Entry   Entered by Super Team from 127.0.0.1 on Fri Feb 13 17:38:00 2026; SHift du jour 
The code for laser alignment does not work properly --> done by hand 
H 5.244
V 4.654
Entry   VM && HG; Linac commissioning  Vacc_2026-02-11_11-05-31.pngScreenshot_from_2026-02-11_15-57-35.pngCharge_trend_2026-02-11_17-12-31.png
09h12 Warm-up ThomX: Modulator, Laser, Fridge

09h21 Chillers were started, cycling all magnets.

RF 50 pps
icon1.gif   Entered by Super Team from 127.0.0.1 on Tue Feb 10 18:34:13 2026; Demarrage Linac 
Mesures après remontage de la cale : 1215 V sur le modulateur. ça tient mais encore des claquages
dans le Canon à 0dB. Il faut faire travailler encore un peu demain. 

la suite demain
Entry   Entered by Super Team from 127.0.0.1 on Fri Feb 6 08:26:22 2026;  Screenshot_from_2026-02-06_10-52-58.png
08h25 Warm-up ThomX: Modulator, Laser, Fridge

08h33 Chillers were started, cycling all magnets.

09h31 HV is on. Vacuum: Li/Vac1 4e-9, Li/Vac2 3e-9, Li/Vac3 3e-9, Li/Vac4 1e-9
Entry   KD, HG, VM; Laser PC status Screenshot_from_2026-02-05_17-11-35.png
** l'iris a été changée et est opérationnelle

/!\ problème dans l'offset il faut ajouter 0.5mm à la valeur relu par Tango (pour 1.3mm
il faut mettre 0.8 mm dans l'ATK panel)
Entry   IC, VM; Ring studies 
7h45: mise en chauffe en remote (modulateur, cyclage, laser, frigo/chillers)

08h43 HV is on

RF gun phase (laser phase) for maximum charge is out of the range, close to 360 dg. or 10 dg. Help is needed! 
Entry   IC, VM; Beam studies 
7h45: mise en chauffe en remote (modulateur, laser, frigo/chillers)

08h41 HV is on

08h49 RF gun phase 152 dg., sect phase 208 dg. beam is in the ring W/O RF
Entry   KD MJ RC DN; Position Horiz FPC ("spectres dromadaires") 
7h55: mise en chauffe en remote (modulateur, cyclage, laser, frigo/chillers)
==> plus de trig sur la machine (sur toute la plage de scan de la phase stab du laser PC). ==> OK, je suis une truffe le laser était
"off"
Entry   VM, ND, VC;  
08h35 Warm-up ThomX: Modulator, Laser, Fridge
08h41 Chillers were started, cycling all magnets.

09h40 HV is ON
Entry   IC, VM, ND;  Screenshot_from_2026-01-16_18-28-24.pngScreenshot_from_2026-01-16_13-22-12.pngScreenshot_from_2026-01-16_13-23-01.pngScreenshot_from_2026-01-16_13-31-16MODEl.pngScreenshot_from_2026-01-16_16-02-15LOCO_1it.png
08h29 Warm-up ThomX: Modulator, Laser, Fridge
Chillers were started, cycling all magnets.

10h48 Beam is in the ring after resolving a lot of problems. The receipt loaded: recipe_recipe_LI_TL_RI_all_20260115_18_10_34.txt, with Linac-Tl
Entry   IC; Ring studies Screenshot_from_2026-01-15_11-04-16.pngScreenshot_from_2026-01-15_11-33-33.pngRi_C1_Quads_is_off_Screenshot_from_2026-01-15_18-19-14.pngScreenshot_from_2026-01-15_16-42-27.pngScreenshot_from_2026-01-15_17-36-28after1LOCO.png
08h56 Warm-up ThomX: Modulator, Laser, Fridge
Chillers were started, cycling all magnets.
Low SF6 pressure. 
Entry   VM, RC, MJ, IC; Test Soleno=245, optic issue de la simu Julien Matching 
08h36 Warm-up ThomX: Modulator, Laser, Fridge
8h41 Chillers were started, cycling all magnets.
09h40  HV is ON
Entry   KD; shift du 13 janvier 2026 
7h55 : mise en chauffe en remote (chiller/frigo, laser, modulateur, cyclage)

9h : démarrage, pas de soucis au niveau du trig

16h30 : demarrage anneau pour recette 230A
icon1.gif   Hayg; Monday Shift : Q-scan + Data (Active Learning)  
Mesures du jour : 


Quad scans à QP1 pour voir d'autres points de fonctionnement avec une matcihing anneau correct (Figure de merite <1 ?)

autres
points Solé
autres points Q > 100pC (jusqu'à 300pC)  


Active learning pour données
Entry   KD, IC, VM, RC; shift du 9 janvier 2026 6x
8h05: mise en chauffe en remote (modulateur, frigo/chillers, laser, cyclage)

09h06 HV is ON

10h10 receipt recipe_recipe_LI_TL_RI_all_20260108_17_34_30.txt (242 A BMAD). RF gun phase 226 dg. Sect Att. 2.457 dB, sect. phase 214 dg.
Entry   IC, HG, RC, DN, JM; Test of the new receipt from BMAD Isol = 242 A 13x
8h55: mise en chauffe (modulateur, frigo/chillers, laser, cyclage)

10h20 HV ON

Start with the receipt nominal.  problem with the RF gun laser camera. Solved.
Entry   VM DN MJ KD; shift du 07 janvier 2026 16x
7h55: mise en chauffe en remote (modulateur, frigo/chillers, laser, cyclage)
11h25 HV is ON

Archivage lance
Entry   KD; shift du 06 janvier 2026 2026-01-06_19_17_58_tl_dg_sst_03-ccd_01_RAW.png2026-01-06_19_17_20_tl_dg_sst_03-ccd_01_RAW.png
8h: mise en chauffe en remote (cyclage, modulateur, frigo/chillers, laser)

problème lancement cyclage RI-C1: QP.04, QP.09 et QP.10

Sole 238
Entry   MJ; shift twiss Q1 versus soleno 
Modulateur en chauffe
Alarme rendant impossible clim casemate . Maher envoie un mail a urgencevc
Check Sf6 : 2 bar ==> Appel JN ==> ajout sf6 2.5 bar
Entry   KD; shift du 19 décembre 2025 
7h20: mise en chauffe en remote (frigo/chiller, laser, modulateur, cyclage)

 

*** Programme ***