23
|
Mon Oct 18 15:15:26 2021 |
Manar Amer | Fixed | report | cabling | software | ThomX igloo | Motors Controler and Software |
When connecting
the Ethernet cable from the hub to the computer,
it must be connected to the correct one (shown |
  |
|
24
|
Tue Oct 19 10:43:42 2021 |
Manar Amer | Fixed | info | vacuum | ThomX igloo | Vacuum pressure to open valves | The pressure for the mirror vacuum chambers
needs to be ~ few 10^-9 mbar for the valves
to be open to the electron ring (the rest |
|
|
25
|
Tue Oct 19 11:06:03 2021 |
Manar Amer | Fixed | info | vacuum | ThomX igloo | Pressure On mirror Chambers |
At
10h45 in the morning, the pressure on the |
|
|
26
|
Tue Oct 19 12:46:40 2021 |
Manar Amer | Fixed | info | vacuum | ThomX igloo | Vacuum pressure to open valves | Reminding: the opening of the valves is
the responsibility of the vacuum group only.
|
|
|
27
|
Tue Oct 19 16:38:31 2021 |
Manar Amer | Fixed | info | vacuum | ThomX igloo | Pressure On mirror Chambers | At 15h30 in
the afternoon, the pressure on the mirror
chambers is: |
|
|
28
|
Wed Oct 20 10:51:29 2021 |
Manar Amer | Fixed | info | vacuum | ThomX igloo | Pressure On mirror Chambers | At 10h in
the morning, the pressure on the mirror chambers
is: |
|
|
29
|
Thu Oct 21 09:45:03 2021 |
Manar Amer | Fixed | info | vacuum | ThomX igloo | Pressure On mirror Chambers | At 9h30 in
the morning, the pressure on the mirror chambers
is: |
|
|
30
|
Thu Oct 21 18:31:11 2021 |
Manar Amer | Fixed | info | vacuum | ThomX igloo | Pressure On mirror Chambers Leckage Test | Leakage test done in the afternoon.
The method :
an atomic mass spectrometer |
 |
|
31
|
Fri Oct 22 17:36:05 2021 |
Manar Amer | Fixed | info | vacuum | ThomX igloo | Pressure On mirror Chambers Plot | A plot showing the descend of the vacuum
in the mirror chambers (data to plot it obtained
yesterday evening) |
|
|
32
|
Tue Oct 26 09:20:01 2021 |
Manar Amer | Fixed | info | vacuum | ThomX igloo | Pressure On mirror Chambers Plot | During the weekend 23-24th of October,
the lab and ThomX suffered a power breakdown.
All the pumping systems had to restart. |
|
|
33
|
Wed Oct 27 09:34:04 2021 |
Manar Amer | Fixed | info | vacuum | ThomX igloo | Pressure On mirror Chambers Plot | Pressure is 1.4e-9 and 2.6e-9 mbar this
morning.
|
|
|
34
|
Thu Nov 4 12:42:38 2021 |
Ronic Chiche | Fixed | info | vacuum | ThomX igloo | Opening of the FP cavity valves | as the vacuum level was good enough, I
asked Eric Mistretta to open the 2 valves
of the FP cavity. |
|
|
35
|
Mon Nov 8 14:50:45 2021 |
Ronic Chiche | Fixed | info | vacuum | ThomX igloo | Opening of the FP cavity valves | On Friday the 5th of November, ThomX suffered
again from a power breakdown.
all the pumping systems had to |
|
|
36
|
Tue Nov 16 15:23:22 2021 |
Manar Amer | Fixed | report | utilities | ThomX igloo | Iris Mounts on Cavity Windows | In order to find the Alignment of the ThomX
cavity, Yann built mounts that could be placed
directly on the windows outside the cavity, |
  |
|
37
|
Fri Nov 19 16:33:29 2021 |
Manar Amer | Fixed | report | utilities | ThomX igloo | Iris Mounts on Cavity Windows | The new iris mounts fixed on the small
cavity windows.
Need additional 2 irises. |
 |
|
38
|
Tue Jan 11 10:32:45 2022 |
Manar Amer | Fixed | report | lasers and optics | ThomX igloo | One Five laser moved | The One Five laser and
its controller have been moved from PLIC
to ThomX Iglo. |
|
|
39
|
Wed Jan 19 18:32:47 2022 |
Ronic Chiche | Fixed | info | cabling | ThomX igloo | new power supplies connexions | this afternoon with Viktor, we redid all
the power supplies connexions.
4x cables are now connected to |
|
|
40
|
Thu Feb 10 09:41:54 2022 |
Ronic Chiche | Fixed | info | cabling | ThomX igloo | Power supplies switched off | This afternoon, an electrical operation
will be done in ThomX, impacting possibly
the casemate power supplies. |
|
|
41
|
Thu Feb 10 15:08:41 2022 |
Ronic Chiche | Fixed | info | mechanics | lasers and optics | ThomX igloo | shutter base plate, L-shape arm and housing frame | This afternoon with Yann:
- we changed the shutter base plate
position to center the beam axis with the |
|
|
42
|
Tue Mar 8 12:40:00 2022 |
Ronic Chiche | Fixed | info | mechanics | ThomX igloo | Chiller installation + interlock | - this morning with Aurélien, we
filled the water tank of the chiller and
we opened the water valves (last pipes on |
|