| ID |
Date |
Author |
Status |
Type |
Category |
Important |
Subject |
Icon |
|
1059
|
Fri Apr 18 08:23:13 2025 |
VM, IC, ND | Fixed | Problem | LI |
|
Measurements 18/4 | | 08h21 Thomx Started: modulator, frig, laser
08h27 Chillers started, cycling all magnets
09h32 HV is 'ON'
09h34 Cannot control the section attenuator
09h50 The issue with the section attenuator was fixed: its server was shut down and restarted, but it was set to 0 dB!!
11h17 RF Gun phase 171 dg., Sect phase is 211 dg. Att. 2.62 dB, TL/BPM2 X=2mm, Charges (from BPMs at Att. 31 dB): -77pC, -77pC, -86pC . Linac steerere: H [1.03 -3.47], V [-1.88 2.63]
Contradictions with ICTs: -87 pC, -73 pC, -80 pC
Beam in the ring
11h40 RCDS on injection receipt all_20250418_11_39_40, RF cav. at 100 kV, phase 16.5 dg., screanshots
12h03 Linac was reajusted. RF Gun phase is 166 dg., sect. phase is 210 dg. Att. 2.58 dB, TL/BPM2 X=3 mm RF cav. 100 kV, phase 13.5 dg. screenshots
12h10 Ring dipoles were changed from 160.4 A to 159.3 A, ring quads were adjusted and tune as well was set back to 0.17. TL/BPM2 X = 0. Screenshots
12h25 RF Gun phase was adjusted to 161 dg.
15:24 Initial Synchro delay for streak camera: -6.60us. Injection at delay of +99.3e3us
Measurements incuding single shots
Study of the injection and of long decays with the streak camera, cf images. Horizontal scale is 2ms, vertical scale is 600ps.
Operating the streak camera create instabilities on the ring 500MHz that may cause phase problems.
16h47 RF Gun phase is 149 dg. RF cav. was at 200 kV, phase 10.5 dg.
17h26 Stop thomx |
|
1164
|
Fri Dec 5 14:48:46 2025 |
Marie Julien Hayg Sophie | | Shift summary | LI | TL | LE | Ring |
|
Matching ring-TL - Recherche des bons twiss pour la TL | | Programme shift : etudes matching anneau-TL - Recherche param twiss TL
Valeurs ideales TL "de Julien" : betaX = 36 betaY = 36 alphaX = -4.5 alphaY = -4.5 ( = figure of merit tres petit)
==================================================================
Mesures param twiss Q1 (quad scan Q1) - charge ~ 100 pC - 50 MeV
**** Soleno = 230
Compresseur = 55000
emitX = 1.8 betaX = 22 alphaX = -7.5
emitY = 1.5 betaY = 7 alphaY = -1.4
Compresseur = 45000
emitX = 1.7 betaX = 14 alphaX = -5.5
emitY = 1.2 betaY = 4 alphaY = -1.1
Compresseur = 65000
emitX = 2.3 betaX = 25 alphaX = -9
emitY = 3.2 betaY = 7 alphaY = -1.6
Compresseur = 95000
emitX = 2.6 betaX = 11 alphaX = -4.
emitY = 3.3 betaY = 9 alphaY = -2.
**** Compresseur = 95000
Soleno = 220
emitX = 7 betaX = 5 alphaX = -2
emitY = 5 betaY = 4 alphaY = -0.5
Soleno = 200
emitX = 13 betaX = 10 alphaX = 0.85
emitY = 10 betaY = 35 alphaY = 0.6
Soleno = 240
emitX = 7.4 betaX = 18 alphaX = -4.3
emitY = 12 betaY = 50 alphaY = -6
SIMU matching : merit = 9
Soleno = 235
emitX = 2.6 betaX = 14 alphaX = -4.
emitY = 5.4 betaY = 21 alphaY = -3.6
Soleno = 238
emitX = 3.8 betaX = 18 alphaX = -4.3
emitY = 7 betaY = 34 alphaY = -5.2
SIMU matching : merit = 24
Soleno = 245
emitX = 8.8 betaX = 30.4 alphaX = -6.5
emitY = 26 betaY = 81.6 alphaY = -8.5
SIMU matching : merit = 10^-25 ==> Q1-Q7 NO backracked sortie linac: -2.02 / 4.76 / -3.176 / 2.0 / 1.62 / -4.085 / 3.98
Q1-Q7 BACKTRACKED -1.88 / 4.74 / -3.28 / 1.99 / 1.69 / -4.03 / 3.85
Essai de stockage : cf screenshot
2 Remarques :
1) 2 figures of merit tres petites ~ 10^-20 qui donnent des valeurs de TL differentes ....
