  Toutes les notes concernant les Commissionning de ThomX, Page 33 of 62  Not logged in ThomX    logo
ID Date Authordown Status Type Category Important Subject Icon Text Attachments
  912   Fri Sep 13 15:02:04 2024 Entered by Viktor Soskov from 134.158.195.153 on Fri Sep 13 11:22:05 2024FixedInfoLinac Commissionning Faisceau laser UV  Bonjour, voici l'images du faisceau
laser UV actuel sur la cathode (Iris : D=2mm,
D=6mm)
 IrisD2mm_Image2024-09-13_10-15-56.pngIrisD6mm_Image2024-09-13_11-13-57.png 
  406   Fri Mar 18 10:34:19 2022 Entered by Viktor Soskov from 134.158.195.153 on Fri Mar 18 10:34:03 2022FixedInfoLinac Commissionning Laser status L'energie UV sur la cathode = 30µJ   
  397   Fri Mar 11 14:10:11 2022 Entered by Viktor Soskov from 134.158.195.153 on Fri Mar 11 14:09:56 2022FixedInfoLaser Laser status Actuellement on a 50 µJ  sur
la cathode  après une rotation
du hublot.
  
  276   Fri Jan 21 10:36:55 2022 Entered by Viktor Soskov from 134.158.195.153 on Fri Jan 21 10:36:38 2022FixedProblemLinac Commissionning Camera Laser Pas possible de demarrer  le logiciel
pour le camera laser.
  
  348   Fri Feb 18 09:02:51 2022 Entered by Viktor Soskov from 134.158.195.153 on Fri Feb 18 09:02:37 2022FixedInfoLinac Commissionning faisceau Y a t'il un fasceau aujourd'hui?   
  326   Fri Feb 11 15:07:56 2022 Entered by Viktor Soskov from 134.158.195.153 on Fri Feb 11 15:07:41 2022FixedProblemLinac Commissionning Positions moteurs M4-1(2) Positions moteurs

LI/OP/OPT.01-Mir.04-MOP.01  
-> =190mm  ???
  
  299   Fri Feb 4 10:39:26 2022 Entered by Viktor Soskov from 134.158.195.153 on Fri Feb 4 10:39:11 2022FixedInfoLinac Commissionning Laser status L'énergie IR du laser a chuté
de 1.9 à 1.4mJ. Des taches d'aeu
ont été aperçues sur
  
  463   Thu May 19 13:13:17 2022 Entered by VC/SC from 134.158.195.142 on Thu May 19 13:13:02 2022Under ProcessLinacLinac Commissionning Démarrage faisceau Reprise après la pause repas, mise
en route faisceau/data/shared/Commissioning_tools/Mesure/20220519/Laser_M4

Fin de la mise en place du capot
 2022-05-19_14_44_35_li_dg_sst_01-ccd_01_RAW.pngScreenshot_from_2022-05-19_19-00-29.png 
  446   Mon May 2 14:02:58 2022 Entered by VC/SC from 134.158.195.141 on Mon May 2 14:02:42 2022Not FixedLinacLinac Commissionning Redpitaya et modulateur icon8.gif Remise en chauffe du modulateur

Reboot des redpitayas pour avoir
le signal HF sur l'IHM
  
  441   Thu Apr 14 09:56:11 2022 Entered by VC/ND/SC from 134.158.195.141 on Thu Apr 14 09:55:56 2022FixedInfoLinac Commissionning Faisceau pour les diagnostics Le programme de la journée
:

- Morning: Iryna, Slava + Viktor
  
  443   Thu Apr 14 16:08:22 2022 Entered by VC/ND from 134.158.195.141 on Thu Apr 14 16:08:07 2022Under ProcessLinacDiag | Linac Commissionning Test mesure de charge HV modulateur 1000V

Li/ps/COL2 180A

Li/ps/str.01/H -1A
  
  461   Thu May 19 08:55:55 2022 Entered by VC, JNC, SC, HG from 134.158.195.141 on Thu May 19 08:55:39 2022Under ProcessLinacLinac Commissionning Mesure courant obscurité But : mesure du courant d'obscurité

Démarrage chauffage modulateur
et refroidissement à 8h45
  
  64   Mon Sep 13 14:20:56 2021 Entered by Super Team on Mon Sep 13 14:18:35 2021Under ProcessLinacLinac Commissionning démarrage RF canon Checks avants conditionnement du canon

1)
Mise en route des chillers

Température
de consigne : 32°C
 vide13092021.pdfvide13092021.dat 
  288   Tue Feb 1 09:15:55 2022 Entered by Super Team from 83.202.31.199 on Tue Feb 1 09:15:40 2022FixedInfoLinac Commissionning Modification planning aujourd'hui Planning de la semaine modifié
:

Mardi : Ouverture de l'igloo,
  
  286   Mon Jan 31 10:03:50 2022 Entered by Super Team from 83.202.31.199 on Mon Jan 31 10:03:38 2022FixedLinacLinac Commissionning Planning cette semaine -----------------------------------------------------------------------------------

Planning de la semaine

Lundi
  
  424   Mon Apr 4 10:50:19 2022 Entered by Super Team from 83.202.31.199 on Mon Apr 4 10:50:04 2022FixedInfoLinac Commissionning Planning cette semaine    Planning_linac_semaine_du_4_avril.pptxsemaine_4_avril.PNG 
  40   Fri Jun 25 11:56:23 2021 Entered by Super Team from 82.64.20.144 on Fri Jun 25 11:55:56 2021Under ProcessLinacRF D1 bilan du 25 juin 2021 Bilan du 25 juin 2021

-Le canon a été mesuré 
à bas niveau sur place et en salle
  
  537   Mon Sep 5 10:53:12 2022 Entered by Super Team from 134.158.89.135 on Mon Sep 5 10:52:53 2022Under ProcessLinacLinac Commissionning Démarrage linac Matinée : Intervention frigoriste

Démarrage technique linac
prévu à 13h30
  
  1149   Wed Nov 12 10:29:49 2025 Entered by Super Team from 134.158.76.9 on Wed Nov 12 10:29:34 2025Under ProcessShift summaryLI | TL | Ring   15h09 Cycling all magnets

15h12 HV is ON

15h15 The modulator was set to
  
  1147   Fri Nov 7 18:45:54 2025 Entered by Super Team from 134.158.205.4 on Fri Nov 7 18:45:38 2025Under ProcessShift summaryLinac Commissionning   08h34  Warm-up ThomX: Modulator, Laser,
Fridge

08h40 Chillers were started,
 Screenshot_from_2025-11-07_16-24-10.pngScreenshot_from_2025-11-07_16-24-35.pngScreenshot_from_2025-11-07_16-23-58.png 