  991   Thu Jan 9 10:31:11 2025 Entered by Nicolas Delerue from 134.158.195.144 on Thu Jan 9 10:30:34 2025Not FixedProblemCC DS ThomX_PhotoCathode using a lot of CPU 

The load on client5 is 29 making all operations slow.

Appently the DS ThomX_PhotoCathode is using a lot of CPU, slowing the rest.

 

 

  963   Fri Nov 15 12:13:42 2024 Entered by Nicolas Delerue from 134.158.195.144 on Fri Nov 15 12:13:26 2024Not FixedInfoTL Charge excess in the TL 

By looking at the BPM transmission tool one can see that there is more charge on TL/BP.03 than on TL/BPM.02 (see attached image).

The BPM seetings have been checked and they are similar.

One can see a similar effect when comparing TL/ICT.01 and TL/ICT.02.

Possible interpretation: the beam is scrapping the beam pipe and creating a shower of secondaries.

  821   Tue Nov 21 14:29:01 2023 Entered by Nicolas Delerue from 134.158.195.142 on Tue Nov 21 14:28:47 2023 Shift summaryDiag Prise de donnees 21/11 

13:57 Mise en chauffe

15:00 Faisecau

Tests sur les ecrans

17:00 Arret

  680   Thu Feb 16 10:52:11 2023 Entered by Nicolas Delerue from 134.158.195.142 on Thu Feb 16 10:51:56 2023FixedInfoLinac Commissionning Health check  

Les erreurs severes dans health check ont ete resolues.

La plupart etaient solvable en suivant les instructions donnees par health check.

La seule erreur plus compliquee etait sur TL/PS/DPI ou il a fallu aller valider (ack) l'erreur en local.

=> les operateurs sont encourages a regarder  health_check et suivre les instructions pour faire disparaitre les erreurs rouges (qui peuvent etre des problemes serieux) ou alors les signaler aux responsables des sous-systemes concernes.

 

  696   Fri Feb 24 16:24:15 2023 Entered by Nicolas Delerue from 134.158.195.142 on Fri Feb 24 16:24:00 2023FixedShift summaryDiag Shift 24/2 

13:30 Mise en chauffe

14:30 Demarrage faisecau

Test de modifications de diverses interfaces.

17:00 Arret machine

  987   Fri Dec 20 14:00:06 2024 Entered by Nicolas Delerue from 134.158.195.142 on Fri Dec 20 13:59:52 2024Not FixedProblemInfra Alarme sur les rondes 

A 13h30 j'ai tent'e de faire un acces controle dans la casemate.

Quand j'ai pris la 1ere clef une alarme (son inhabituel) s'est declenchee au niveau de la fosse sud avec un chenillard rouge sur les verrines (fooses nord, sud et klystron).

J'ai appele le SPR comme explique hier.

Je suis tombe sur un repondeur...

Jean-Noel a tourne des clefs sur le PSS et l'alarme s'est arretee.

Plusieurs rondes sont tombees.

  243   Tue Jan 11 19:30:19 2022 Entered by Nicolas Delerue from 134.158.195.141 on Tue Jan 11 19:30:03 2022FixedFixSY Pb declenchement scope synchro 

La frequence des diags etait reglee a 0.1Hz et le scope de la salle de controle se declenchait sur les diags. C'est pour cela que le scope se declenchait toutes les 10s.

Les signaux en salle de controle ont une longueur de 10ms mais ceux distribues ont les largeurs demandees (20us et 10us respective,ent pour les signaux klystron)

J'ai verifie les reglages des signaux de declenchement du Klystron (generateur 1, canaux 9 et 10). Nous sommes aux memes reglages (retard, amplitude et largeur) que dans la recette du 17/11.

 

  417   Thu Mar 24 17:12:01 2022 Entered by ND/VC/HG/SC from 134.158.195.142 on Thu Mar 24 17:11:44 2022Reference SolutionLinacLinac Commissionning Paramètres Faisceau 

Alignement laser

On retrouve la phase pour la charge max phi = 313 degres (consigne chiller canon = 31.25 degres)

On enlève 40 degres à la phase de charge max pour arriver à la phase d'énergie maximum phi = 273 degres

On focalise le faisceau avec la bobine de sortie canon I = 170 A

On peut l'observer sur la camera LI/DG/SST.01

On passe ensuite la section phi section = 100 degres (consigne chiller section 28.95 degres)

On met du courant dans le steerer avant section LI/PS/STR.02-V.01 I = 0.83A et LI/PS/STR.02-H.01 I = -0.90A

On observe sur TL/DG/SST.01

On peut observer les trends des ICTs avec taurus plot er/ca/rac.05-elr.01_wac.02/ch0 pour ICT1

  416   Thu Mar 24 15:41:18 2022 Entered by ND/VC/HG/SC from 134.158.195.142 on Thu Mar 24 15:41:04 2022FixedLinacLinac Commissionning Alignement laser 

Position moteur M4 avant alignement laser :

x = 380 et y = 5373

Position moteur M4 après alignement laser :

x = 580 et y = 5373

Image laser avant (prise par Hayg) =

Image laser après =

 

  484   Tue Jun 21 09:58:30 2022 Entered by ND/SC from 134.158.195.141 on Tue Jun 21 09:58:15 2022Under ProcessLinacAimants Demarrage et faisceau 

9h45 Mise en chauffe modulateur. Test interface générale Nicolas pour l'allumage du modulateur.

