Entry   Entered by Super Team from 134.158.195.141 on Tue Feb 8 08:54:38 2022;  
    Reply   Entered by Super Team from 134.158.195.141 on Tue Feb 8 08:54:38 2022; RE:  
Message ID: 303     Entry time: Tue Feb 8 09:03:44 2022     In reply to: 302
 Author: Entered by Super Team from 134.158.195.141 on Tue Feb 8 08:54:38 2022 
 Status:  
 Type: Urgent 
 Category: Linac Commissionning 
 Important:
 Subject: RE:  
 Icon:  

Faut redémarrer les Redpitaya en hard.

 

Entered by Super Team from 134.158.195.141 on Tue Feb 8 08:54:38 2022 wrote:

Bonjour Hayg,

L'IHM RF GUN_Section ne s'ouvre pas merci pour la débloquer

Maher

 