302
|
Tue Feb 8 08:54:53 2022 |
Entered by Super Team from 134.158.195.141 on Tue Feb 8 08:54:38 2022 | | Urgent | Linac Commissionning |
|
| |
Bonjour Hayg,
L'IHM RF GUN_Section ne s'ouvre pas merci pour la débloquer
Maher |
|
303
|
Tue Feb 8 09:03:44 2022 |
Entered by Super Team from 134.158.195.141 on Tue Feb 8 08:54:38 2022 | | Urgent | Linac Commissionning |
|
RE: | |
Faut redémarrer les Redpitaya en hard.
| Entered by Super Team from 134.158.195.141 on Tue Feb 8 08:54:38 2022 wrote: |
|
Bonjour Hayg,
L'IHM RF GUN_Section ne s'ouvre pas merci pour la débloquer
Maher
|
|
|
304
|
Tue Feb 8 15:55:24 2022 |
Entered by Super Team from 134.158.195.141 on Tue Feb 8 15:55:10 2022 | | Urgent | Linac Commissionning |
|
| |
salut Hayg,
comment revenir à l'echelle j'ai fait un zoom sur l'affichage des redpy?
Maher |
|
305
|
Tue Feb 8 15:58:07 2022 |
Entered by Super Team from 134.158.195.141 on Tue Feb 8 15:55:10 2022 | | Urgent | Linac Commissionning |
|
RE: | |
tu fais un echappe
| Entered by Super Team from 134.158.195.141 on Tue Feb 8 15:55:10 2022 wrote: |
|
salut Hayg,
comment revenir à l'echelle j'ai fait un zoom sur l'affichage des redpy?
Maher
|
|
|
306
|
Tue Feb 8 15:59:55 2022 |
Entered by Super Team from 134.158.195.141 on Tue Feb 8 15:59:41 2022 | | Urgent | Linac Commissionning |
|
| |
sur le clavier? |
|
307
|
Tue Feb 8 16:04:33 2022 |
Entered by Super Team from 134.158.195.141 on Tue Feb 8 16:04:17 2022 | | Problem | Linac Commissionning |
|
| |
Je pense que l'IHM est morte car elle est figée, il faut redémarrer? |
|
308
|
Tue Feb 8 16:26:48 2022 |
Entered by Super Team from 134.158.195.141 on Tue Feb 8 16:04:17 2022 | | Problem | Linac Commissionning |
|
RE: | |
Oui j'ai l'impression qu'il y a encore un souci avec redpi,
dis moi quand tu les redemarre
| Entered by Super Team from 134.158.195.141 on Tue Feb 8 16:04:17 2022 wrote: |
|
Je pense que l'IHM est morte car elle est figée, il faut redémarrer?
|
|
|
309
|
Tue Feb 8 17:01:51 2022 |
Entered by Super Team from 134.158.195.141 on Tue Feb 8 17:01:37 2022 | | Shift summary | Linac Commissionning |
|
| |
Je laisse le modulateur en fonctionnement cette nuit aussi
Maher |
|
310
|
Wed Feb 9 09:13:04 2022 |
Entered by Super Team from 134.158.195.141 on Wed Feb 9 09:12:42 2022 | | Shift summary | Linac Commissionning |
|
| |
Le modulateur à tourner toute la nuit on position Trig, je démarre un essai de longue durée avec RF dans le canon et la section
Hier aussi nous avions toute l'aprèm de la RF dans le canon et la section
IHM RF signaux ne s'affichent pas, je re-demarre l'IHM |
|
311
|
Wed Feb 9 16:59:58 2022 |
Entered by Super Team from 134.158.195.141 on Wed Feb 9 16:59:36 2022 | | Shift summary | Linac Commissionning |
|
| |
Arret du test longue durée à 17h00, pas d'interlock durant toute la période, pas d'interlock intempestif qui avait avant durant les tests depuis lundi aprèm ( 14h00 )
Maher |
|
317
|
Thu Feb 10 15:48:32 2022 |
Entered by Maher OMEICH from 134.158.91.212 on Thu Feb 10 15:48:04 2022 | | Fix | RF D1 |
|
résumé de l'intervention Scandinova | |
Bonjour
Voici le resumé de l'intervention Scandinova tiré du rapport de l'intervention du 07/02/2022 à 09/02/2022
