ID Date Author Status Type Category Important Subject Icon Text Attachments
  426   Mon Apr 4 17:00:13 2022 Entered by Viktor Soskov from 134.158.195.153 on Mon Apr 4 16:59:57 2022FixedInfoLinac Commissionning Laser status Un hublot a ete change Si->CaF2. Energie
UV sur la cathode 52µJ, Iris est dispo.
  
  425   Mon Apr 4 16:01:10 2022 Entered by Super Team from 134.158.195.142 on Mon Apr 4 16:00:51 2022 Shift summaryLinac Commissionning   Démarrage modulateur, chillers   
  424   Mon Apr 4 10:50:19 2022 Entered by Super Team from 83.202.31.199 on Mon Apr 4 10:50:04 2022FixedInfoLinac Commissionning Planning cette semaine    Planning_linac_semaine_du_4_avril.pptxsemaine_4_avril.PNG 
  423   Mon Apr 4 10:08:24 2022 Entered by Super Team from 134.158.195.142 on Mon Apr 4 10:07:56 2022 Shift summaryRF D1 | Linac Commissionning   démarrage modulateur, ronde faite
fosse sud et nord ( inodation fosse nord
coté pompe de relevage/ plus que d'hab.
  
  422   Mon Mar 28 16:54:30 2022 Entered by HM/SC/JNC from 134.158.195.142 on Mon Mar 28 16:54:16 2022FixedLinacLinac Commissionning Arret faisceau Transport du faisceau jusqu'au dump
avec solénoides, steerers et quadrupoles
on
  
  421   Mon Mar 28 16:13:08 2022 Entered by JNC/HM/SC from 134.158.195.142 on Mon Mar 28 16:12:52 2022Under ProcessLinacLinac Commissionning Démarrage technique et faisceau Démarrage technique général

Tests faisceau jusqu'au dump
  
  420   Fri Mar 25 10:26:06 2022 Entered by Maher OMEICH from 134.158.91.212 on Fri Mar 25 10:25:42 2022Under ProcessProblemRF D1 modulator Pour les problèmes du modulator
j'ai contacté par mail Scandinova,
j'ai relancé hier et aujoud'hui
  
  419   Fri Mar 25 08:22:18 2022 VC SC HG NDUnder ProcessLinacDiag | Linac Commissionning commisionning Charge et OTR  demarrage Modulateur 8h20

9h15 temp chiller ok

energie laser 32uJ atténuateur
 12x 
  418   Thu Mar 24 17:26:38 2022 Entered by Super Team from 134.158.195.142 on Thu Mar 24 17:26:25 2022FixedLinacLinac Commissionning Arrêt faisceau     
  417   Thu Mar 24 17:12:01 2022 Entered by ND/VC/HG/SC from 134.158.195.142 on Thu Mar 24 17:11:44 2022Reference SolutionLinacLinac Commissionning Paramètres Faisceau Alignement laser

On retrouve la phase pour la charge
max phi = 313 degres (consigne chiller canon
  
  416   Thu Mar 24 15:41:18 2022 Entered by ND/VC/HG/SC from 134.158.195.142 on Thu Mar 24 15:41:04 2022FixedLinacLinac Commissionning Alignement laser Position moteur M4 avant alignement laser
:

x = 380 et y = 5373
 2022-03-24_15_40_29_li_op_las_02_log_scale_False_despeckle_False_min_scale_0_max_scale_10.png2022-03-24_16_14_17_li_op_las_02_log_scale_False_despeckle_False_min_scale_0_max_scale_10_8.png 
  415   Thu Mar 24 10:34:15 2022 Entered by Nicolas Delerue from 134.158.195.144 on Thu Mar 24 10:34:03 2022FixedFixInfra | Linac Commissionning config clefs PSS Operateurs: VC, SC, ND

Pour memoire, cf photo...
 IMG_20220324_102230_1_copy_1248x1664.jpg 
  414   Thu Mar 24 09:44:28 2022 Entered by Nicolas Delerue from 134.158.195.144 on Thu Mar 24 09:43:47 2022FixedShift summaryDiag | CC | RF D1 Mesures 24/3/2022 Operateurs: ND, VC, SC

===

 
 Screenshot_from_2022-03-24_16-51-36.png 
  413   Thu Mar 24 09:26:22 2022 Entered by Super Team from 134.158.195.141 on Thu Mar 24 09:25:25 2022Under ProcessLinacDiag ThomX -commitionning diag Demarrage modulateur 9H

demarrage chiller 9h15
  
  411   Wed Mar 23 12:52:58 2022 Entered by Super Team from 134.158.195.141 on Wed Mar 23 12:52:44 2022Under ProcessLinacElectronique | Linac Commissionning Test des redpitaya baie 17 Point de départ :

- Signal d'entrée :
Générateur AFG Techtro, Sortie
 6x 
  410   Wed Mar 23 11:10:16 2022 Entered by Maher OMEICH from 134.158.91.212 on Wed Mar 23 11:09:58 2022 Shift summaryLinac Commissionning   10h40 Démarrage modulateur et chillers,
casemate encore ouverte à fermer vers
midi
  
  409   Tue Mar 22 11:28:11 2022 Entered by Super Team from 134.158.195.141 on Tue Mar 22 11:27:07 2022Not FixedLinacLaser | RF D1 Signal Redpitaya Signal Photodiode :

Pour comprendre les échelles
ainsi que le manque de dynamique, Viktor
 Screenshot_from_2022-03-22_11-28-59.png 
  408   Mon Mar 21 14:45:35 2022 Entered by Maher OMEICH from 134.158.91.212 on Mon Mar 21 14:45:17 2022 Shift summaryLinac Commissionning   ( 10h00 ) Démarrage modulateur et
refroidissement, fermuture casemate et zone
modulateur
  
  407   Mon Mar 21 09:53:11 2022 Entered by Iryna Chaikovska from 134.158.195.144 on Mon Mar 21 09:52:37 2022 InfoAimants Cyclage QUAD (TL) The cycling of the following quads ( to
zero current) were tested. The corresponding
cycling cuves were loaded in the DS (checked).
  
  406   Fri Mar 18 10:34:19 2022 Entered by Viktor Soskov from 134.158.195.153 on Fri Mar 18 10:34:03 2022FixedInfoLinac Commissionning Laser status L'energie UV sur la cathode = 30µJ   