  433   Thu Apr 7 11:31:31 2022 Entered by Viktor Soskov from 134.158.195.153 on Thu Apr 7 11:31:17 2022FixedInfoLinac Commissionning Laser status Hublot_1 (dans la salle laser) a été
enlevé, hublot_2 (casemate) - changé
pour CaF2.
  
  434   Thu Apr 7 12:51:41 2022 Entered by Viktor Soskov from 134.158.195.153 on Thu Apr 7 11:31:17 2022FixedInfoLinac Commissionning RE: Laser status  




 2022-04-07_12_27_54_li_op_las_02_Laser_log_scale_False_despeckle_False_min_scale_0_max_scale_30_8.png2022-04-07_12_50_39_li_op_las_02_Laser_log_scale_False_despeckle_False_min_scale_0_max_scale_30_8.png 
  435   Mon Apr 11 12:09:18 2022 Mo/JNC/CB Shift summaryLinac Commissionning Demarrage 12h00 démarrage modulateur et chillers,
fermeture casemate

15h : démarrage laser
  
  436   Mon Apr 11 16:55:20 2022 JNC/CBUnder ProcessShift summaryLinac Commissionning shift du 11 avril 2022 + analyse Visualisation à la phase de charge
max du faisceau sur l'écran LI
SST1
 16x 
  437   Mon Apr 11 16:57:32 2022 Mo/JNC/CB Shift summaryLinac Commissionning RE: Demarrage Pour ce qui est de la caméra laser,
l'interface image_laser ne gère
que l'affichage, donc si le server est
  
  438   Tue Apr 12 09:08:20 2022 Entered by Viktor Soskov from 134.158.195.153 on Tue Apr 12 09:08:05 2022FixedInfoLinac Commissionning Laser status Laser est allumé. Gate - False.   
  439   Tue Apr 12 12:52:48 2022 JNC/CB Shift summaryLinac Commissionning shift du 12 avril + analyse Mise en chauffe modulateur

A faire scan dimension sortie canon
en fonction de coil2 et scan QP à
 13x 
  440   Thu Apr 14 08:04:58 2022 Entered by Super Team from 134.158.195.141 on Thu Apr 14 08:04:41 2022Under ProcessOtherDiag | Electronique | Linac Commissionning ThomX -commitionning diag Demarrage modulateur et chiller 8h06   
  441   Thu Apr 14 09:56:11 2022 Entered by VC/ND/SC from 134.158.195.141 on Thu Apr 14 09:55:56 2022FixedInfoLinac Commissionning Faisceau pour les diagnostics Le programme de la journée
:

- Morning: Iryna, Slava + Viktor
  
  442   Thu Apr 14 11:05:07 2022 Entered by IC/V/SC from 134.158.195.141 on Thu Apr 14 11:04:51 2022Under ProcessLinacLinac Commissionning Polarités des quadrupoles Faisceau en route, visualisation sur TL/DG/SST.01

Bobine focalisation : 190 A, LI/PS/STR.01-H01
= -1A, LI/PS/STR01-V01 = 1A, Faisceau quasi
 Screenshot_2022-04-14_11-10-59.png 
  443   Thu Apr 14 16:08:22 2022 Entered by VC/ND from 134.158.195.141 on Thu Apr 14 16:08:07 2022Under ProcessLinacDiag | Linac Commissionning Test mesure de charge HV modulateur 1000V

Li/ps/COL2 180A

Li/ps/str.01/H -1A
  
  444   Thu Apr 14 16:31:58 2022 Entered by SC/ND from 134.158.195.141 on Thu Apr 14 16:31:44 2022Under ProcessLinacLinac Commissionning Faisceau Phase 145 degres charge max Q = 77 pC

HT = 1090 V

Energie max (-40 degres) Q = 69
  
  445   Mon May 2 10:30:35 2022 Entered by JNC/VC from 134.158.195.141 on Mon May 2 10:30:21 2022FixedLinacLinac Commissionning Fermeture machine Jean Noel a fermé la fosse nord,
Elle est INONDEE, on va faire un ticket aux
infras.
  
  446   Mon May 2 14:02:58 2022 Entered by VC/SC from 134.158.195.141 on Mon May 2 14:02:42 2022Not FixedLinacLinac Commissionning Redpitaya et modulateur icon8.gif Remise en chauffe du modulateur

Reboot des redpitayas pour avoir
le signal HF sur l'IHM
  
  447   Mon May 2 18:26:12 2022 JNC/CB FixLinac Commissionning suite et fin debug Redpitaya redémarrer

Seuil de la pompe au niveau du
canon modifiée en local (CH1)
 2022-05-02_19_29_11_li_dg_sst_01-ccd_01_RAW_1.png 
  448   Mon May 9 10:49:47 2022 MaherEntered by Super Team from 134.158.195.141 on Mon May 9 10:49:29 2022 Shift summaryLinac Commissionning   10h50 Modulateur en chauffe, chillers en
fonctionnement
  
  449   Mon May 9 11:06:48 2022 maher Shift summaryLinac Commissionning   Après discusion avec Victor, j'arrete
le modulateur et chillers, peut-etre re-démarrage
en milieu de l'aprem!
  
  450   Mon May 9 17:52:34 2022 JNC/CB/HG Shift summaryLinac Commissionning redémarrage laser aligné sur la cathode

la camera laser ne marche pas malgré
un redémarrage via le healthcheck
  
  451   Tue May 10 09:28:35 2022 Entered by SC from 134.158.195.141 on Tue May 10 09:28:22 2022Under ProcessLinacLinac Commissionning Démarrage Mise en route modulateur et schillers   
  452   Tue May 10 10:11:37 2022 Entered by Viktor Soskov from 134.158.195.153 on Tue May 10 10:11:18 2022FixedInfoLinac Commissionning Laser status Devices:

....DIA.01-CTL.01 et LAS.01-ASP.01
fonctionnet.
  