Fri Mar 6 10:44:11 2026 |
VM, HG, JN | Under Process | Shift summary | RF D1 |
|
| | 09h00 Warm-up ThomX: Modulator, Laser,
Fridge
09h05 Chillers were started, cycling |
| |
Draft
|
Fri Mar 6 09:00:45 2026 |
VM | Under Process | Shift summary | |
|
| | 09h00 Warm-up ThomX: Modulator, Laser,
Fridge
09h05 Chillers were started, cycling |
| |
1203
|
Thu Mar 5 13:19:22 2026 |
MJ VM DN RC HG | | Shift summary | LI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning |
|
Etudes matching |
| Mesures : Spectres et taille source
X + Quads scans associées, @
|
| |
1202
|
Wed Mar 4 08:35:23 2026 |
VM, MJ, DN, RC | Fixed | Shift summary | Linac Commissionning | Ring Commissioning |
|
Check point du fonctionnement anneau du 24/02 suite a l'ajout de resistances dipole le 24/02 au soir | | 08h35 Warm-up ThomX: Modulator, Laser,
Fridge
Programme |
7x | |
Draft
|
Fri Feb 27 08:00:46 2026 |
IC, VM | Under Process | Urgent | Laser |
|
, entered from 127.0.0.1 | | 07h55: mise en chauffe en remote (frigo/chillers,
laser, modulateur, cyclage)
09h00 HV is on |
| |
Draft
|
Thu Feb 26 08:18:00 2026 |
IC, VM | | | |
|
| | 08h15: mise en chauffe en remote (frigo/chillers,
laser, modulateur, cyclage)
08h15: mise en chauffe en remote |
| |
1199
|
Wed Feb 25 07:29:16 2026 |
KD MJ DN VK IC | Under Process | Shift summary | Opt | Linac Commissionning | Ring Commissioning |
|
25 fevrier 2026 - Alignement TRANSFO - Prise d'images PhotonicScience Rack transfo IN/OUT | | 7h30: mise en chauffe en remote (frigo/chillers,
laser, modulateur, cyclage)
*** |
| |
1198
|
Tue Feb 24 07:38:01 2026 |
KD, VM, RC, MJ, IC | Under Process | Shift summary | Laser | Opt | Linac Commissionning | Ring Commissioning |
|
shift du 24 fevrier 2026 | | 7h40: mise en chauffe en remote (frigo/chillers,
modulateur, laser, cyclage)
|
7x | |
Draft
|
Mon Feb 23 09:43:36 2026 |
IC | | | |
|
Ring studies | | 9h40: mise en chauffe (chillers/frigo,
modulateur, cyclage)
HV ON |
| |
1196
|
Fri Feb 20 07:54:25 2026 |
IC, VM | Under Process | Shift summary | Ring Commissioning |
|
| | 7h50: mise en chauffe en remote (chillers/frigo,
modulateur, cyclage)
08h57 HV is on |
  | |
Draft
|
Thu Feb 19 07:32:42 2026 |
KD, VM, RC, MJ, IC, DN | Under Process | Shift summary | Opt | Linac Commissionning | Ring Commissioning |
|
shift du 19 fevrier 2026 | | 7h30: mise en chauffe en remote (chillers/frigo,
modulateur, laser, cyclage)
08h55 HV is ON |
  | |
1194
|
Wed Feb 18 07:40:44 2026 |
KD | Under Process | Shift summary | Opt | Linac Commissionning | Ring Commissioning |
|
shift du 18 février 2026 | | 7h40: mise en chauffe en remote (frigo/chiller,
modulateur, laser, cyclage)
8h40 HV ON |
| |
1193
|
Tue Feb 17 07:48:24 2026 |
MJ, KD,VM,IC, RC, DN | Under Process | Shift summary | Opt | Linac Commissionning | Ring Commissioning |
|
shift du 17 fevrier 2026 | | 7h50 : mise en chauffe en remote (frigo/chillers,
modulateur, laser, cyclage)
Le cyclage de RI-C1/QP.08, RI-C1/QP.11 |
10x | |
1192
|
Fri Feb 13 17:38:15 2026 |
Entered by Super Team from 127.0.0.1 on Fri Feb 13 17:38:00 2026 | Under Process | Shift summary | LI |
|
SHift du jour | | The code for laser alignment does not work
properly --> done by hand
H 5.244 |
| |
1191
|
Wed Feb 11 09:12:35 2026 |
VM && HG | Under Process | Shift summary | LI |
|
Linac commissioning | | 09h12 Warm-up ThomX: Modulator, Laser,
Fridge
09h21 Chillers were started, cycling |
  | |
1190
|
Tue Feb 10 18:34:33 2026 |
Entered by Super Team from 127.0.0.1 on Tue Feb 10 18:34:13 2026 | Under Process | Shift summary | LI | RF D1 |
|
Demarrage Linac |
| Mesures après remontage de la cale
: 1215 V sur le modulateur.
ça tient mais |
| |
1189
|
Fri Feb 6 08:26:41 2026 |
Entered by Super Team from 127.0.0.1 on Fri Feb 6 08:26:22 2026 | Under Process | Shift summary | RF D1 |
|
| | 08h25 Warm-up ThomX: Modulator, Laser,
Fridge
08h33 Chillers were started, cycling |
| |
1188
|
Thu Feb 5 13:18:03 2026 |
KD, HG, VM | Fixed | Info | LI | TL | LE | Ring | CC | Laser | Opt | MECA | SY | Vide | Electronique |
|
Laser PC status | | ** l'iris a été changée
et est opérationnelle
/!\ |
| |
1187
|
Fri Jan 23 07:42:45 2026 |
IC, VM | Under Process | Shift summary | Laser |
|
Ring studies | | 7h45: mise en chauffe en remote (modulateur,
cyclage, laser, frigo/chillers)
08h43 HV is on |
| |
1186
|
Thu Jan 22 07:37:58 2026 |
IC, VM | Under Process | Shift summary | Linac Commissionning | Ring Commissioning |
|
Beam studies | | 7h45: mise en chauffe en remote (modulateur,
laser, frigo/chillers)
08h41 HV is on |
|
|