  Toutes les notes concernant les Commissionning de ThomX, Page 54 of 62  Not logged in ThomX    logo
ID Date Authordown Status Type Category Important Subject Icon Text Attachments
  686   Sat Feb 18 14:37:40 2023 Entered by Marie Jacquet from 134.158.205.50 on Sat Feb 18 14:37:01 2023 Shift summaryLinac Commissionning Comparaisons mesures-simuls ASTRA versus I_Soleno - Complements elog 676 et 681 En pj  2023-02-18-elog.pdf 
  Draft   Wed Mar 8 11:45:46 2023 Entered by Marie Jacquet from 134.158.205.47 on Wed Mar 8 11:45:31 2023    I-dipole vs X_TLBPM02 - Mesures/Simul (suite elog 28 fev) Tue Feb 28 08:48:29
2023

8H50-demarrage chiller et chauffage
  
  708   Wed Mar 8 11:47:20 2023 Entered by Marie Jacquet from 134.158.205.47 on Wed Mar 8 11:45:31 2023 Shift summaryLinac Commissionning (suite elog 28 fev) data X_TLBPM02 vs I_Dipole - Plot Mesures/Simul  Tue Feb 28 08:48:29
2023

8H50-demarrage chiller et chauffage
 2023-02-28-I_Dip_vs_X_TLBPM02.png 
  591   Fri Oct 14 12:59:34 2022 Entered by Marie Jacquet from 134.158.205.43 on Fri Oct 14 12:59:10 2022 InfoLinac Commissionning Schema position elements LINAC Demande par plusieurs personnes, je vous
transmets ici mon schema de la position des
elements dans le LINAC
 LINAC-position-elements.bmp 
  623   Fri Nov 4 11:56:48 2022 Entered by Marie Jacquet from 134.158.205.43 on Fri Nov 4 11:56:17 2022Not FixedShift summaryLinac Commissionning Mesures BPM et YAG vs Steerers - 17/10, 24/10 et 26/10 Ci-joint le bilan BPM
et YAG vs steerer de 3 jours differents :
le 17 le 24 et le 26 octobre
 2022-11-04-BPM-YAG-STR.pdf 
  1024   Fri Feb 28 00:32:21 2025 Entered by Marie Jacquet from 134.158.205.38 on Thu Feb 27 23:45:19 2025 Shift summaryLI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning 27 fevrier (visite Alberto Paola Luca)  ** Nouvelle
prise d'images pour determiner les distortions
du det :
  
  556   Fri Sep 16 16:39:55 2022 Entered by Marie Jacquet from 134.158.205.33 on Fri Sep 16 16:39:35 2022 Shift summaryLinac Commissionning shifts des 12 et 13 septembre - axes MAG vs BPM_TL et YAG_TL Données prises les 12 et
13 septembre

Très faible charge (<10
  
  Draft   Fri Sep 16 16:13:55 2022 Entered by Marie Jacquet from 134.158.205.33 on Fri Sep 16 16:13:31 2022 Shift summaryLinac Commissionning       
  1030   Thu Mar 6 10:38:31 2025 Entered by Marie Jacquet from 134.158.205.25 on Thu Mar 6 10:37:50 2025 Shift summaryLI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning Programme de la journee : preparation des valeurs a remplir  1 : Alignement Axe
Q1-Q3 avec SCRIPT - Conditions
 Compare_Align_ALL.pngTrend_Position_Yag_Sautes.pngJauges_2025-03-06_18-47-14.png2025-03-06-Q1Q3_Q4Q5.pdf 
  1116   Tue Sep 9 15:19:47 2025 Entered by Marie Jacquet from 134.158.205.21 on Tue Sep 9 15:19:28 2025FixedShift summaryLI | TL | LE | Ring X-rays - Recherche on-axis avec script fwhm - Prise de qq spectres - Mesure taille source ** spectre CdTe avec feuille Au (pour calib)

** Utilisation du script FWHM des
spectres, mapping 2D - Enregistrment spectres
  
  1087   Wed Jun 11 08:46:58 2025 Entered by Marie Jacquet from 134.158.205.17 on Wed Jun 11 08:46:44 2025 Shift summaryLI | Ring 2025-06-04 Fluo-spectro : Spectre du 2025-06-04    spectres_20250604.pdf 
  982   Tue Dec 17 23:26:45 2024 Entered by Marie Jacquet from 134.158.205.16 on Tue Dec 17 23:26:26 2024FixedShift summaryLI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning shift 17/12 - scan vert FPC - 50 MeV 8h10 : mise en chauffe de la machine (modulateur,
laser, frigo et chiller)

9h30: faisceau dans anneau avec
 6x 
  1042   Thu Mar 20 18:41:55 2025 Entered by Marie Jacquet from 134.158.205.16 on Thu Mar 20 18:41:39 2025 Shift summaryLI | Ring | Linac Commissionning | Ring Commissioning 19 et 20 mars - Mesures X-rays - Bravin & co 19
mars 2025

 spectre_42keV.png 
  672   Mon Feb 13 13:35:12 2023 Entered by Marie Jacquet from 134.158.195.141 on Mon Feb 13 13:34:44 2023Not FixedProblemLinac Commissionning problemes avec SST et YAGLI 1)  "Show camera" 
soit ca plante , soit ca finit par s'ouvrir
mais au bout de plusieurs minutes
 Screenshot_from_2023-02-13_13-36-34.png 
  673   Mon Feb 13 15:07:11 2023 Entered by Marie Jacquet from 134.158.195.141 on Mon Feb 13 13:34:44 2023Not FixedProblemLinac Commissionning RE: problemes avec SST et YAGLI 1) Je viens de tenter de reproduire le
problème. Il est normal que cela mette
du temps à charger, surtout au premier
  
  674   Mon Feb 13 17:07:20 2023 Entered by Marie Jacquet from 134.158.195.141 on Mon Feb 13 13:34:44 2023Not FixedProblemLinac Commissionning RE: RE: problemes avec SST et YAGLI Apres discussion avec Kevin et tests en
salle de controle:

- cela semble rapide sur client3
  
  319   Thu Feb 10 17:24:40 2022 Entered by Maher OMEICH from 78.193.58.208 on Thu Feb 10 17:24:23 2022 InfoRF D1 modulateur Bonsoir

Modulateur mis sous tension

Maher
  
  301   Mon Feb 7 18:19:49 2022 Entered by Maher OMEICH from 78.193.58.208 on Mon Feb 7 18:19:11 2022 InfoRF D1 modulateur Début de l'intervention de Scandinova
sur le modulateur ce matin

modification dans le soft du modulateur,
  
  72   Wed Sep 22 16:15:32 2021 Entered by Maher OMEICH from 134.158.91.212 on Wed Sep 22 16:15:04 2021Not FixedLinacLinac Commissionning   J'ai encore le problème avec
le modulateur même après une
modification suggérée par Scandinova
  
  410   Wed Mar 23 11:10:16 2022 Entered by Maher OMEICH from 134.158.91.212 on Wed Mar 23 11:09:58 2022 Shift summaryLinac Commissionning   10h40 Démarrage modulateur et chillers,
casemate encore ouverte à fermer vers
midi
  