11h00 Cyclage dipole anneau en cours. Cyclage TL/PS/DP.01 impossible. External error.

11h18 Mise en route chillers via interface generale pour tests

11h30 Allumage faisceau

11h50: Perte modulateur

11h54: retour faisceau; -6 deg phase

11h56: Pas de 1 degree ajoutees dans l'interface de Phase et git pull effectue

11h59: Perte modulateur; Nouvelle phase 14512h09: Demarrage dipoles anneau

Position faisceau I(RI-C1/PS/DP)=0A
Position faisceau I(RI-C1/PS/DP)=200A
Position faisceau I(RI-C1/PS/DP)=250A
Position faisceau I(RI-C1/PS/DP)=270A
Position faisceau I(RI-C1/PS/DP)=0A

Observation: un courant de plus de 200A dans RI-C1/PS/DP.01 perturbe le faisceau dans le linac.

L'effet semble apparaitre entre 170A et 190A.

12:53 Cyclage RI_C1/PS/DP.01

13h15 Alignement laser ( RI_C1/PS/DP.01 current = 168A)

14h45 Mesures effet dipole anneau sur faisceau linac

15h04 Cyclage RI_C1/PS/DP.01220

15h26 passage section COL02 = 190A visu sur écran TL/DG/SST.01 avec guidage

15h27 fin du cyclage, Prise de données sur LI/DG/SST.01 pour différents ampérages de RI_C1/PS/DP.01 avec COL02 = 220A COL.01 = 63.58A.

Scan à énergie max :

Scan a charge max sans solenoides :

(Unit'es de deplacement [axe vertical] a confirmer)

16h31 Transport jusqu'à la Faraday Cup de la TL avec les dipoles de l'anneau allumés à 170A

STR.02-V.01 = +0.4A et STR.02-H.01 = -0.8A, COL.02 = 205A, image SST 16h34, phase energie max = 93 degres.

16h56 Arret machine

 

 

 

 

 

 

 

 

 

 

 

  487   Fri Jun 24 11:11:58 2022 Entered by ND/SC from 134.158.195.141 on Tue Jun 21 09:58:15 2022Under ProcessLinacAimants RE: Demarrage et faisceau 

La même chose avec le signal des BPM en plus.

Entered by ND/SC from 134.158.195.141 on Tue Jun 21 09:58:15 2022 wrote:

9h45 Mise en chauffe modulateur. Test interface générale Nicolas pour l'allumage du modulateur.

11h00 Cyclage dipole anneau en cours. Cyclage TL/PS/DP.01 impossible. External error.

11h18 Mise en route chillers via interface generale pour tests

11h30 Allumage faisceau

11h50: Perte modulateur

11h54: retour faisceau; -6 deg phase

11h56: Pas de 1 degree ajoutees dans l'interface de Phase et git pull effectue

11h59: Perte modulateur; Nouvelle phase 14512h09: Demarrage dipoles anneau

Position faisceau I(RI-C1/PS/DP)=0A
Position faisceau I(RI-C1/PS/DP)=200A
Position faisceau I(RI-C1/PS/DP)=250A
Position faisceau I(RI-C1/PS/DP)=270A
Position faisceau I(RI-C1/PS/DP)=0A

Observation: un courant de plus de 200A dans RI-C1/PS/DP.01 perturbe le faisceau dans le linac.

L'effet semble apparaitre entre 170A et 190A.

12:53 Cyclage RI_C1/PS/DP.01

13h15 Alignement laser ( RI_C1/PS/DP.01 current = 168A)

14h45 Mesures effet dipole anneau sur faisceau linac

15h04 Cyclage RI_C1/PS/DP.01220

15h26 passage section COL02 = 190A visu sur écran TL/DG/SST.01 avec guidage

15h27 fin du cyclage, Prise de données sur LI/DG/SST.01 pour différents ampérages de RI_C1/PS/DP.01 avec COL02 = 220A COL.01 = 63.58A.

Scan à énergie max :

Scan a charge max sans solenoides :

(Unit'es de deplacement [axe vertical] a confirmer)

16h31 Transport jusqu'à la Faraday Cup de la TL avec les dipoles de l'anneau allumés à 170A

STR.02-V.01 = +0.4A et STR.02-H.01 = -0.8A, COL.02 = 205A, image SST 16h34, phase energie max = 93 degres.

