ID Date Authordown Status Type Category Important Subject Icon Text Attachments
  787   Mon Jul 31 16:57:11 2023 VK, IC. VM, LS Shift summaryRing Commissioning Work on the new optics 9h30 Start of the modulator and laser

Start of the beam. Problem with
charge, the max charge at the end of the
  
  763   Mon Jun 12 14:52:39 2023 VK, IC. VM Shift summaryRing Commissioning Reestablishing running conditions at 500.38 MHz Goal of the shift: Reestablish the good
storage at 500.38 and then try to optimize
the storage and orbit.
 scan_charge_phase_min_0.0_max_360.0_14_32_59.pngScreenshot_from_2023-06-12_15-23-07.pngScreenshot_from_2023-06-12_15-40-14.pngScreenshot_from_2023-06-12_17-38-24.pngScreenshot_from_2023-06-12_17-32-48.png 
  770   Wed Jun 14 18:18:32 2023 VK, IC. VM Shift summaryRing Commissioning Srart of the beam physics measurements The main idea fo this week is to
prepare the beam for the search of the first
X-rays.
 14x 
  771   Thu Jun 15 17:46:40 2023 VK, IC. VM Shift summaryRing Commissioning Orbit correction, BLM in the Ring The BLM detector boxes were installed in
the ring. We connected 3 fibers and 2 scintillator
detectors in th ring to be able to observe
 7x 
  753   Wed May 17 09:16:47 2023 VK, IC. AL Shift summaryRing Commissioning Understanding of the shift in RF frequency 8:40 Start warming up, problem with PSS.
It was restarted.

Problems to start and tune the
 18x 
  Draft   Fri Jun 23 09:47:54 2023 VK, IC, DN, RC, JN Shift summaryRing Commissioning search for X-rays 8h30 Start of the modumator, laser, magnet
cycling

9h45 Beam is ON. Scan charge vs.
  
  754   Fri May 19 18:05:29 2023 VK, IC Shift summaryRing Commissioning RF frequency of the Ring In the morning, after the start-up pf the
machine, scan phase-charge and small tuning
it was possible to store the beam with the
 scan_charge_phase_min_0.0_max_360.0_10_43_35.pngScreenshot_from_2023-05-19_13-50-56.pngScreenshot_from_2023-05-19_13-56-41.pngScreenshot_from_2023-05-19_12-15-50.png 
  574   Mon Oct 3 20:31:09 2022 VK, AL, ICReference SolutionShift summaryRing Commissioning Beam is stored Shift started at 18h

With the current injector settings,
it was difficult to inject.  We loaded
 6x 
  Draft   Fri Mar 3 11:49:50 2023 VK VMNot FixedShift summaryLI | Ring | Linac Commissionning | Ring Commissioning Shift 03 Start modulator; alims;

We cannot start machine. No e-beam.
Timing laser RF? Need help of linac team. 
  
  701   Fri Mar 3 12:08:59 2023 VK VMNot FixedShift summaryLI | Ring | Linac Commissionning | Ring Commissioning RE: Shift 03 evreything is ok

The laser shutter was closed !
Becareful the shutter state is inverted.
  
  702   Fri Mar 3 12:29:49 2023 VK VMNot FixedShift summaryLI | Ring | Linac Commissionning | Ring Commissioning RE: RE: Shift 03 Il se passe des choses pendant la nuit
qui mette les diags de la machine en radent
:
  
  837   Thu Feb 1 08:10:14 2024 VK VC HG SC MEUnder ProcessShift summaryLI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning commitionning 8h10 rémarrage machine chauffage
klystron frigo et chiller

pB DS   calc/er_sy/rac.17-elr.01-rdp.0X.Y 
  
  819   Fri Nov 17 08:28:18 2023 VC/SCUnder ProcessShift summaryLI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | SY | Linac Commissionning | Ring Commissioning Commissionning LE 8h20 demararage machine

laser PC

Frifo chiller
  
  496   Wed Jul 6 09:53:02 2022 VC/NDUnder ProcessShift summaryDiag | Laser | Linac Commissionning RE: Q beam versus E laser Verification resistivite eau:

- 6.7Mo dans la baie 18 (alims)

- 550ko sur la voie 1 dans le local
  
  Draft   Mon Oct 3 14:08:06 2022 VC/KD/SCNew SolutionLinacLinac Commissionning Faisceau linac 13h : MO : Mise en chauffe modulateur et
mise en route refroidissement

14h : Fermeture casemate, démarrage
  
  531   Thu Aug 25 15:43:38 2022 VC/KD/HM/HGUnder ProcessLinacLinac Commissionning Shift Linac + LT 25 aout 2022 14h00 : injection dans la TL avec faisceau
sur TL-SST2

avec les parametres QP1=+1.6A,
  
  921   Tue Sep 24 08:53:33 2024 VC-VMUnder ProcessShift summaryLinac Commissionning Shift summary demarrage modulateur 8h50

"Perle" avait ouvert
les portes de l'igloo.... le clés
 Screenshot_from_2024-09-24_11-15-45.pngScreenshot_from_2024-09-24_11-21-49.pngScreenshot_from_2024-09-24_17-41-23.png 
  926   Fri Sep 27 10:52:33 2024 VC-MJFixedShift summaryLinac Commissionning Demarrage faisceau faisceau... sur Li SST0.1

position laser était à
5.1 2.55 (on ne sait pas pourquoi)
  
  830   Wed Jan 17 08:55:07 2024 VC-KDUnder ProcessShift summaryLinac Commissionning | Ring Commissioning commitionning 8H50

Demarrage chauffage, chiller, et
cyclage aimants
 10x 
  532   Fri Aug 26 08:56:05 2022 VC-CB-KDUnder ProcessLinacLinac Commissionning run du 26 aout 2022 9H

mise en chauffe modulateur

10H modulateur OK
 Etat_Machine_2022-08-26_17-37-28.png2022-08-26_17_34_13_tl_dg_sst_03-ccd_01_RAW_18.png 