Hugues Monard from 134.158.89.218 on Tue Oct 18 15:12:09 2016Under ProcessShift summaryresumes   test  2014-05-15_Conditionnement_circulateur_RF_et_canon_PHIN.pptx 
  Draft   Thu Apr 8 21:14:09 2021 Entered by talour from 134.158.205.2 on Thu Apr 8 21:11:41 2021FixedShift summaryPrise de donnees       
  14   Tue Jun 8 14:42:30 2021 Entered by Sophie Chance from 134.158.195.144 on Tue Jun 8 14:42:17 2021Under ProcessQuestionetc   Attenuateur LI/HFI/ATT.02-MOT01 en butée
à 3329
  
  16   Tue Jun 8 14:49:12 2021 Entered by Sophie Chance from 134.158.195.144 on Tue Jun 8 14:48:07 2021FixedInfodocs   LI/HFI/ATT.02-MOT.01 Attenuateur Canon   
  18   Tue Jun 8 15:06:12 2021 Entered by Sophie Chance from 134.158.195.144 on Tue Jun 8 15:05:59 2021FixedInfoetc   ATT02-MOT01 attenuateur canon en butée
à -8 jusque 3329
  
  19   Tue Jun 8 15:58:08 2021 Entered by Sophie Chance from 134.158.195.144 on Tue Jun 8 15:57:55 2021Under ProcessInfoetc   Modulateur remis en chauffe car interlock   
  21   Tue Jun 8 17:16:10 2021 Entered by Sophie Chance from 134.158.195.144 on Tue Jun 8 17:15:58 2021FixedInfoetc   Modulateur OK, HT = 500 V en trig   
  23   Tue Jun 8 17:30:12 2021 Entered by Sophie Chance from 134.158.195.144 on Tue Jun 8 17:29:26 2021FixedInfoetc   Capture ecran modulateur  HT_1100.png 
  26   Wed Jun 9 10:55:06 2021 Entered by bruni from 134.158.195.141 on Wed Jun 9 10:54:54 2021Under ProcessInfoPrise de donnees   le modulateur est en chauffe

Réglages des signaux RF
avec le scope
  
  28   Wed Jun 9 14:03:09 2021 Entered by bruni from 134.158.195.141 on Wed Jun 9 14:02:53 2021Under ProcessShift summaryPrise de donnees   Repérage des chaines de mesures
RF : atention, les coupleurs sur guides indique
une atténation réfléchie
  
  29   Wed Jun 9 14:42:25 2021 Entered by bruni from 134.158.195.141 on Wed Jun 9 14:42:13 2021Under ProcessShift summaryPrise de donnees   On règle l'atténuateur
section à mi_course 800 pas. On règle
le zero de li/hfi/att.01-mot.01 (atténuateur
 tension_puissance_klystron_canon_section.ods 
  53   Fri Jul 16 14:33:28 2021 Entered by Maher OMEICH from 134.158.91.212 on Fri Jul 16 14:31:16 2021 LinacLinac Commissionning   Activité semaine passée
Canon
-Montage canon
sur la poutre fait
-Premiers mesures canon
bas niveau sur la poutre réaliser
-Alignement
  
ELOG V3.1.4-395e101