  682   Thu Feb 16 14:57:54 2023 MJ SC Shift summaryLinac Commissionning   Pour phase section 110, pour etre aligne
sur l'axe des 3 quads Q1 Q2 Q3 
 : str1H -1.3   
 Screenshot_from_2023-02-16_15-48-39.pngScreenshot_from_2023-02-16_16-01-46.pngScreenshot_from_2023-02-16_16-18-55.png 
  683   Thu Feb 16 19:25:09 2023 Entered by Marie Jacquet from 134.158.89.45 on Thu Feb 16 19:24:54 2023Not FixedUrgentDiag   Voila en pj le status de cette semaine
sur les calib LINAC BPM et Yag

Calib BPM LI BPMTL1 YAGTL1
 calib-bpm-yag.pdf 
  724   Thu Mar 30 17:20:43 2023 Entered by Marie Jacquet from 134.158.89.45 on Thu Mar 30 17:20:29 2023 Shift summaryLinac Commissionning   Shift ce matin

** YagTL1 vs soleno avec alignement
a la Kev ou a la Hayg (mais chaque fois aligne
 2023-03-30-YAGTL1_vs_Soleno.png 
  733   Tue Apr 11 22:34:19 2023 Marie Vincent Noureddine Jean-Noel Shift summaryLinac Commissionning   Debut vers 16h

Passage section avec Isol=200,
1.7 db, ph=110
  
  757   Thu May 25 15:08:18 2023 NC,IC, VM,lS Shift summaryRing   9:10 warm up modulator

10:30: cycling of magnets

10:20 : scan charge phase
 ring_storage_quality__2023_05_25_15_10_phase_scan_frm_1000_atx300_to_2500_at_x360.pngring_storage_quality__2023_05_25_15_31_phase_scan_from_0_atx300_to_250_atx3230_30kV.pngring_storage_quality__2023_05_25_15_39_phase_scan_from_0_atx4320_to_2500_atx4470_35kV.png 
  Draft   Tue Oct 10 13:46:06 2023 KD MJ Shift summary        
  829   Tue Jan 16 09:00:27 2024 MJ et SC Shift summaryLinac Commissionning   9h Mise en chauffe modulateur et refroidissements

Démarrage ampli laser

9h07 fermeture casemate
 2024-01-16_10-49-54_yag_bpm_LI.png2024-01-16_13-25-52_charges.png2024-01-16_13-28-26_bpmTL2.png2024-01-16_14-37-22-TLbpm.png 
  872   Fri May 31 08:08:56 2024 M EK, IC, DN, SC Under ProcessLinacLI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning   8h10 : Impossible de mettre en chauffe
le modulateur via IHM

En local également impossible
 6x 
  Draft   Fri Sep 27 10:44:50 2024 MJ VC  Linac Commissionning       
  936   Mon Oct 7 09:31:13 2024 Entered by Super Team from 134.158.195.141 on Mon Oct 7 09:30:50 2024FixedInfoLinac Commissionning   pression SF6: 2.3 bar

(nb: redémarrage pc modulateur
demain mardi 8/10 à 9h00)
  
  942   Wed Oct 23 17:30:58 2024 Entered by Super Team from 134.158.195.141 on Wed Oct 23 17:27:14 2024Under ProcessShift summaryLinac Commissionning   Gun phase 50 dg., At 0.5 dB; Sect phase
230 dg. At 2.65 dB; Sol. 220 A, Gun charge
-131 pC, Linac -112 pC, TL  -120 pC.
 DispersionTLBPM2.png 
  950   Wed Oct 30 11:33:04 2024 VM, IC, VKUnder ProcessInfoLI | TL | LE | Ring   9h25 Start ThomX

11h20 HV on, linac RF OK, but there
is no laser on the cathode. Trying to fix.
 6x 
  955   Thu Nov 7 08:53:22 2024 IC, VK, VM, JNUnder ProcessShift summaryRing   8h50 Start of the modumator and all subsystems

PC client 1 was frozen => we
restarted
 6x 
  960   Thu Nov 14 08:33:34 2024 Entered by Super Team from 134.158.195.141 on Thu Nov 14 08:33:03 2024Under ProcessInfoLinac Commissionning   08h30 Start ThomX

10h00 HV is 'ON'

11h03 RF Gun phase 230 dg. Att.
 15x 
  965   Thu Nov 21 08:27:15 2024 VM Entered by Super Team from 134.158.195.141 on Thu Nov 21 08:26:43 2024Under ProcessInfoRing Commissioning   08H25 Start ThomX

09H45 HV is 'ON'

09h49 Breakdown in the RF Gun
  
  Draft   Thu Nov 28 08:19:05 2024 VM, IC, VK Under ProcessInfoRing Commissioning   08h18 Start ThomX

10h00 HV is 'ON'

10h35 RF Gun phase is 174 dg. Section
  
  974   Thu Dec 5 08:31:34 2024 VM Entered by Super Team from 134.158.195.141 on Thu Dec 5 08:31:12 2024Under ProcessShift summaryRing Commissioning   08h28 Start ThomX

08h40 Some magnets remain switched
off. Cycling was not performed
  
  975   Fri Dec 6 08:24:36 2024 VM, IC, VK, HG Under ProcessShift summaryRing Commissioning   08h25 Start ThomX

09h55 HV is 'ON'

10h18 RF Gun Phase is 159 dg. Sect.
 8x 
  980   Fri Dec 13 08:22:36 2024 VM, IC, VKUnder ProcessShift summaryRing Commissioning   08h23 Start ThomX

09h40 HV is 'On'

10h24 RF Gun Phase 183 dg. Sect.
 Screenshot_from_2024-12-13_11-28-46.pngScreenshot_from_2024-12-13_14-44-28.pngScreenshot_from_2024-12-13_14-46-59.png 
  Draft   Thu Dec 19 11:10:03 2024 IC, VK, VMUnder ProcessShift summaryRing Commissioning   11h05 Start ThomX

11h50 BPM02-Libera04 wiring has
been checked: 'OK' 
  