Draft
|
Thu Feb 23 10:08:35 2023 |
ND, VK, VM | Under Process | Shift summary | Ring Commissioning |
|
Shift 23/2 | | 9h22 mise en chauffe
Pb site elog; autres sites web |
9x |
|
696
|
Fri Feb 24 16:24:15 2023 |
Entered by Nicolas Delerue from 134.158.195.142 on Fri Feb 24 16:24:00 2023 | Fixed | Shift summary | Diag |
|
Shift 24/2 | | 13:30 Mise en chauffe
14:30 Demarrage faisecau
Test de modifications de diverses |
|
|
697
|
Mon Feb 27 19:51:39 2023 |
CB/JNC | | Shift summary | Linac Commissionning |
|
run du 27 février 2023 | | Problème démarrage de caméra
LI/SST1 (forcage plosieurs fois), les autres
ont redémarrée au deuxième |
|
|
699
|
Wed Mar 1 10:18:28 2023 |
CB/JNC/MJ/ VK/VM | | Shift summary | Linac Commissionning |
|
run du 1er mars 2023 | | 9h30 mise en chauffage
Température canon 31.75,
section 29.2 degrés |
 |
|
Draft
|
Fri Mar 3 11:49:50 2023 |
VK VM | Not Fixed | Shift summary | LI | Ring | Linac Commissionning | Ring Commissioning |
|
Shift 03 | | Start modulator; alims;
We cannot start machine. No e-beam.
Timing laser RF? Need help of linac team. |
|
|
701
|
Fri Mar 3 12:08:59 2023 |
VK VM | Not Fixed | Shift summary | LI | Ring | Linac Commissionning | Ring Commissioning |
|
RE: Shift 03 | | evreything is ok
The laser shutter was closed !
Becareful the shutter state is inverted. |
|
|
702
|
Fri Mar 3 12:29:49 2023 |
VK VM | Not Fixed | Shift summary | LI | Ring | Linac Commissionning | Ring Commissioning |
|
RE: RE: Shift 03 | | Il se passe des choses pendant la nuit
qui mette les diags de la machine en radent
: |
|
|
704
|
Mon Mar 6 09:09:52 2023 |
VC | Under Process | Problem | Linac Commissionning |
|
pB synchro suite | | Test des signaux de "Timing"
en calle de controle
1- la communication avec l'IHM |
|
|
705
|
Mon Mar 6 11:09:50 2023 |
MO VC | Under Process | Linac | Linac Commissionning | Ring Commissioning |
|
Commitionning | | 10 H demarrage chauffage modulateur et
chillers (le pc modulateur était
planté => Maher l'a redémarré) |
|
|
706
|
Mon Mar 6 12:16:31 2023 |
MJ HG KD VC | Not Fixed | Urgent | Linac Commissionning |
|
URGENT SST off | | Camera SST inutilisable en debut de shift.
IL FAUT ABSOLUMENT ARRETER de faire
des trucs sur les cameras entre 2 shifts |
  |
|
Draft
|
Wed Mar 8 11:45:46 2023 |
Entered by Marie Jacquet from 134.158.205.47 on Wed Mar 8 11:45:31 2023 | | | |
|
I-dipole vs X_TLBPM02 - Mesures/Simul (suite elog 28 fev) | | Tue Feb 28 08:48:29
2023
8H50-demarrage chiller et chauffage |
|
|
708
|
Wed Mar 8 11:47:20 2023 |
Entered by Marie Jacquet from 134.158.205.47 on Wed Mar 8 11:45:31 2023 | | Shift summary | Linac Commissionning |
|
(suite elog 28 fev) data X_TLBPM02 vs I_Dipole - Plot Mesures/Simul | | Tue Feb 28 08:48:29
2023
8H50-demarrage chiller et chauffage |
|
|
709
|
Thu Mar 9 00:55:10 2023 |
ND, Sandry Wallon | Under Process | Shift summary | Diag |
|
Programme prise de donnée 9/03/2023 | | 9h15 Les stations etaient laissees ouvertes
9h15 Mise en chauffe modulateur
9h30 PSS gele => Appel MO |
  |
|
710
|
Fri Mar 10 09:34:09 2023 |
IC, VM, ND, VK | New Solution | Shift summary | Ring |
|
Prise de donnee 10/3/2023 | | 9h20 Start modulator, cycle magnets
10h20 Intevention Vincent sur PA
10h40 Scan charge phase |
7x |
|
711
|
Mon Mar 13 12:18:02 2023 |
MJ | Not Fixed | Urgent | Linac Commissionning |
|
IHM SST HS - URGENT | | IHM sst HS en debut de shift cf image :
toutes les cases show camera sont blanches
yag 2 3 4 !! RIEN ne marche |
 |
|
712
|
Mon Mar 13 12:33:40 2023 |
Entered by Viktor Soskov from 134.158.195.153 on Mon Mar 13 12:33:23 2023 | Fixed | Info | Linac Commissionning |
|
Laser status | | Bonjour, lundi matin (le 13/03) j'ai
trouvé le laser allumé, donc
il fonctionne pendant le week-end !!! |
|
|
713
|
Mon Mar 13 13:54:31 2023 |
MJ | Not Fixed | Urgent | Linac Commissionning |
|
Le bouton PHASE CANON sur le panneau IHM NE FONCTIONNE PLUS !!!!!!!!!!! | | Le bouton PHASE CANON sur le panneau
IHM NE FONCTIONNE PLUS !
plus d'acces a la phase canon. |
|
|
714
|
Tue Mar 14 09:14:05 2023 |
Entered by Viktor Soskov from 134.158.195.153 on Mon Mar 13 12:33:23 2023 | Fixed | Info | Linac Commissionning |
|
RE: Laser status | | Bonjour Viktor,
c'est moi (KD) qui ai allumé
le laser lundi matin. Le laser était |
|
|
715
|
Tue Mar 14 12:10:25 2023 |
KD, SC | Under Process | Shift summary | LI | Laser | Linac Commissionning |
|
shift du 14 mars 2023 | | 12h10 : mise en chauffe modulateur + frigo/chillers
La cavité est intervenu
le matin sur le laser CFP. |
|
|
716
|
Thu Mar 16 10:15:13 2023 |
ND, Enzo Crou, Noé Idesheim, Jean-Nicolas Quenot | New Solution | Shift summary | Ring Commissioning |
|
Prise de donnee 16/3/2023 | | 9:15 Mise en chauffe
10:30 Ronde casemate
10:40 Start beam |
17x |