  Toutes les notes concernant les Commissionning de ThomX, Page 37 of 58  Not logged in ThomX    logo
Entry   MOEntered by Super Team from 134.158.195.141 on Wed Jun 1 11:02:17 2022; remplacement SF6 
Entry   MO/SC/HG, JNC/CB; Demarrage et faisceau charge_phase__at_31-05-2022__10-39-33.jpg
Entry   Entered by MO/SC/VS/HG from 134.158.195.141 on Mon May 30 09:38:24 2022; Mise en route et faisceau charge_phase__at_30-05-2022__14-50-15.jpgAlignement_laser__at_30-05-2022__14-59-01.jpg
Entry   Entered by Super Team from 134.158.195.141 on Tue May 24 09:09:19 2022; Démarrage pour faisceau aujourd'hui 
Entry   Entered by Super Team from 134.158.195.141 on Mon May 23 09:11:49 2022;  Alignement_laser__at_23-05-2022__11-28-01.jpgPhase_rf_vs_Isoleno.jpg
Entry   HG / MJ ; Mesures alignement solénoide  2022-05-18-Shift_Hayg.pdf
Entry   Entered by VC/SC from 134.158.195.142 on Thu May 19 13:13:02 2022; Démarrage faisceau 2022-05-19_14_44_35_li_dg_sst_01-ccd_01_RAW.pngScreenshot_from_2022-05-19_19-00-29.png
Entry   Entered by HG from 134.158.195.142 on Thu May 19 12:54:21 2022; Donnees laser 
Entry   Entered by VC, JNC, SC, HG from 134.158.195.141 on Thu May 19 08:55:39 2022; Mesure courant obscurité 
Entry   Entered by MO/SC/VS from 134.158.195.141 on Mon May 16 09:37:52 2022; Démarrage linac 2022-05-16_10_05_11_li_op_las_02_RAW.pngRediptayas_modulateur.pngcharge_phase__at_16-05-2022__11-07-11.jpg
Entry   Entered by Super Team from 134.158.195.141 on Fri May 13 17:16:11 2022; Démarrage impossible (JNC/HG) 
Entry   Entered by Super Team from 134.158.195.141 on Thu May 12 15:29:50 2022; mesure impultion laser sur table optique 
Entry   Entered by Super Team from 134.158.195.141 on Wed May 11 18:32:20 2022; Run machine : JNC/HG 2022-05-11_18_45_12_li_op_las_02_log_scale_False_despeckle_False_min_scale_0_max_scale_350.png2022-05-11_18_51_09_li_op_las_02_log_scale_False_despeckle_False_min_scale_0_max_scale_350.png2022-05-11_19_01_22_li_op_las_02_Iris1.5mm_log_scale_False_despeckle_False_min_scale_0_max_scale_300.pngScreenshot_from_2022-05-11_21-15-19.pngScan_pos_phase_LIL__at_11-05-2022__21-34-50.png
Entry   CB/HG/SC/HM/JNC; Charge phase charge_phase__at_10-05-2022__14-20-56.jpgAlignement_laser__at_10-05-2022__15-05-16.jpgpointfinal_10052022.pngScan_pos_phase_LIL__at_10-05-2022__21-38-25.pngScan_pos_phase_LIL__at_10-05-2022__21-49-51.png
Entry   Entered by Super Team from 134.158.195.141 on Tue May 10 14:03:41 2022; Faisceau sur le premier ecran LI/DG/SST.01 2022-05-10_14_03_55_li_dg_sst_01-ccd_01_RAW.png
Entry   Entered by SC/VC from 134.158.195.141 on Tue May 10 13:26:30 2022; Démarrage faisceau 
Entry   Entered by SC/HG from 134.158.195.141 on Tue May 10 10:48:45 2022; Démarrage linac 
Entry   Entered by Viktor Soskov from 134.158.195.153 on Tue May 10 10:11:18 2022; Laser status 
Entry   Entered by SC from 134.158.195.141 on Tue May 10 09:28:22 2022; Démarrage 
Entry   JNC/CB/HG; redémarrage 