- Valeurs ideales TL "de Julien" : betaX = 36 betaY = 36 alphaX = -4.5 alphaY = -4.5
- Valeurs du jour : betaX = 30.4 betaY = 81.6 alphaX = -6.5 alphaY = -8.5
A suivre - Trouver Bonne figure of merit + minimisation emittance ....
2) Valeurs QUADs "QP3" utilisee dans la simu RING (quads autour de l'IP) :
QP3 SIMU julien : - 6.7 A
QP3 REEL :
c1_qp8 = -6.02
c2_qp8 = -6.03
c1_qp9 = -6.11
c2_qp9 = -6.0
==> ~ 0.7 A de difference - Pour les autres quads : SIMU vs REEL sont proches.
|
|
1239
|
Mon May 11 09:33:17 2026 |
Vincent | Under Process | Linac | LI | TL |
|
Manip Gplast | | 9h30 test radioprotection OK (mesure en dessous du bruit de fond)
13h30 fenetre installée pompage en cours
14h fin de l'intervention
|
|
1210
|
Thu Mar 12 15:17:49 2026 |
MJ, KD | Fixed | Shift summary | Linac Commissionning | Ring Commissioning |
|
MONOCHROMATEUR - 12 mars 2026 | | Alignement CdTe On-axis a l'oeil
Prises spectres ouvertures fentes2 0.3x0.3 : OnAxis , V+40 , H+40 , H+20 , V+20 , H-20 , H+20 , V-20
-----------------------------------------------------------------------------------------------------------
Alignement MONO parallele au faisceau : Hexa mono Ry_mono = -0.1 deg
----------------------------------------------------------------------------------------------------------
Fente2 OnAxis
Ry = - 2.6 - 0.1 deg (43.6 keV code Kilperic) - R_sample = 5.2 deg
Spectres Fentes2 ouvertes ** 1 x 1 mm
** Max
Ry = - 2.5 - 0.1 deg (44.3 keV code Kilperic)
Spectres Fentes2 ouvertes ** Max
** 1 x 1 mm
** 0.5 x 0.5
** 2 x 2
** 3 x 3
Ry = - 2.45 - 0.1 deg (46 keV code Kilperic)
Spectres Fentes2 ouvertes ** Max
** 0.5 x 0.5
** 2 x 2
Mesure du flux diode calib avec et sans MONO
SANS MONO
Fentes2 ** 1 x 1 mm 12h50-51
** 2 x 2 12h51-52
** 3 x 3 12h52-53
Avec MONO : IMPOSSIBLE trop de bruit de fond
Mesure du flux avec DECTRIS
Ry = - 2.45 ==> Images 404 et 405 (13h11)
Ry = - 2.5 ==> Images 406 et 407 (13h12)
Ry = - 2.6 ==> Images 408 et 409 (13h13)
REF Ry = - 0.1 ==> Images 410 et 411 (13h18)
Fente2 V+40
Ry = - 2.9 - 0.1 deg (39 keV code Kilperic)
Spectres Fentes2 ouvertes ** 1 x 1 mm
** Max
** 2 x 2
Mesure du flux avec DECTRIS
Ry = - 2.9 ==> Images 415 et 416 (13h41)
REF Ry = - 0.1 ==> Images 418 et 419 (13h43)
Prise spectre ref a V+40
Fente2 V+70
Ry = - 3.8 - 0.1 deg (30 keV code Kilperic)
Spectres Fentes2 ouvertes ** 1 x 1 mm
** Max
** 2 x 2
** 5 x 5
** et divers autres
Fente2 H-37
Prise spectre ref a H -37
Pour Ry = - 2.9° (angle mono), R_sample = 6.5° (2theta)
Spectres Fentes2 ouvertes ** 2 x 2 mm
** Max
Fente2 H-64
Prise spectre ref a H -64
Pour Ry = - 3.8° (angle mono), R_sample = 8.5° (2theta) ==> Emean ~ 27keV
Pour Ry = - 3.2° (angle mono), R_sample = 7.3° (2theta) ==> Emean ~ 31.5keV
Fente2 H+36
Prise spectre ref a H +36
Pour Ry = - 2.9° (angle mono), R_sample = 5.5° (2theta) ==> Emean ~ 42keV
Pour Ry = - 3.2° (angle mono), R_sample = 6.1° (2theta) ==> Emean ~ 38keV
|
|
1226
|
Tue Apr 7 07:49:37 2026 |
IC,VM, KD, DN, MJ | Under Process | Shift summary | Linac Commissionning | Ring Commissioning |
|
MONO 61.5 MeV - 07 avril 2026 | | 7h50 : mise en chauffe en remote (frigo/chillers, modulateur, laser, cyclage)
09h30 HV is ON
10h23 Energy = 61.5 MeV, Laser Phase 39 dg., Sect. Phase 225 dg., Sect. Att. 0.952 dB, I_Gun -78.1953 pC, I_Linac -122.7687 pC, I_TL -102.6104 pC RF_Ampl. 148.7161 kV, RF_Phase -45.5 dg.