***********************************
Summary of Work
Replaced EP2316-0008 module
Increased filters on HIU for Standby and HV
Increased filter for IntCom interlock
Suggested some mesh to added between Klystron and rack for EMC protection
Corrected some software parameters relating to filament and SPS to increase functionality
Reduced filters for water flow switches due to glitching averaging
A 24h Long Run was carried out. Modulator kept in HV for 24h prior
Conclusion
Problem did not occur while on site, actions taken to reduce the risk of unneccessary interlocks were taken
***************************************
Cordialement
Maher |
|
319
|
Thu Feb 10 17:24:40 2022 |
Entered by Maher OMEICH from 78.193.58.208 on Thu Feb 10 17:24:23 2022 | | Info | RF D1 |
|
modulateur | |
Bonsoir
Modulateur mis sous tension
Maher |
|
332
|
Tue Feb 15 08:39:25 2022 |
Entered by Super Team from 134.158.195.141 on Tue Feb 15 08:38:46 2022 | | Shift summary | Linac Commissionning |
|
Shift du jour | |
8H30 demarrage chauffage Klystron et thermalisation canon section |
|
349
|
Fri Feb 18 09:04:19 2022 |
Entered by Super Team from 134.158.195.141 on Fri Feb 18 09:04:03 2022 | | Problem | RF D1 |
|
| |
Bonjour
Suite à l'interlock modulateur hier j'étais vérifier sur place et l'interlock était l'eau collecteur klystron, on peut le voir clairement sur l'écran modulateur dans "event", à vérifier si personne n'a touché à l'eau. Scandinova a fait une modification quand il est intervenu pour permettre de passer la turbulance de l'eau du à l'air dans le circuit
Maher
|
|
354
|
Fri Feb 18 17:29:44 2022 |
Entered by Super Team from 134.158.195.141 on Fri Feb 18 16:19:49 2022 | | Linac | RF D1 |
|
| |
le modulateur a fonctionné pendant 2h15 avec HF sans coupure
Arret modulateur 17h30, |
|
358
|
Mon Feb 21 15:44:44 2022 |
Entered by Super Team from 134.158.195.141 on Mon Feb 21 15:44:18 2022 | | Problem | RF D1 |
|
débit collecteur klystron | |
démarrage en hard du l'ordinateur du modulateur
mise en standby modulateur pour cette nuit pour vérifier le pb d'eau.
mise à jour de l'heure et la date de l'ordinateur du modulateur |
|
359
|
Tue Feb 22 08:51:33 2022 |
Entered by Super Team from 134.158.195.141 on Tue Feb 22 08:51:16 2022 | | Problem | RF D1 |
|
| |
Mise en route des chillers
Pas de variation de débit collecteur klystron durant la nuit, on continu ( pas d'intervention sur le réseau eau déminé svp ) |
|
360
|
Tue Feb 22 09:30:14 2022 |
Entered by Super Team from 134.158.195.141 on Tue Feb 22 09:29:58 2022 | | Shift summary | Linac Commissionning |
|
| |
RF en route |
|
363
|
Tue Feb 22 16:10:18 2022 |
CB/JNC/SC/MO | | Problem | Linac Commissionning |
|
CONTROLE A DISTANCE STRICTEMENT INTERDIT |
|
Merci d'avoir d'obligeance d'appeler la salle de contrôle pour toute action, même si ca vous parait anodin |
|
364
|
Tue Feb 22 16:39:32 2022 |
Entered by CB/JNC/SC from 134.158.195.141 on Tue Feb 22 16:39:16 2022 | | Linac | Linac Commissionning |
|
Mesure energie canon | |
Phase energie max = 255 degres
Scan steerer vertical après canon à 2 dB sans la section LIL en sortie canon (SST.01)
Données dans /data/shared/commissioning_tools/20220222/ |