27
|
Tue Oct 19 16:38:31 2021 |
Manar Amer | Fixed | info | vacuum | ThomX igloo | Pressure On mirror Chambers | At 15h30 in
the afternoon, the pressure on the mirror
chambers is: |
|
|
28
|
Wed Oct 20 10:51:29 2021 |
Manar Amer | Fixed | info | vacuum | ThomX igloo | Pressure On mirror Chambers | At 10h in
the morning, the pressure on the mirror chambers
is: |
|
|
29
|
Thu Oct 21 09:45:03 2021 |
Manar Amer | Fixed | info | vacuum | ThomX igloo | Pressure On mirror Chambers | At 9h30 in
the morning, the pressure on the mirror chambers
is: |
|
|
40
|
Thu Feb 10 09:41:54 2022 |
Ronic Chiche | Fixed | info | cabling | ThomX igloo | Power supplies switched off | This afternoon, an electrical operation
will be done in ThomX, impacting possibly
the casemate power supplies. |
|
|
10
|
Wed Feb 24 17:35:55 2021 |
Ronic Chiche | Fixed | report | mechanics | vacuum | utilities | Optical room | Operations before moving the optical table | Operations before moving the optical table
from the optical room to the Igloo.
— the cavity has been filled |
|
|
34
|
Thu Nov 4 12:42:38 2021 |
Ronic Chiche | Fixed | info | vacuum | ThomX igloo | Opening of the FP cavity valves | as the vacuum level was good enough, I
asked Eric Mistretta to open the 2 valves
of the FP cavity. |
|
|
35
|
Mon Nov 8 14:50:45 2021 |
Ronic Chiche | Fixed | info | vacuum | ThomX igloo | Opening of the FP cavity valves | On Friday the 5th of November, ThomX suffered
again from a power breakdown.
all the pumping systems had to |
|
|
38
|
Tue Jan 11 10:32:45 2022 |
Manar Amer | Fixed | report | lasers and optics | ThomX igloo | One Five laser moved | The One Five laser and
its controller have been moved from PLIC
to ThomX Iglo. |
|
|
4
|
Tue Nov 19 17:55:20 2019 |
Ronic Chiche | Fixed | issue | mechanics | vacuum | Optical room | New valves cabling | Today, Manu and Eric changed the cavity
valves pressure system to open and close
them. |
|
|
6
|
Wed Nov 20 14:52:45 2019 |
Loïc Amoudry | Fixed | info | lasers and optics | vacuum | Optical room | New valve cabling and 30Hz noise PZT | The Pneumatic valves are still coming back
to "close" position.
Now the air bottle is always "open" |
  |
|
11
|
Fri Feb 26 17:04:57 2021 |
Ronic Chiche | Fixed | report | mechanics | ThomX igloo | Moving the optical table to the Igloo | This morning the Bovis company moved the
optical table from the optical room to the
Igloo without any problem. |
9x |
|
23
|
Mon Oct 18 15:15:26 2021 |
Manar Amer | Fixed | report | cabling | software | ThomX igloo | Motors Controler and Software |
When connecting
the Ethernet cable from the hub to the computer,
it must be connected to the correct one (shown |
  |
|
36
|
Tue Nov 16 15:23:22 2021 |
Manar Amer | Fixed | report | utilities | ThomX igloo | Iris Mounts on Cavity Windows | In order to find the Alignment of the ThomX
cavity, Yann built mounts that could be placed
directly on the windows outside the cavity, |
  |
|
37
|
Fri Nov 19 16:33:29 2021 |
Manar Amer | Fixed | report | utilities | ThomX igloo | Iris Mounts on Cavity Windows | The new iris mounts fixed on the small
cavity windows.
Need additional 2 irises. |
 |
|
20
|
Fri Oct 15 17:57:54 2021 |
Ronic Chiche | Fixed | info | mechanics | lasers and optics | vacuum | detectors and electronics | cabling | software | ThomX igloo | Installation update | This afternoon with Manar, we finished
connecting FP-cavity mirrors motors and alignment
mirrors motors to their 3 ISP controllers. |
|
|
21
|
Mon Oct 18 09:46:14 2021 |
Ronic Chiche | Fixed | info | mechanics | lasers and optics | vacuum | detectors and electronics | cabling | software | ThomX igloo | Installation update | after the WE, the right vessel vacuum level
is 1.7e-7 mbar (primary + turbo pumps)
and the left vessel vacuum level |
|
|
22
|
Mon Oct 18 15:01:07 2021 |
Ronic Chiche | Fixed | info | mechanics | lasers and optics | vacuum | detectors and electronics | cabling | software | ThomX igloo | Installation update | Now, both vessels are pumped by an ionic
pump (both Turbo pumping entrances have been
closed). |
|
|
9
|
Wed Jul 1 17:00:18 2020 |
Ronic Chiche | Fixed | report | mechanics | vacuum | Optical room | Edge installation | 19/06/2020
The first part of the edge installation
was on done by Yann and Ronic |
|
|
13
|
Thu Jun 10 16:55:37 2021 |
Ronic Chiche | Fixed | info | mechanics | ThomX igloo | Connecting the optical table to the ThomX ring | On the 19th of May, the optical table has
been moved inside the ThomX concrete housing
and connected to the Symetrie hexapod and |
  |
|
16
|
Thu Oct 14 15:08:56 2021 |
Ronic Chiche | Fixed | info | detectors and electronics | utilities | ThomX igloo | Cleaning, Motors Controllers mini-rack, hexapod controller, chiller and vacuum | This morning with Manar, we started to
clean the floor around the cavity, the outside
part of the panels of the housing, and the |
|