ID Date Author Status Type Category Important Subjectdown Icon Text Attachments
  220   Thu Dec 16 09:53:38 2021 Entered by Super Team from 134.158.195.141 on Thu Dec 16 09:53:20 2021Under ProcessShift summarySY | Linac Commissionning Demarage machine Les chillers sont démarrés
et le modulateur en chauffe

Test de l'influence sur les
  
  1061   Tue Apr 29 11:03:14 2025 Entered by Super Team from 134.158.195.141 on Tue Apr 29 11:02:38 2025Under ProcessInfoLI | TL Data taking for ML  Demarrage ACQ pour ML 

Random : Phi_GUN, Phi_Section,
ST1, ST2, Solenoid, QP1, QP2, QP3 
  
  835   Fri Jan 26 09:36:01 2024 ND, Anna K, Elene K Shift summaryLI | TL | LE Data taking 26/01 9:30 Warm-up

11:00 Modulator OFF => restart
warm-up
 7x 
  1072   Mon May 19 17:57:15 2025 Entered by Super Team from 134.158.195.141 on Mon May 19 17:56:57 2025Under ProcessInfoLI | TL Data : Sole scan, Q scan, random linac Yag_TL1 Today's data :
- coil scan (+ images)
- Q3 scan
  
  77   Wed Sep 29 17:03:32 2021 Entered by Super Team from 134.158.195.143 on Wed Sep 29 16:57:52 2021Under ProcessLinacLinac Commissionning Dark current Pemiere image du courant d'obscurité. 

L'image
est prise sur la station SST01 du Linac.
 First_DarkCurrent.tif 
  35   Fri Jun 11 18:47:23 2021 HaygReference SolutionLinacRF D1 DS pour les températures des chillers icon1.gif Listes des Ds pour les températures
des chillers


GUN : ER/HF/RAC.17-API.AI1/
  
  124   Wed Oct 27 16:48:50 2021 Entered by Super Team from 134.158.195.141 on Wed Oct 27 16:48:32 2021Not FixedUrgentCC | Linac Commissionning DS calc en défaut Les DS CALC sont en défaut et impossible
de les relancer sur client3. Ils n'apparaissement
pas dans astor.
  
  991   Thu Jan 9 10:31:11 2025 Entered by Nicolas Delerue from 134.158.195.144 on Thu Jan 9 10:30:34 2025Not FixedProblemCC DS ThomX_PhotoCathode using a lot of CPU The load on client5 is 29 making all operations
slow.

Appently the DS ThomX_PhotoCathode
 Screenshot_2025-01-09_10-30-03.pngScreenshot_from_2025-01-09_10-32-26.png 
  177   Tue Nov 23 13:12:37 2021 Entered by Iryna Chaikovska from 134.158.89.93 on Tue Nov 23 13:12:22 2021Under ProcessOtherAimants | Linac Commissionning Cyclage quadrupoles 23/11/2021

We would like to cycle the quadrupoles
in the linac. The procedure of the cycling
 Screenshot_2021-11-23_at_13.14.26.pngScreenshot_from_2021-11-23_14-09-27.pngScreenshot_from_2021-11-23_14-10-15.pngcylage_quad.pngcylage_quad2A.png 
  175   Tue Nov 23 10:56:50 2021 Entered by Iryna Chaikovska from 134.158.195.143 on Tue Nov 23 10:56:34 2021FixedOtherAimants | Linac Commissionning Cyclage dipole  For 22/11/2021

There is the remaining field from
the dipoles in the TL. In order to go straight
 cylage_dipole.pngScreenshot_from_2021-11-23_12-16-04.pngScreenshot_2021-11-23_at_14.40.52.png 
  407   Mon Mar 21 09:53:11 2022 Entered by Iryna Chaikovska from 134.158.195.144 on Mon Mar 21 09:52:37 2022 InfoAimants Cyclage QUAD (TL) The cycling of the following quads ( to
zero current) were tested. The corresponding
cycling cuves were loaded in the DS (checked).
  
  270   Thu Jan 20 16:01:14 2022 Emmanuel GoutierreFixedLinacAimants Conversion valeur moteur rotation solénoïde Conversion des valeurs des moteurs de rotation
du solénoïde

axmo_z
 Conversion_mm_avec_angle_de_rotation_solenoide.pdf 
  188   Thu Nov 25 17:07:29 2021 Entered by Super Team from 134.158.195.142 on Thu Nov 25 17:07:16 2021FixedLinacLinac Commissionning Contrôle terminé     
  185   Thu Nov 25 15:01:54 2021 Entered by Super Team from 134.158.195.142 on Thu Nov 25 15:01:41 2021Under ProcessLinacLinac Commissionning Contrôle Radioprotection Les controles radioprotection ont commencé
vers 14h50

Paramètres faisceau : 100
  
  893   Tue Jul 30 10:17:06 2024 M.O, M ELK, Hayg, SlavaUnder ProcessShift summaryLI | RF D1 Conditionnement section SC/ME/MO/VK/HG  signaux RF mesurés :

avec Oscillo :

orange
 Vide_Screenshot_2024-07-30_17-13-24.png 
  876   Thu Jun 6 08:29:19 2024 M EK, SC, ND, VCUnder ProcessLinacLI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning Conditionnement section 6/06 8h20 : mise en chauffe de modulateur

start frigo et chiller section

Pression SF6 2.6 bar
 1100V_3us_10Hz_attsec_16dB.png1120V_3us_10Hz_attsec_16dB.png 
  894   Wed Jul 31 09:58:14 2024 M.O, M ELK, Slava , IrynaUnder ProcessLinacLI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning Conditionnement section 31/07 signaux RF mesurés :

avec Oscillo :

orange
 image_de_splitter_.pngbreakdown_25Hz_3us_09dB_14h52.png 
  871   Thu May 30 08:36:04 2024 MEK, ND, VC, Under ProcessLinacLI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning Conditionnement section 30/05 icon8.gif 08h30: set to stanby modulator

start frigo & chiller section

start cond. @ 2 dB ( Pis= 16 MW)
 1.5_dB_2µs_5Hz_RF_breakdown.png1.1dB_2µs_5Hz_RF_breakdown_réseau_HF.png 
  892   Mon Jul 29 09:34:57 2024 M ELK, Slava, Iryna, HaygUnder ProcessLinacLI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning Conditionnement section 29/07 signaux RF mesurés :

avec Oscillo :

orange
 Interlock_Sec_0.2dB_10Hz_3µs_15_19.pngInterlock_Sec_0.2dB_10Hz_3µs_15_35.png 
  870   Wed May 29 08:47:44 2024 M EK, KD, DN, HGUnder ProcessLinacLI | TL | LE | Ring | Diag | Aimants | CC | Infra | Laser | Opt | RF D1 | RF Anneau | MECA | SY | Vide | Electronique | Linac Commissionning | Ring Commissioning Conditionnement section 29/05 8h45: set to standby Modulateur

start Frigo et chiller section

start cond. @ 1.4 dB ( Pis=18 MW)
 1dB_1us_5Hz_interlock.png 