*** Mesure Monochromateur 61.5MeV ***
* angle initiale mono : Ry_mono(0) = -0.1° (ajouté aux valeurs d'angles pour la position moteur)
* Position fentes initiale [-19;-16]
Point On Axis :
- Angle Mono 1.5° --> position RSample : 3.5°
- Angle Mono 1.6° --> position RSample : 3.7°
- Angle Mono 1.7° --> position RSample : 3.9°
- Angle Mono 1.8° --> position RSample : 4.1°
H +30mm (position hexapod TX = -12):
- Angle Mono 1.8° --> position RSample : 3.7°
- Angle Mono 2° --> position RSample : 4.1°
H +40mm (position hexapod TX = -23):
- Angle Mono 1.8° --> position RSample : 3.6°
- Angle Mono 2° --> position RSample : 4°
H -30mm (position hexapod TX = 53):
- Angle Mono 1.5° --> position RSample : 3.9°
- Angle Mono 1.6° --> position RSample : 4.1°
- Angle Mono 1.8° --> position RSample : 4.5°
H -40mm (position hexapod TX = 64):
- Angle Mono 1.5° --> position RSample : 4°
- Angle Mono 1.6° --> position RSample : 4.2°
- Angle Mono 1.8° --> position RSample : 4.6°
V +30mm (position hexapod TX = 21, TY : 30):
- Angle Mono 1.5° --> position RSample : 3.5°
- Angle Mono 1.6° --> position RSample : 3.7°
- Angle Mono 1.8 --> position RSample : 4.1°
V -30mm (position hexapod TX = 21, TY : -30):
- Angle Mono 1.5° --> position RSample : 3.5°
- Angle Mono 1.6° --> position RSample : 3.7°
- Angle Mono 1.8 --> position RSample : 4.1°
*** Images pilatus (thershold 30keV) ==> position On Axis, avec Rsample = 2°
1.8° :
452 (expo 2s), 453 (expo 5s), 454 (expo 10s), 455 (expo 20s)
1.5° :
456 (expo 20s), 457 (expo 20s), 458 (expo 10s)
2° :
459 (expo 20s), 460 (expo 20s), 461 (expo 30s), 465 (expo 20s)
*** Re-reglage streak camera (car completement dereglee)
longueur paquet : 40 ps fwhm (idem injection et apres injection) |
|
631
|
Mon Nov 28 14:25:46 2022 |
Entered by Marie Jacquet from 134.158.89.45 on Mon Nov 28 14:25:31 2022 | | Shift summary | Linac Commissionning |
|
Lmag STR 3 (steerer après la LIL) | | Nouvelle détermination de Lmag du Steerer 3
Lmag STR3 = 67.6 mm (cf. pj)
Avec ça, la mesure de l'énergie post LIL devrait être de ~50 MeV au lieu des ~52 qu'on trouvait habituellement. |
|
645
|
Wed Dec 7 16:58:54 2022 |
Entered by Super Team from 134.158.195.142 on Wed Dec 7 16:58:42 2022 | | Shift summary | Linac Commissionning |
|
Linac measurements @ différent modulator voltage settings | |
Modulateur : 1070 V
On se met à la phase de l'Emax
Energie : Ekin = 4.55 MeV
Energie après la LIL (1.5dB) :
- 108° sur la LIL --> 1Ekin = 46.6 MeV
- 115° sur la LIL --> 1Ekin = 46.1 MeV
- 115° sur la LIL --> 1Ekin = 46.83 MeV (1.05dB)
la manip realignement premier doublet de dipole semble avoir bien ameliore les choses : plus besoin de mettre str4 a -10 pour s aligner verticalement dans qp5. A verifier !
