1189
|
Fri Feb 6 08:26:41 2026 |
Entered by Super Team from 127.0.0.1 on Fri Feb 6 08:26:22 2026 | Under Process | Shift summary | RF D1 |
|
| | 08h25 Warm-up ThomX: Modulator, Laser,
Fridge
08h33 Chillers were started, cycling |
|
|
Draft
|
Fri Mar 6 10:44:11 2026 |
VM, HG, JN | Under Process | Shift summary | RF D1 |
|
| | 09h00 Warm-up ThomX: Modulator, Laser,
Fridge
09h05 Chillers were started, cycling |
|
|
755
|
Fri May 19 20:22:42 2023 |
MJ, KD | Under Process | Shift summary | RF Anneau | Ring Commissioning |
|
RF et anneau | | Apres 18h30 : prise ne main de la machine
pour aller dans la LE ==> le kicker d'extraction
est interlocké (abdandon) |
 |
|
759
|
Tue May 30 09:44:07 2023 |
MJ, KD | Under Process | Shift summary | RF Anneau | Ring Commissioning |
|
RE: RF et anneau | |
Mercredi 24 j'ai fait un test
sur la cavité RF : |
|
|
1161
|
Wed Dec 3 11:09:12 2025 |
Entered by Super Team from 134.158.195.141 on Wed Dec 3 11:08:54 2025 | Not Fixed | Info | RF Anneau | Linac Commissionning | Ring Commissioning |
|
Demarrage ThomX |
| Soucis Septum : Maher
help |
|
|
504
|
Mon Jul 11 14:56:39 2022 |
Entered by Super Team from 134.158.195.141 on Mon Jul 11 14:56:17 2022 | | Shift summary | RF Anneau |
|
| | Arret à 15h00 |
|
|
505
|
Tue Jul 12 12:27:38 2022 |
Entered by Super Team from 134.158.195.141 on Tue Jul 12 12:27:24 2022 | | Shift summary | RF Anneau |
|
| | 12h00 Remplacement du PS par Scandinova
et mise en route modulateur pour test mise
en route frigo et chillers |
|
|
508
|
Wed Jul 13 12:00:19 2022 |
Mo | | Shift summary | RF Anneau |
|
| | 12h00 Arret test modulateur et départ
de l'Ingé. de Scandinova
Ouverture de la casemate |
|
|
2
|
Tue Oct 18 14:25:34 2016 |
Entered by Hugues Monard from 134.158.89.218 on Tue Oct 18 14:25:09 2016 | Not Fixed | Shift summary | Prise de donnees |
|
test de log | | jeudi 18 octobre
il faudrait mettre un place un
canevas type pour un point de fonctionnement |
|
|
Draft
|
Thu Apr 8 21:14:09 2021 |
Entered by talour from 134.158.205.2 on Thu Apr 8 21:11:41 2021 | Fixed | Shift summary | Prise de donnees |
|
| | |
|
|
22
|
Tue Jun 8 17:27:35 2021 |
Entered by Sophie Chance from 134.158.195.144 on Tue Jun 8 17:27:21 2021 | Under Process | Info | Prise de donnees |
|
HT sur modulateur et radioprotection | | Contrôle radioprotection en cours
HT = 1240V tension max, vide klystron : 1.2
uA |
|
|
26
|
Wed Jun 9 10:55:06 2021 |
Entered by bruni from 134.158.195.141 on Wed Jun 9 10:54:54 2021 | Under Process | Info | Prise de donnees |
|
| | le modulateur est en chauffe
Réglages des signaux RF
avec le scope |
|
|
28
|
Wed Jun 9 14:03:09 2021 |
Entered by bruni from 134.158.195.141 on Wed Jun 9 14:02:53 2021 | Under Process | Shift summary | Prise de donnees |
|
| | Repérage des chaines de mesures
RF : atention, les coupleurs sur guides indique
une atténation réfléchie |
|
|
29
|
Wed Jun 9 14:42:25 2021 |
Entered by bruni from 134.158.195.141 on Wed Jun 9 14:42:13 2021 | Under Process | Shift summary | Prise de donnees |
|
| | On règle l'atténuateur
section à mi_course 800 pas. On règle
le zero de li/hfi/att.01-mot.01 (atténuateur |
|
|
30
|
Wed Jun 9 18:12:09 2021 |
Entered by bruni from 134.158.195.141 on Wed Jun 9 18:11:49 2021 | Fixed | Shift summary | Prise de donnees |
|
Mise en route RF +PA | | HT on, on met le PA
On met la HT à 500V, soit
128 kV de HT klystron. On mesure avec le |
|
|
33
|
Thu Jun 10 14:11:38 2021 |
Entered by bruni from 134.158.195.141 on Thu Jun 10 14:11:25 2021 | Under Process | Info | Prise de donnees |
|
Mesures puissance HF | | Pic = 139 mV : on retrouve de bonnes valeurs
de puissance après changement de cristal
! |
|
|
263
|
Wed Jan 19 10:15:38 2022 |
Entered by H Monard from 134.158.195.142 on Wed Jan 19 10:15:18 2022 | Fixed | Info | Opt | Vide | Linac Commissionning |
|
pas de faisceau aujourd'hui | | L'equipe CFP a terminé son intervention
des fuites sont présentes
sur la CFP à la remise sous vide. |
|
|
784
|
Tue Jul 25 19:15:02 2023 |
Opérateurs ThomX | Under Process | Shift summary | Opt | Ring Commissioning |
|
shift du 25 juillet 2023 | | * Démarrage de la machine par Iryna/Slava/Viktor
et démarrage cavité CFP par
Ronic/Daniele |
13x |
|
1017
|
Fri Feb 21 08:30:30 2025 |
shift crew | Under Process | Shift summary | Opt | Linac Commissionning | Ring Commissioning |
|
shift du 21 février 2025 | | 8h30 : démarrage machine en remote
(modulateur, laser, chiller/frigo, cyclage)
Nouveau |
6x |
|
Draft
|
Mon Feb 24 08:00:09 2025 |
KD VC VM | Under Process | Shift summary | Opt | Linac Commissionning | Ring Commissioning |
|
shift du 24 février 2025 | | 8h: mise en chauffe de la machine (Frigo/chiller,
laser, modulateur et cyclage aimants).
9H demarrage faisceau |
|