16h56 Arret machine

 

 

 

 

 

 

 

 

 

 

 

 

  472   Tue Jun 7 09:53:01 2022 Entered by ND/JNC/VC/VS/MO/SC from 134.158.195.141 on Tue Jun 7 09:52:47 2022Under ProcessLinacLinac Commissionning Etat des lieux 

Presents: SC, ND, JNC, VS, MO

Fermeture casemate

Tests des DSs en cours

Fosse Nord ouverte

Démarrage Laser en cours

11h Fermeture machine, mise en chauffe modulateur, mise en route chillers

11h07 cyclage aimants anneaux début

ATKPanel des alimentations des solenoides ne s'ouvre pas

12:16 Resistivite de l'eau incorrecte; Arret des tests de cyclage

12:30 Resistivite de l'eau: 866Mo

13h34 : Arret chauffage modulateur

Reprise prévue à 14h30 pour voir où en est la valeur de la résistivité de l'eau

15h33 La résistivité de l'eau n'est pas encore bonne Nous arretons la machine.

 

 

  5   Tue Dec 1 09:57:09 2020 Entered by Moutardier from 134.158.76.123 on Tue Dec 1 09:56:35 2020 Inforesumes Verrification pour le démarrage a blanc 

Verification de l'état de la Synchro : OK, tout les signaux sont en trigger externe.

Verification de l'état des diagnostiques :
- Libera 3 : n'est pas encore cofiguré (pas génant pour le démarrage a blanc)
- Caméra TL/DG/SST.03-CCD.01 : débranché (pas génant pour le démarrage a blanc)
- Moteur des fentes (TL/DG/SRH.01-MoG.01 et TL/DG/SRH.01-MoG.02) éteint (pas génant pour le démarrage a blanc)
-> OK pour le démarrage a blanc

  223   Thu Dec 16 14:58:50 2021 Entered by Moutardier Alexandre from 91.168.92.148 on Thu Dec 16 14:58:26 2021 ProblemAimants | Linac Commissionning Alimentation en état FAULT !!! 

D'après health_check toutes les alimentations electrique des solenoides, deviateur et quadrupole sont en état FAULT.

Est ce que quelqu'un présent sur place pourrait aller voir pourquoi ?

  221   Thu Dec 16 10:40:03 2021 Entered by Moutardier Alexandre from 91.168.92.148 on Thu Dec 16 10:39:49 2021 InfoCC test en ssh 

Connection ssh sur client4 pour tester une modification de health_check

  222   Thu Dec 16 14:57:31 2021 Entered by Moutardier Alexandre from 91.168.92.148 on Thu Dec 16 10:39:49 2021 InfoCC RE: test en ssh 

Modifications faites, testées et fonctionnelles.

Entered by Moutardier Alexandre from 91.168.92.148 on Thu Dec 16 10:39:49 2021 wrote:

Connection ssh sur client4 pour tester une modification de health_check

 

  237   Mon Jan 10 09:27:14 2022 Entered by Moutardier Alexandre from 193.55.29.170 on Mon Jan 10 09:26:50 2022 FixDiag | CC | Linac Commissionning Automatique "health check" 

Allumage de client 5. Pourquoi était-il éteint sachant qu'il y a des ds qui doivent tourner dessus ?

Lancement du processus de mise a jour automatique de l'état de la machine (health_check) sur client 5.
En cas de soucis le bouton "Force update" permet de lancer une procédure de verification de l'état de la machine manuellement.

(Un pull sur /data/sharde/... a été fait pour prendre en compte de très vieille modification de l'IHM)

Démarrage du ds CALC pour les mesures de charge (CALC/ICT/Charge_...)

Erreur vanne jauge aquité

WaveCatcher en état FAULT -> Discussion avec Irayna et Slava pour les remettrent en état.

Le seul autre equipement avec un "problème" est le laser qui est éteint. Viktor est la est doit l'allumer.

  543   Fri Sep 9 18:26:51 2022 Entered by Moutardier Alexandre from 134.158.195.145 on Fri Sep 9 18:26:38 2022 InfoDiag First injection in the ring  

Injection dans l'anneau.

Signaux sur les 5 premier BPM de l'anneau without kicker.
(Attention, le premier BPM vu par le faisceau est RI-C1/DG/BPM.02)

  121   Tue Oct 26 15:19:17 2021 Entered by Moutardier Alexandre from 134.158.195.144 on Tue Oct 26 15:18:59 2021 InfoRF D1 Image PIC PBC photodiode a l'oscilloscope en salle de controle 

Attenuateur RF canon : 0.25 dB

Orange : Photodiode
Vert : PBC
Jaune : PIC

  194   Tue Nov 30 17:11:41 2021 Entered by Moutardier Alexandre from 134.158.195.144 on Tue Nov 30 17:11:17 2021FixedProblemCC Problème pc client2 

Le client 2 a freeze.
Il était impossible de fermer les intefaces ouverte, d'ouvrir un nouveau terminal, de ce déconnecter ...
Parfois il fasait in bruit similaire a celui qu'on n'a lorsque l'on reste appuyé sur la touche retour sur un terminal.
J'ai essayer de me connecter depuis un autre client et la connection ssh ne voulais pas ce faire non plus.

Le pc a était éteint de force. Il semble refonctionner maintenant.