Pour le shift de demain : Recette de vendredi dernier 15h41 testée et semble fonctionelle jusqu'à l'ecran yag TL/DG/SST.03
1090 :
Phase Qmax -> 125
Phase Emax -> 125 - 50 = 75
Ekin : 4.9 MeV
LIL : 1.5 dB
125 degrés Ekin : 48.4 MeV
116 degrés Ekin : 49.3 MeV
100 degrés Ekin : 48.6 MeV
90 degrés Ekin : 46.3 MeV
|
|
1089
|
Wed Jun 18 12:45:49 2025 |
Entered by Super Team from 134.158.195.141 on Wed Jun 18 12:45:28 2025 | Under Process | Info | Linac Commissionning |
|
Linac measurement + phase + | |
- Phi Qmax ; 324° : Phi Emax : 274°
- Qmax : 70-80 pC (Att : 290°) and 300 pC (Att : 420°)
- Recipt : 50MeV_100pC_20250527_14_10_19.txt
- Att Section : 2.45 dB, phi min disp : 209°
- Quad align done
13h20 : Pause
13h30 ND operateur.
Acces controle
Alignement ligne streak linac
14h50 Laser alignement.
Travail sur chassis laser en cours et prioritaire.
Allumage kicker injection
La voie 19 du generateur de retrad des diags etait toujurs connectee au scope avec le smemes regalges que la voie 8.
On remet les wavecatcher sur les reglages anterieurs.
15h40
img5=HV
img6=Trig
Beam ON
On observe pas de probleme sur les ICT.
Charge IC22 / ICT3 non lue soucis WC ... ? On regarde Spsum sur BPM pour voir que la charge reste constante, les positions sur TLBPM2 ne bougent pas ( X=0.1 Y =2)
Trend de la phase 
pas de mesure de longueur aujourd'hui 
Quelques mesure
Goal: bunch length measurement in the transfert line to improve the model. Parameters to vary : phase (Section) , charge, laser size (? should not play a role), laser length (see with Viktor) |
|
533
|
Mon Aug 29 08:14:22 2022 |
VC | Under Process | Shift summary | Linac Commissionning |
|
Linac commitionning | | 8h15 demarrage regulation température
8h45 chauffage Klystron
10H chauffage ready => machine prete
Phase max : 294 -> 290 -> 258 (12h30)
12h40 : Pause déjeuner
( remplacement des dosimètres d'ambiance ==> présence eau fosse nord: pompe de relevage à démarrer )
14h55 : phase de Qmax : 250
TL-SST01- H -1.37A -V 0.57
Alignement à l'oeil par rapport aux quads (Q1 Q2 Q3) Steerer Linac Str-1 (H -1.52A Str-V 0.37)
Valeurs Iris alligné : 5.9 / 3.51
|
|
1191
|
Wed Feb 11 09:12:35 2026 |
VM && HG | Under Process | Shift summary | LI |
|
Linac commissioning | | 09h12 Warm-up ThomX: Modulator, Laser, Fridge
09h21 Chillers were started, cycling all magnets.
RF 50 pps
1210 --> interlock
1150 : ok
Vacc : vac4 dominates (section)
Q_max (420) = 700 pC !
Alignement cathode à vérifier :
position [X ; Y] : [5.33822878121 ; 4.32296059091]
pente [X ; Y] : [685.183030303 ; 1644.7430303]
error [X ; Y] : [1197.22874693 ; 11425.5175959]
13h38 Standby
14h09 Steereing coils along the section were installed, HV is on, the laser gate was closed
14h10 Sect Att. 30 dB, RF gun Att. 20 dB, HV 1160 ==>1215 V
14h13 All seems OK, Sect. Att. 20 dB
14h15 Sect. Att. 10 dB
14h18 Att. 5 dB
14h20 Att. 3 dB
14h22 Att. 2.44 dB
14h24 interlock, sect. vacuum jumps, restarted
14h30 RF Gun Att. 15 dB. Gun vacuum drops
14h32 Gun Att. 10 dB.
