1165
|
Tue Dec 9 08:00:00 2025 |
KD MJ RC DN | Under Process | Shift summary | Linac Commissionning | Ring Commissioning |
|
shift du 09 décembre 2025 - 70 MeV et 40 MeV | | 8h : mise en chauffe en remote (modulateur,
cyclage, frigo/chillers, laser)
Stockage 70MeV ok, le faisceau |
6x |
|
1164
|
Fri Dec 5 14:48:46 2025 |
Marie Julien Hayg Sophie | | Shift summary | LI | TL | LE | Ring |
|
Matching ring-TL - Recherche des bons twiss pour la TL | | Programme
shift : etudes matching anneau-TL - Recherche
param twiss TL |
|
|
1163
|
Fri Dec 5 08:31:59 2025 |
Entered by Super Team from 134.158.195.141 on Fri Dec 5 08:31:45 2025 | Under Process | Shift summary | Ring Commissioning |
|
| | 08h31 Warm-up ThomX: Modulator, Laser,
Fridge
08h36 Chillers were started, cycling |
|
|
1162
|
Thu Dec 4 08:59:07 2025 |
Entered by Super Team from 134.158.195.141 on Thu Dec 4 08:58:52 2025 | | Shift summary | LI | TL | Ring |
|
Preparation/check of the 70 MeV WP for X-ray run | | Goal: preparation and checking the machine
operation at 70 MeV and 40 MeV (ideally with
X-rays) |
  |
|
1161
|
Wed Dec 3 11:09:12 2025 |
Entered by Super Team from 134.158.195.141 on Wed Dec 3 11:08:54 2025 | Not Fixed | Info | RF Anneau | Linac Commissionning | Ring Commissioning |
|
Demarrage ThomX |
| Soucis Septum : Maher
help |
|
|
1160
|
Tue Dec 2 09:28:15 2025 |
Entered by Super Team from 134.158.205.28 on Tue Dec 2 09:27:54 2025 | Not Fixed | Info | LI | TL | LE | Ring | Diag | Linac Commissionning | Ring Commissioning |
|
Shift ThomX/Xrays : Soucis démarrage |
| Last Recettes for 50 MeV:
recipe_recipe_LI_TL_RI_good_20251127_12_42_51.txt
recipe_recipe_LI_TL_RI_good_20251125_16_42_01.txt |
|
|
1159
|
Thu Nov 27 08:01:20 2025 |
KD | Under Process | Shift summary | Linac Commissionning | Ring Commissioning |
|
shift du 27 novembre 2025 | | 8h: mise en chauffe à distance (modulateur,
frigo/chiller, laser, cyclage)
9h30: Chargement de la recette |
    |
|
1158
|
Wed Nov 26 07:47:52 2025 |
KD MJ VM DN RC | Under Process | Shift summary | Linac Commissionning | Ring Commissioning |
|
shift du 26 novembre 2025 | | 7h50: mise en chauffe à distance
(frigo/chiller, laser, modulateur, cyclage)
11h13 Beam is in the ring, 50 MeV, |
8x |
|
1157
|
Tue Nov 25 09:32:03 2025 |
Entered by Super Team from 134.158.195.141 on Tue Nov 25 09:31:46 2025 | Under Process | Shift summary | Diag | Ring Commissioning |
|
| | 09h31 Warm-up ThomX: Modulator, Laser,
Fridge
09h36 Chillers were started, |
|
|
1156
|
Mon Nov 24 13:22:59 2025 |
ND + JM + HG | Under Process | Shift summary | LI |
|
Prise de données 24/11 | | 9:15 Mise en chauffe
9h30 Arrivée du SPR: testsSSI
ce matin => pas de faisceau avant midi |
|
|
1155
|
Fri Nov 21 08:02:04 2025 |
KD MJ DN Students | Under Process | Shift summary | Linac Commissionning | Ring Commissioning |
|
shift du 21 novembre 2025 | | 8h: mise en chauffe en remote (modulateur,
frigo/chillers, laser, cyclage)
9h: start |
  |
|
1154
|
Thu Nov 20 09:26:33 2025 |
VM, IC | Under Process | Urgent | LI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning |
|
BBA Ring | | Goal: Ring BBA
09h14 Unable to start thomx. Need
help. Probably problem with cooling water. |
 |
|
1153
|
Wed Nov 19 10:43:41 2025 |
HG + JM + ND (aprem) | Under Process | Info | LI | TL | LE |
|
Shift mesure Twiss + Simu |
| 8:30 : demarrage à distance
12:10 : QP7 Scan 1 (Phase section |
7x |
|
1152
|
Tue Nov 18 11:11:33 2025 |
HG, JM, ND | Under Process | Shift summary | LI |
|
Prise de données 18/11 | | 9h Intervention laser
Intervention pour realignement
el/dg/sst.01 |
|
|
1151
|
Tue Nov 18 07:56:42 2025 |
KD | Under Process | Shift summary | Linac Commissionning |
|
shift du 18 novembre 2025 | | 7h50: mise en chauffe en remote de la machine
(laser, frigo/chiller, cyclage)
==> le modulateur ne répond |
|
|
Draft
|
Thu Nov 13 08:00:59 2025 |
KD MJ VM HG | Fixed | Shift summary | LI | TL | LE | Ring | Opt | Linac Commissionning | Ring Commissioning |
|
shift du 13 novembre 2025 - spectres a differentes valeurs de bpmTL2_X | | Apres que Kevin a regle tous les problemes
synchro signal bpm etc etc etc
L'interface SST ne fonctionne |
|
|
1149
|
Wed Nov 12 10:29:49 2025 |
Entered by Super Team from 134.158.76.9 on Wed Nov 12 10:29:34 2025 | Under Process | Shift summary | LI | TL | Ring |
|
| | 15h09 Cycling all magnets
15h12 HV is ON
15h15 The modulator was set to |
|
|
1148
|
Mon Nov 10 16:15:53 2025 |
KD, M2 GI | Fixed | Shift summary | LI | TL | Linac Commissionning |
|
shift du 10 novembre 2025 | | 8h: mise en chauffe en remote (modulateur,
laser, frigo/chiller)
10h: Démarrage machine |
|
|
1147
|
Fri Nov 7 18:45:54 2025 |
Entered by Super Team from 134.158.205.4 on Fri Nov 7 18:45:38 2025 | Under Process | Shift summary | Linac Commissionning |
|
| | 08h34 Warm-up ThomX: Modulator, Laser,
Fridge
08h40 Chillers were started, |
  |
|
Draft
|
Thu Nov 6 08:30:52 2025 |
Entered by Super Team from 134.158.195.141 on Thu Nov 6 08:30:37 2025 | Under Process | Urgent | TL | LE |
|
| | 08h30 Warm-up ThomX: Modulator,
Laser, Fridge
08h36 Chillers were started, |
 |