833
|
Wed Jan 24 08:57:25 2024 |
VC, IC, VK, VM | Under Process | Shift summary | Linac Commissionning | Ring Commissioning |
|
Commissioning | | Demmarrage machine à 8h45
IHM ThomX warm-up
8H55 Chauffage klystron, Frigo |
10x |
|
834
|
Thu Jan 25 08:49:29 2024 |
VC DN ND, IC, VM, KD, AS RC , VK... | Under Process | Shift summary | Linac Commissionning | Ring Commissioning |
|
commitionning | | 8h45 demarrage chauffage Modulateur et
frigo
Pb sur le serveur li/opt.02-las.01-asp.01 |
27x |
|
836
|
Wed Jan 31 14:12:25 2024 |
RC VC MJ | Under Process | Other | Ring Commissioning |
|
commitionning | | Chauffage mod 11h
demarrage machine 14H
on suit le star faisceau step par |
 |
|
837
|
Thu Feb 1 08:10:14 2024 |
VK VC HG SC ME | Under Process | Shift summary | LI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning |
|
commitionning | | 8h10 rémarrage machine chauffage
klystron frigo et chiller
pB DS calc/er_sy/rac.17-elr.01-rdp.0X.Y |
|
|
839
|
Thu Feb 1 16:30:20 2024 |
Entered by Marie Jacquet from 134.158.89.45 on Thu Feb 1 16:30:01 2024 | Under Process | Shift summary | LI | TL | LE | Ring |
|
Complement de la fin du elog 837 | | En complement de la fin de l'entree
elog 837 ou il est ecrit a la fin :
on |
|
|
840
|
Fri Feb 2 08:16:50 2024 |
Entered by Super Team from 134.158.195.141 on Fri Feb 2 08:16:31 2024 | Under Process | Shift summary | LI | TL | LE | Ring | Linac Commissionning | Ring Commissioning |
|
Shift du 2 février 2024 | | La clé PA est resté enclenchée
hier. Il faut penser à la tourner
avant de partir (demande de Maher) |
|
|
842
|
Tue Feb 6 08:52:28 2024 |
VC MJ KD | Under Process | Shift summary | LI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning |
|
commissionning | | 8h45 demarrage machine
modulateur frigo ampli laser chiller
et cyclage des aimants |
7x |
|
844
|
Thu Feb 8 08:31:19 2024 |
KD, HG, VC, RC | Under Process | Shift summary | Linac Commissionning | Ring Commissioning |
|
shift du 8 février 2024 | | 8h20 : Mise en chauffe de la machine pour
shift de la journée
Charge Phase :
Remarque |
 |
|
846
|
Mon Feb 26 09:07:06 2024 |
VC, VK, VM, IC, ND | Under Process | Shift summary | LI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning |
|
redemarage machine après élongation anneau | | 9H démarrage machine en mode linac
chauffage klystron ok
chiller ok |
 |
|
847
|
Tue Feb 27 09:10:47 2024 |
KD, VK, VM | Under Process | Shift summary | Ring Commissioning |
|
run du 27 février 2024 | | 9h: mise en chauffe de la machine (chillers,
laser, aimants, modulateur)
Mohamed regle la cavité |
|
|
848
|
Wed Feb 28 08:49:30 2024 |
VC, VM, VK | Under Process | Shift summary | LI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning |
|
Commintionning RING | | demarrage machine 8H50
Alim
EL/PS/DPI.01 demarrage à |
   |
|
850
|
Fri Mar 1 10:30:38 2024 |
VK, VM, IC | Under Process | Shift summary | Ring | Ring Commissioning |
|
Recomissioning of the SR, search for the revolution frequency | | 8h50 Start of the machine
Laser amplifier was somehow OFF.
Very strange situation and not clear why |
13x |
|
851
|
Fri Mar 1 10:39:04 2024 |
VK, VM, IC on Thu Feb 29 | Under Process | Shift summary | Ring | Ring Commissioning |
|
Recomissioning of the SR, search for the revolution frequency | | Start of the machine 9h
Optimization of the beam transport
to the Ring. |
  |
|
853
|
Mon Mar 4 08:58:01 2024 |
Entered by Super Team from 134.158.195.141 on Mon Mar 4 08:57:45 2024 | Under Process | Shift summary | Ring | Ring Commissioning |
|
Recomissioning of the SR, search for the revolution frequency | | 08h50 Start up of the machine
- Problem with the vaccum,
the valves around the RF cavity are down. |
|
|
854
|
Tue Mar 5 15:10:32 2024 |
IC, VM, VK | Under Process | Shift summary | Ring Commissioning |
|
Restart and tuning of the injector | | 10h Intervention to repair the water leakage.
It was repaired.
New problem with vacuum |
|
|
855
|
Wed Mar 6 08:49:56 2024 |
IC, VM, VK | Under Process | Shift summary | Ring Commissioning |
|
X-ray generation | | 8h50 Warming up the machine
10h start the beam
Tuning the injector |
  |
|
Draft
|
Thu Mar 7 08:58:28 2024 |
VK, VM, IC | Under Process | Shift summary | Ring Commissioning |
|
Recomissioning of the SR, search for the X-rays | | 8h50 Warming up the machine
Problem with the vaccum around
the RF cavity (see screenshot attached). |
|
|
857
|
Tue May 14 11:12:18 2024 |
ND, MEK | Under Process | Shift summary | RF D1 |
|
Conditionnement section | | 8:45 Impossible de passer le modulateur
en standby.
Probleme d'eau. |
|
|
861
|
Thu May 16 07:59:36 2024 |
KD | Under Process | Shift summary | Linac Commissionning |
|
Conditionnement section 16/05 | | 8h: démarrage Klystron, frigo et
chiller |
|
|
862
|
Thu May 16 08:38:19 2024 |
MEK, RC,VC, VK | Under Process | Linac | LI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning |
|
Conditionnement section 16/05 | | conditionnement démmare à
7.4 dB atténuation section ( ) pour
une largeur impulsion RF 1µs et fréquence |
|