14h34 Interlock, unknown reasone, restarted
14h36 Interlock, unknown reasone, restarted
14h41 RF Gun Att. 8 dB.
14h46 RF Gun Att. 7 dB.
14h50 RF Gun Att. 6 dB.
14h53 RF Gun Att. 5 dB. (Gun vac01 1e-8)
14h55 RF Gun Att. 4 dB.
15h01 RF Gun Att. 3 dB.
15h05 Interlock, restarted (not a vacuum problem)
15h06 RF Gun Att. 2 dB.
15h10 RF Gun Att. 1 dB, Sect Att. 1.44 dB
15h11 Interlock, sect. Vacuum (Vac05), Sect Att. 2 dB
15h15 Interlock, sect. Vacuum
15h20 RF Gun Att. 0.8 dB, Sect Att. 2.04 dB
15h22 Interlock, sect. Vacuum (Vac05)
15h24 RF Gun Att. 0.7 dB, Sect Att. 2.04 dB
15h27 RF Gun Att. 0.6 dB, Sect Att. 2.04 dB
15h32 RF Gun Att. 0.5 dB, Sect Att. 2.04 dB
15h34 RF Gun Att. 0.4 dB, Sect Att. 2.04 dB
15h36 Interlock, sect. Vacuum (Vac05)
15h37 RF Gun Att. 0.3 dB, Sect Att. 2.04 dB
15h39 RF Gun Att. 0.2 dB, Sect Att. 2.04 dB
15h42 RF Gun Att. 0.1 dB, Sect Att. 2.04 dB (gun breakdowns)
15h53 RF Gun Att. 0.0 dB, Sect Att. 2.04 dB (gun breakdowns)
16h00 HV off. 12.5 pps
16h01 HV on
16h07 Gate open, Laser Att. 233, -100 pC, RF Gun phase 103 dg.
16h35 RF Gun phase 103 dg., Sect. phase 221 dg., Sect. Att. 2.36 dB -100 pC. Linac steerers to align QP1 - QP3 H [-0.22 -2.82], V [-2.52 3.15]. Li/BPM01 x=1.8, y =0, but not on the screen
from the code : QP1 - QP3 H [-0.23 -2.82], V [-2.53 3.16].
Charge is oscillating, do not see the reason.
rechecked the laser alignment : it's seems to be within the variations of the beam position. Cannot do better.
Remark concerning the timing ... 25 min more on the trend data (tango, libera side ? ) : see the trend file for the positions.
H : 5.256
V : 4.643
QP1 scan to check the working point.
18h30 Stop |
|
651
|
Mon Dec 12 10:26:13 2022 |
SC/MJ | | Shift summary | Linac Commissionning |
|
Linac + TL divers | | Mise en chauffe modulateur et refroidissement
modulateur 1090 - iris 1.3 - phase ch max 142 - energie max -50 - charge 100 pC - soleno 200 - energie canon Ekin 4.6 MeV
Mesure YAG BPM steerer LI
DIAG probleme : BPM LI : enorme bruit de fond sur X .......... cf pj
passage LIL 1.2 dB - phase 110
STR1H -1.22 ST1V +0.5 STR3H -3 pour s'aligner sur Q1 Q2 Q3
Mesure enegie Ekin = 50.7 MeV vers midi
Mesure Yag Bpm steerer TL
Passage dipole 160.5
Etudes alignement Q4 a Q7
DIAG probleme : YAG TL2 camera coupee au milieu ......... cf pj
RE mesure energie 14h Ekin = 49.8
|
|
808
|
Tue Oct 24 10:58:26 2023 |
CB,KD,SC | | Linac | LI | Linac Commissionning |
|
Linac | | 8h30 Mise en chauffe modulateur (MO)
Problème synchro, Intervention
10h30 Réglage du laser dans l'iris avec M5, iris = 0.8 pour etre homogene, taille de sigx = 0.22 et sigy = 0.23mm rms. feedbackM4 mis en route à 5.24/2.91mm
Charge phase
HT modulateur = 1090 V
Mise en route cavité RF
Passage de la position laser avec M4 de (5.24,2.91) à (4.92,2.35)
Position moteur soleno initiale : LI/AE/COL.01-MOT.01 = 0.8 mm; LI/AE/COL.01-MOT.02 = 3.3 mm; LI/AE/COL.02-MOT.01 = 10.201 mrad ; LI/AE/COL.02-MOT.02 = -4.9 mrad;
recherche position sur celle du courant d'obscurité : 5.1/2.55
scan charge phase@14h27, Qmax @200degrés, et focmax @ 207 degrés
Alignement Laser PhotoCathode :
