1158
|
Wed Nov 26 07:47:52 2025 |
KD MJ VM DN RC | Under Process | Shift summary | Linac Commissionning | Ring Commissioning |
|
shift du 26 novembre 2025 | | 7h50: mise en chauffe à distance
(frigo/chiller, laser, modulateur, cyclage)
11h13 Beam is in the ring, 50 MeV, |
8x |
|
903
|
Wed Aug 21 09:21:45 2024 |
KD MJ VK | Under Process | Shift summary | LI | Linac Commissionning |
|
shift du 21 aout 2024 | | 9h20 : mise en chauffe de la machine (modulateur,
laser, frigo)
9h25 : pression SF6 remise 2.2 |
   |
|
994
|
Tue Jan 14 07:53:17 2025 |
KD MJ VC HG | Under Process | Shift summary | MECA | Linac Commissionning | Ring Commissioning |
|
shift du 14 janvier 2025 | | 7h50 : mise en chauffe machine à
distance (chiller, frigo, modulateur, laser)
9h15 re demarrage du serveur LI/OP/LAS.02 |
|
|
1096
|
Tue Jul 1 08:15:08 2025 |
KD MJ VC DN RC | Under Process | Shift summary | Opt | Linac Commissionning | Ring Commissioning |
|
shift du 01 juillet 2025 | | 8h15: mise en chauffe distance (chiller/frigo,
modulateur, laser, cyclage)
9h45: modulateur ok |
|
|
1213
|
Tue Mar 17 08:07:49 2026 |
KD MJ RC DN VK | Under Process | Shift summary | Opt | Linac Commissionning | Ring Commissioning |
|
ENERGY-ANGLE reconstruction : prise de donnees - 17 mars 2026 | | 8h05 : mise en chauffe en remote (frigo/chillers,
modulateur, laser, cyclage)
*** programme : Mesures |
|
|
1223
|
Wed Apr 1 07:45:03 2026 |
KD MJ RC DN VK | Under Process | Shift summary | Opt | Linac Commissionning | Ring Commissioning |
|
1e avril 2026 - Scan Energy-Angle 61.5 MeV | | 7h40 : mise en chauffe en remote (frigo/chillers,
modulateur, laser, cyclage)
==> SF6 à remplir avant |
|
|
1231
|
Wed Apr 15 08:04:29 2026 |
KD MJ RC DN VK | Under Process | Shift summary | Linac Commissionning | Ring Commissioning |
|
ENERGY/ANGLE 40 MeV - 15 avril 2026 | | 8h05: mise en chauffe à distance
(frigo/chillers, modulateur, laser, cyclage)
*** |
|
|
1165
|
Tue Dec 9 08:00:00 2025 |
KD MJ RC DN | Under Process | Shift summary | Linac Commissionning | Ring Commissioning |
|
shift du 09 décembre 2025 - 70 MeV et 40 MeV | | 8h : mise en chauffe en remote (modulateur,
cyclage, frigo/chillers, laser)
Stockage 70MeV ok, le faisceau |
6x |
|
1185
|
Wed Jan 21 07:56:59 2026 |
KD MJ RC DN | Under Process | Shift summary | LI | TL | LE | Ring | Linac Commissionning | Ring Commissioning |
|
Position Horiz FPC ("spectres dromadaires") | | 7h55: mise en chauffe en remote (modulateur,
cyclage, laser, frigo/chillers)
==> plus de trig sur la machine |
|
|
916
|
Tue Sep 17 09:08:45 2024 |
KD MJ HG | Under Process | Shift summary | LI | Linac Commissionning |
|
Shift du 17 septembre 2024 | | 9h: mise en chauffe (sauf cyclage)
remise de SF6: 2.4bars --> 2.6bars
programme : |
9x |
|
1199
|
Wed Feb 25 07:29:16 2026 |
KD MJ DN VK IC | Under Process | Shift summary | Opt | Linac Commissionning | Ring Commissioning |
|
25 fevrier 2026 - Alignement TRANSFO - Prise d'images PhotonicScience Rack transfo IN/OUT | | 7h30: mise en chauffe en remote (frigo/chillers,
laser, modulateur, cyclage)
*** |
|
|
1155
|
Fri Nov 21 08:02:04 2025 |
KD MJ DN Students | Under Process | Shift summary | Linac Commissionning | Ring Commissioning |
|
shift du 21 novembre 2025 | | 8h: mise en chauffe en remote (modulateur,
frigo/chillers, laser, cyclage)
9h: start |
  |
|
Draft
|
Tue Oct 10 13:46:06 2023 |
KD MJ | | Shift summary | |
|
| | |
|
|
917
|
Thu Sep 19 08:36:25 2024 |
KD MJ | Reference Solution | Shift summary | Linac Commissionning |
|
shift du 19 septembre 2024 | | 8h30: mise en chauffe de la machine
Programme de la journée
: |
|
|
1009
|
Wed Feb 12 08:00:31 2025 |
KD MJ | Under Process | Shift summary | LI | TL | Linac Commissionning |
|
shift du 12 février 2025 - Alignements | | 8h: mise en chauffe à distance (modulateur,
frigo, chiller, laser)
9h30: laser semble pas aligné |
  |
|
1169
|
Mon Dec 15 08:06:26 2025 |
KD MJ | Under Process | Shift summary | Linac Commissionning | Ring Commissioning |
|
shift du 15 décembre 2025 | | 8h: mise en chauffe en remote (chiller/frigo,
laser, modulateur, cyclage)
* cannot enter to the ring with |
|
|
1222
|
Tue Mar 31 15:42:33 2026 |
KD MJ | Fixed | Shift summary | Laser | Linac Commissionning | Ring Commissioning |
|
shift du 31 mars 2026 : MONO 70 MeV + spectres 61.5 MeV | | /!\ fort impact du moteur Rsample de la
ligne X sur la cavité CFP (obligé
de le mettre off) |
 |
|
534
|
Tue Aug 30 08:56:43 2022 |
KD | Under Process | Shift summary | Diag | Aimants | Laser | RF D1 | SY | Linac Commissionning |
|
Shift Linac + TL + Injection 30/08/2022 | | 8h57 : Démarrage modulateur, laser
(Gate False), chillers
Programme de la journée |
|
|
536
|
Wed Aug 31 09:32:13 2022 |
KD | Under Process | Shift summary | Diag | Aimants | CC | Laser | RF D1 | SY | Electronique | Linac Commissionning |
|
Shift du 31/08/2022 (injection anneau) | | 9h30 : Démarrage du chauffage Modulateur,
laser et Chillers
Programme du jour : |
    |
|
597
|
Wed Oct 19 17:00:28 2022 |
KD | New Solution | Shift summary | LI | TL | LE | Diag | Linac Commissionning |
|
shift du 19 octobre 2022 | | démarrage faisceau 15h45
Programme : essaye recette
de la veille |
 |