HOME Prise de donnees MML Controle commande Simulations Notes Hardware Ligne X Laser Interaction Diagnostiques Synchronisation
Commissionning Commissionning Preparation Pannes ShiftCheck
  Toutes les notes concernant les Commissionning de ThomX, Page 32 of 58  Not logged in ThomX    logo
Entry   Entered by Viktor Soskov from 134.158.195.153 on Mon Oct 10 15:10:21 2022; Laser status 
Entry   KD, VS, SC; shift du 10 octobre 2022 
Entry   IC, VM, VK, AL, JH; Optimization of the ring 6x
Entry   Entered by Marie Jacquet from 88.165.97.136 on Fri Oct 7 00:30:03 2022; shifts LINAC 4/10 et 6/10 
Entry   VK/ND/SC; Faisceau Anneau 10x
Entry   VK, VM, HG,IC, AL;  
Entry   Entered by Nicolas Delerue from 134.158.88.175 on Tue Oct 4 17:33:52 2022; Planning shift Thursday 6th October 
Entry   MJ/HG/SC; Alignement linac 
Entry   VK, AL, IC; Beam is stored 6x
Entry   VC/KD/SC; Faisceau linac 
Entry   Slava, Viktor M, Iryna; Check the QUADs in the ring 
Entry   AM, VI, VK, IC, VC, ND; Shift du 30/09/2022 16x
Entry   AM, IC, VK, VI, SC, ND; Shift du 29/09/2022 9x
Entry   Entered by Marie Jacquet from 134.158.89.45 on Wed Sep 28 19:13:52 2022; Shift du 12-13/09 en image  2022-09-28-elog.pdf
icon14.gif   VC VK AM IC & all; Shift du 28/09/2022 Screenshot_from_2022-09-28_19-05-00.pngScreenshot_from_2022-09-28_19-08-26.pngfirst_turn28092022.png
Entry   VC SC CB; Shift du jour 
Entry   Vincent Chaumat; Mesure puissance Canon et section pBoucle.pngPisection.png
Entry   Entered by Viktor Soskov from 134.158.195.153 on Mon Sep 26 09:57:59 2022; Laser status 
Entry   Entered by Super Team from 134.158.195.141 on Fri Sep 23 08:39:36 2022; Shift du 23/09/2022 6x
Entry   Entered by Hayg Guler from 134.158.91.29 on Thu Sep 22 10:08:17 2022; , entered from 134.158.91.29 
ELOG V3.1.4-395e101