* On utilise le courant d'obscurité pour centrer le photo-courant (à la phase de focalisation max), cf. figure projections
* Le faisceau semble plus symétrique et ne bouge pas à l'écran LI/SST1 à quelques pixels près (sauf en vertical, dérive de 50pixel pour 10° de phase à partir de la focalisation max)
* Nouvelle valeur position Laser : Horizontal : 5.1mm, Vertical : 2.55mm
réalignement soleno : LI/AE/COL.01-MOT.01 = 1.32 mm; LI/AE/COL.01-MOT.02 = 3.32 mm; LI/AE/COL.02-MOT.01 = 7.58 mrad ; LI/AE/COL.02-MOT.02 = -3 mrad;
Mesure d'énergie sortie Canon (phase focalisation max - 50°) : 4.96 MeV (1090V) et 4.98 MeV (1100V), phase 159 degrés pour référence par rapport au charge phase
Scan dim VS Solénoide ci joint, zoom fait avec 10% of full intensity --> pas de saturation mais image très bruitée
solenoide à 189A, reglage steerer li = 1h= 0.9, 1V -0.7, 2H -1.7A, 2V 1 A
scan QP3 pour QP1= +1.8, et qp2=-2.2A, sterers linac : li = 1h= 1.5, 1V -1.9, 2H -2A, 2V 1.9 A
Start scans of QP3 tomorow recette sauvée linac + TL straight (laser pos : 5.1/2.55), and energy spread tuning
|
|
809
|
Wed Oct 25 08:59:10 2023 |
CB | | Linac | LI |
|
Linac | | Température canon à 31.75° modifiée hier
8h59 Mise en chauffe modulateur et chillers
Tests interface start for ring
Scan charge phase, foc max à 221°, charge max à priori à 219°
Laser : Iris = 0.8 mm, Prise d'images dans dossier image laser, feedback on, position iris = (5.1,2.55)
Chargement de la recette d'hier, mode linac, pas de dipole meme si indiqué sur la recette.
11h15 modification du faisceau sur yag TL/DG/SST.01 (forme transverse complétement différente en visuel sur la caméra plus décalage du faisceau vers la droite en regardant la caméra)
Prise d'Image sur TL/DG/SST.01 phi=171°
Pause
A faire cette apres midi : scan d'emittance
(0.24V) le réfléchi disparait par intermittence sur le RF_plot
Scan emittance philaser 171°(dim_QP3_180A) et philaser 165° (dim_QP3_180A_2) philaser 173° (dim_QP3_180A_3) variation QP3 de -1 à 1 A, et QP1=1.8A, QP2=-2.2A
Scan dim_QP1_180A -2A < QP1 < 2A phi section = 111°
philaser 172° Phi section 118° :
dim_QP2_180A
dim_QP3_180A_4 scan de QP3 de -2A à 2A
phase canon et section ajustée sur l'écran LT SST2 spot min sans quads sans steerers TL phase gun 172, phase section 105
On refait un scan avec uniquement QP3 sur TL_SST1 à ces valeurs ( dim_QP3_5)
Positionnement au centre de l'écran sur TL/DG/SST.02, Rotation du faisceau observée lors de la mise en route de QP5
Faisceau au centre de l'écran équivaut à un décalage dans les bpms de quelques millimètre (cf dossier bpm_centrage du répertoire Mesure/today)
Scan de QP4 observé sur TL/SST.02 sans autres quads (QP1, QP2 et QP3 sont à zéro), TL/PS/STR.01-V.01 = -2A tous les autres steerers de la TL sont à zéro. (steerers de la LI identiques à précedemment)
Mise en place des valeurs des quadrupoles de la recette anneau à 500.25 MHz en gardant les réglages linac d'aujourd'hui. Prise d'image sur TL/SST.03 et enregistrement recette.
--> Recette test TL + LE enregistré avec les valeurs des quadrupoles anneau de 500.25 MHz, un seul steerer pour toute la TL.
