12
Mon May 17 11:53:35 2021
Ronic Chiche
Fixed
info
utilities
ThomX igloo
ThomX housing roof opening
Today, Yannick Petrilli removed 5 concrete
bars (5-9) from the ThomX housing roof in
order to let the optical table be installed
11
Fri Feb 26 17:04:57 2021
Ronic Chiche
Fixed
report
mechanics
ThomX igloo
Moving the optical table to the Igloo
This morning the Bovis company moved the
optical table from the optical room to the
Igloo without any problem.
9x
10
Wed Feb 24 17:35:55 2021
Ronic Chiche
Fixed
report
mechanics | vacuum | utilities
Optical room
Operations before moving the optical table
Operations before moving the optical table
from the optical room to the Igloo.
— the cavity has been filled
9
Wed Jul 1 17:00:18 2020
Ronic Chiche
Fixed
report
mechanics | vacuum
Optical room
Edge installation
19/06/2020
The first part of the edge installation
was on done by Yann and Ronic
8
Wed Nov 27 09:48:44 2019
Ronic Chiche
Fixed
info
cabling
Optical room
new circuit breaker for the UPS
A new circuit breaker has been installed
today before the UPS to fix the shutdown
issues we observed some months ago when too
6
Wed Nov 20 14:52:45 2019
Loïc Amoudry
Fixed
info
lasers and optics | vacuum
Optical room
New valve cabling and 30Hz noise PZT
The Pneumatic valves are still coming back
to "close" position.
Now the air bottle is always "open"
4
Tue Nov 19 17:55:20 2019
Ronic Chiche
Fixed
issue
mechanics | vacuum
Optical room
New valves cabling
Today, Manu and Eric changed the cavity
valves pressure system to open and close
them.
3
Fri Nov 15 14:51:54 2019
Ronic Chiche
Fixed
info
mechanics | lasers and optics | detectors and electronics
Optical room
Smaract Controllers setting
Scheme of cabling of the SmarAct motors
controllers for acting on Frep and CEP.
2
Tue Oct 1 12:24:11 2019
Ronic Chiche
Fixed
issue
utilities
Optical room
Chiller of the new laser amplifier
Today, the chiller worked at 17°C during
3 hours without error, no freezing nor flow
sensor error.
1
Mon Sep 30 16:32:31 2019
Ronic Chiche
Fixed
issue
utilities
Optical room
Chiller of the new laser amplifier
We observed 2 issues for the chiller of
the new CELIA laser amplifier:
setting the water temperature