Entry   KD; shift du 13 janvier 2026 
Entry   VM, RC, MJ, IC; Test Soleno=245, optic issue de la simu Julien Matching 
Entry   IC; Ring studies Screenshot_from_2026-01-15_11-04-16.pngScreenshot_from_2026-01-15_11-33-33.pngRi_C1_Quads_is_off_Screenshot_from_2026-01-15_18-19-14.pngScreenshot_from_2026-01-15_16-42-27.pngScreenshot_from_2026-01-15_17-36-28after1LOCO.png
Entry   IC, VM, ND;  Screenshot_from_2026-01-16_18-28-24.pngScreenshot_from_2026-01-16_13-22-12.pngScreenshot_from_2026-01-16_13-23-01.pngScreenshot_from_2026-01-16_13-31-16MODEl.pngScreenshot_from_2026-01-16_16-02-15LOCO_1it.png
Entry   VM, ND, VC;  
Entry   KD MJ RC DN; Position Horiz FPC ("spectres dromadaires") 
Entry   IC, VM; Beam studies 
Entry   IC, VM; Ring studies 
Entry   Entered by Super Team from 127.0.0.1 on Fri Feb 6 08:26:22 2026;  Screenshot_from_2026-02-06_10-52-58.png
icon1.gif   Entered by Super Team from 127.0.0.1 on Tue Feb 10 18:34:13 2026; Demarrage Linac 
Entry   VM && HG; Linac commissioning  Vacc_2026-02-11_11-05-31.pngScreenshot_from_2026-02-11_15-57-35.pngCharge_trend_2026-02-11_17-12-31.png
Entry   Entered by Super Team from 127.0.0.1 on Fri Feb 13 17:38:00 2026; SHift du jour 
Entry   MJ, KD,VM,IC, RC, DN; shift du 17 fevrier 2026 10x
Entry   KD; shift du 18 février 2026 Quads_settings_after_match.md
Entry   KD, VM, RC, MJ, IC, DN; shift du 19 fevrier 2026 Screenshot_from_2026-02-19_16-50-44.pngScreenshot_from_2026-02-19_16-03-44.pngScreenshot_from_2026-02-19_16-03-32.png
Entry   IC, VM;  Screenshot_from_2026-02-20_16-34-18.pngScreenshot_from_2026-02-20_16-15-37.pngScreenshot_from_2026-02-20_12-00-27.png
Entry   KD, VM, RC, MJ, IC; shift du 24 fevrier 2026 7x
Entry   KD MJ DN VK IC; 25 fevrier 2026 - Alignement TRANSFO - Prise d'images PhotonicScience Rack transfo IN/OUT 
Entry   IC, VM; , entered from 127.0.0.1 Screenshot_from_2026-02-27_10-25-37.png
Entry   VM;  