Solenoide à 220A au lieu de 180A, visu sur camera TL/SST.02,
Phase laser = 172°, phase phase section = 105° attenuateur section 1.855dB
Demain : demarrage sur le point avec soleno 180A, vérification des phases et chargement de la recette presque sans steerer avec les valeurs quads et soleno donné par l'équipe anneau
Injection dans l'anneau reprise si nécessaire manuelle des steerers 3 et 4. Constatation ensemble des décalages bpms écrans dans la TL.
|
|
810
|
Thu Oct 26 09:02:33 2023 |
VC,SC, ND, IC, VK, CB, V | | Linac | LI | TL | Ring |
|
Linac | | 8h30 Mise en chauffe
Pas d'internet sur client1 et client2
9:45 Pb Database Tanngo.
10:10 Ticket 13100 mis au CC
10:16 Le CC constate le probleme.
10:20 Defaut centrale SSI intermittent
10h57 Defaut tango camera corrigé partiellement, permettant de faire du faisceau aujourd'hui, mais investigation plus poussée à faire
10h58 Re-démarrage des caméras
11h12 phase foc max = 215° phase utilisée 165°
12h Chargement recette de l'anneau, remise en place des solenoides comme avant changement de la veille, remise en place du laser et réglage anneau et stockage à 500.25 MHz
13h30 remise en route dephasage cavité RF, remise en place de la valeur de la phase
14h58 Stockage dans l'anneau apres mesures linac
Mise en place des réglages linac d'hier pour tests sur injection anneau
réajustement des valeurs de steerers TL pour optimisation de l'injection.
prises des images dans ces conditions et données anneau
Préparation de 180A en modifiant QP2 et 3 uniquement. A tester sur l'anneau
Quad scan à 180A et à 220A
Arret |
|
713
|
Mon Mar 13 13:54:31 2023 |
MJ | Not Fixed | Urgent | Linac Commissionning |
|
Le bouton PHASE CANON sur le panneau IHM NE FONCTIONNE PLUS !!!!!!!!!!! | | Le bouton PHASE CANON sur le panneau IHM NE FONCTIONNE PLUS !
plus d'acces a la phase canon.
Nicolas t'as fait qqchiose ? |
|
953
|
Tue Nov 5 17:30:10 2024 |
Entered by Viktor Soskov from 134.158.195.153 on Tue Nov 5 17:29:48 2024 | Fixed | Info | Laser |
|
Laser-cathode | | Bonjour, le laser (miroirs du parcours optique) a ete realigne.
L'etat actuel: l'enrgie sur la cathode ~ 80µJ ( Iris 1.3mm, Att 420)
Viktor. |
|
984
|
Wed Dec 18 11:59:49 2024 |
Entered by Viktor Soskov from 134.158.195.153 on Wed Dec 18 11:59:34 2024 | Fixed | Info | Laser |
|
Laser-cathode | | Bonjour, le laser-cathode a ete realigne (miroir M5, miroir dans la salle laser). L'energie UV sur la cathode 55 µJ, Iris =1.3mm; Att=440 |
|
344
|
Wed Feb 16 11:25:44 2022 |
Entered by Viktor Soskov from 134.158.195.153 on Wed Feb 16 11:21:22 2022 | Fixed | Info | Linac Commissionning |
|
Laser status, entered from 134.158.195.153 | | Le fasceau laser est bloqué avec l'option "Gate_Int" - True,False |
|
281
|
Wed Jan 26 16:40:57 2022 |
Entered by Viktor Soskov from 134.158.195.153 on Wed Jan 26 16:40:42 2022 | Fixed | Info | Linac Commissionning |
|
Laser status | | J'ai arreté laser. Vous pouvez le allumer, si vous en aurez besoin. |
|
299
|
Fri Feb 4 10:39:26 2022 |
Entered by Viktor Soskov from 134.158.195.153 on Fri Feb 4 10:39:11 2022 | Fixed | Info | Linac Commissionning |
|
Laser status | | L'énergie IR du laser a chuté de 1.9 à 1.4mJ. Des taches d'aeu ont été aperçues sur le boitier d'ampli. Il faut ensisager ~ 2 jours pour nettoyer l'optique d'ampli + réaigligment. Si je ne arriverais pas, il faut envisager une visite d'Amplitude. |
|